Att. 3 Statement of Work 240819.pdf
PDF 343 KB Posted
- Attached to
- GT Maintenance Facility Complex Paving Federal contract opportunity
- Solicitation number
- 12445524Q0154
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for a federal construction project at the Grey Towers National Historic Site in Milford, Pennsylvania. The project consists of the removal and disposal of the existing asphalt surface, and the placement of new asphalt materials, including mobilization, asphalt removal and disposal, culvert cleanout, aggregate base, concrete pads, machine grading, asphalt paving, and permanent pavement markings.
The period of performance for this 30-day project is scheduled to begin upon receipt of the Notice to Proceed. The contractor must submit various items for approval, including a construction schedule, list of subcontractors and suppliers, emergency contact information, and traffic control plan, among others. The work is subject to the Davis-Bacon Act, and the U.S. Department of Agriculture, Forest Service is the contracting agency. This SOW is attached to a related federal contract opportunity that is set aside for small businesses.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Att. 1 Appendix C – FSSS 240819.pdf | ||
| 12445524Q0154 240919.pdf | ||
| Att. 2 Plan sheets combined 240819.pdf | ||
| Att. 4 Wage Determination Pike County PA 240621.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment
Project GREY TOWERS PAVEMENT PRESERVATION and REHABILITATION
General Information
1.0 Scope of Work
This project consists of removal and disposal of existing asphalt surface, and placement of new asphalt materials.
Work includes, but is not limited to mobilization, asphalt removal and disposal, culvert cleanout, aggregate base, concrete pads, machine grading, asphalt paving and permanent pavement markings.
Please note that this is a Federal Construction project and Davis Bacon wages apply. Refer to appropriate appendix for current wage determination.
A. PROJECT LOCATION
Project is located within Grey Tower National Historic Site, Pike County, Pennsylvania.
Project area 1:
Includes Service Drive access, and parking areas. See location map on plan cover sheet and attached maps.
B. PERIOD OF PERFORMANCE
The period of performance of this project is scheduled to be 30 Days.
No work may begin prior to receipt of the Notice to Proceed.
Construction of all work items shall be performed efficiently during consecutive workdays.
C. The Forest Service, US Department of Agriculture has adopted the Standard Specifications for Construction of Roads and Bridges of Federal Highway Projects, FP-14, U.S. Customary Units (FP-14) for construction of National Forest System Roads and other projects.
The full provisions of FP-14 shall apply as applicable on the construct, unless modified by these Special Project Specifications.
The full FP-14 specification documents are available online at:
https://highways.dot.gov/federal-lands/specs
The FP-14 is available in a 6 ¼” X 9 ¼” wire bound paper form. They are for sale by the U.S. Government Printing Office by contacting:
Superintendent of Documents U.S. Government Printing Office Internet: bookstore.gpo.gov Phone: (toll free) 866.512.1800 Fax: 202.512.2250 Mail: Stop SSOP, Washington, DC 20402-0001
2.0 Background
The existing paved surface at the Maintenance Facility for the National Historic Site at Grey Towers has exceeded the service life and needs repair and rehabilitation. The Grey Towers site includes multiple building and paved roads. This project is focused on the road infrastructure and begins addressing deferred maintenance.
Contractor Requirements
3.0 Technical Requirements / Tasks
See Appendix C
4.0 Government Furnished
Government shall provide access to the project locations. The contractor must coordinate construction schedule within the limits identified.
Work at the site shall be conducted between Monday through Friday, 0700 until 1700. Work may be allowed on Saturday and Sunday with a minimum of 72-hour notice from the Contractor and written authorization by the Contracting Officer Representative(COR). No on-site work shall be performed on Government Holidays.
https://highways.dot.gov/federal-lands/specs
5.0 Deliverables / Schedule
Submittal Schedule:
The following required items need to be submitted according to the schedule shown to prevent delays or stoppages of work.
ITEM ACTION SCHEDULE
Construction Schedule Approval by
CO/COR
2 weeks before mobilization
List of Subcontractors and Suppliers For Record* 2 weeks before mobilization
List of Emergency contact names, numbers, and title of personnel.
Approval by
CO/COR
2 weeks before mobilization
Letter of Contractor’s on-site superintendent Approval by
CO/COR
2 weeks before mobilization
Traffic Control plan Approval by
CO/COR
30 days prior to use
Written notice of closing the road Approval by
CO/COR
10 days before closure
Soil Erosion and Sediment Control Plan Approval by
CO/COR
30 days prior to start of construction
Aggregate mechanical analysis Approval by
CO/COR
10 days prior to hauling
Aggregate weight delivery tickets, and scale certification
Approval by
CO/COR
Daily, As delivered to site
Concrete mix design Approval by
CO/COR
30 days prior to production
Concrete load tickets Approval by
CO/COR
Daily, As delivered to site
Asphalt mix design Approval by
CO/COR
30 days prior to production
Asphalt weight delivery tickets and scale certification
Approval by
CO/COR
Daily, As delivered to site
Written documentation of disposal site and authority for disposal
Approval by
CO/COR
Prior to disposal
Certified Payroll Approval by
CO/COR
With invoices
* "For record" assumes that an Item which meets Specifications as written is supplied. Other "equal" products require review and approval by the CO/COR, and may take longer to review.
Notification Schedule:
The following events require an advance written notification to the COR. Notifications may mailed, emailed, or hand delivered.
EVENT PRIOR NOTICE REQUIRED
Change in Schedule As soon as identified
Intent to mobilize 48 hours
6.0 Travel
Not applicable
7.0 Contractor’s Key Personnel
Contractor must provide written documentation identifying project Superintendent, that will be onsite during construction, as defined in FP-14, Section 101.
8.0 Security Requirements
Not applicable
9.0 Data Rights
All testing data and documentation prepared in accordance with Contractor performance of this project shall be submitted to the COR, and is the property of the Government.
10.0 Section 508 – Electronic and Information Technology Standards Not applicable
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| Submittal Schedule: |
| The following required items need to be submitted according to the schedule shown to prevent delays or stoppages of work. |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Attachment |
File details come from the government source that posted it. Updated .