This document contains responses to industry questions regarding solicitation number 12505B24Q0011 from the Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area for 80 weaned piglets. The solicitation requires piglets that are 18-21 days of age, weigh no less than 12 pounds at weaning, and must be moved directly from sow to transportation to the facility. Delivery is due by January 4, 2024, with up to one day of flexibility. Questions from industry were answered, clarifying that either male or female piglets are acceptable but mixed sex lots should be close to equal proportions, and that weight rather than strict age is considered when ordering large quantities as long as requirements are met.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQ 12505B24Q0011.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions from Industry
12505B24Q0011
80 Weaned Piglets
Q1. Does it have to be any specific sex? Male or Female?
Response: Either sex will fulfill the requirement however if providing a mixed sex lot, the sex of the piglets need to be close to equal proportion. If mixed sex the contractor shall specify the number of each sex they are quoting
Q2. Suppliers go off of weight not age when ordering such large quantities. When you were creating this Gov't SOLICITATION did they ever mention any weight causes a 21-day-old (weaned piglet) weigh between 13-15lbs we did not know if there was any weight preference - this greatly affects pricing.
Response: Piglets can be 18-21 days of age and weigh no less than 12 lb at weaning.
They must be moved directly from sow to transportation to facility.
Q3. Solicitation states by Jan 4th or near, 2024 what's the latest date to receive if any hiccups occur?
Response: Jan 4 is delivery date, +/- 1 day