Refinish Floors at NLAE (12505B22R0010) Questions and Answers through 7/01/2022

Question Answer

I saw where the drawings were posted. However, the drawings posted do not indicate which areas are to be done in order to determine dimensions. Also, the drawings posted are mechanical drawings which are not ideal for determining square footage, especially since they are not scaled drawings. Are there any floor plan drawings that have the work area marked that can be provided or a square footage amount of the work area that can be provided? There is an uploaded set of prints with square footage

Can you specify which rooms are apart of the request for quote as it is not explicitly stated in the SOW?

129, 131, 135, 141, 142, 201, 207, 209, 211, 217, 219, 221, 225, 229, 243, 247, 249, 301, 301A, 311, 317, 321, 327, 329, 335, 337, 341, 345, 345A, Can you provide a room schedule so we know which rooms are to be coated? See #2

Can you provide a cove base detail? (SOW Application)

4" vinyl trim, black 5 Is there any 3-phase power available? Yes 6 Are we able to use propane floor grinders? Yes 7 Can you provide the intended phase plan? Phasing will be discussed with contractor

Is Tennent 1/8” Full Flake System an acceptable alternative to the Stonshield QBT? (SOW Products) Yes

What rooms / halls are included in the project to receive new flooring? We received 3 drawings for the 1st – 3rd floors. Each drawing has SF amounts, but I have been unable to locate a finish schedule. Are all rooms / halls to get the new flooring or only some? If only some rooms, which ones? See #2

Refinish Floors at NLAE (12505B22R0010) Questions and Answers through 7/01/2022

Are they looking for the existing coating to be recoated over or are they looking for the existing coating to be removed to the concrete substrate and the new system installed directly to the slab? If recoat, can they confirm the existing system that is on the floor? Existing coating to be smoothed out/prepped for new flake coating.

Existing coating is a rough grit type coating. Do not need to take to slab.

Integral cove base is to match existing height. What is the existing height? Is the cove base height the same in all rooms to be serviced or does it change? If it changes, then what rooms have what heights?

See # 4

Will the project need to be performed in phases or will the entirety of the areas to be service be given to us at once?

If it needs to be done in phases, how many phases will it need to be done in and what rooms will be in each phase? Phases. Groups of labs will be available at times. Some labs will need to move to refinished labs to continue critical lab work.

There are multiple lines in the Scope of Work about patching and repairing damaged and deteriorated concrete. How large, how many and where are the damages / repairs located? Flooring is not damaged. Just need to prep surface.

Will we be able to look at the areas to be serviced before providing a service quote?

Site visits already took place per the solicitation. No additional site visits are being conducted.

END