This document contains questions and answers regarding solicitation number 12445524Q0014 for HVAC replacement at the Green Mountain National Forest Mt Tabor Work Center. The USDA Forest Service is seeking to replace the HVAC system with new multi-speed furnaces, 2-stage compressors, and related equipment. Bidders must provide line sets from new coils to condensers that may be run on the building exterior. Pricing should be included for the specified hybrid water heater and an alternative product. All questions are due by March 7, 2024 under NAICS 238220 with a $19 million size standard. The response provides specifications and clarifies that a bunkhouse is unavailable, PVC venting may follow manufacturer guidelines, and alternatives to the specified water heater should include cut sheets.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GMF MT Tabor Work Center HVAC Replacement
Q&A’s
12445524Q0014
1) In the technical specifications for the gas furnaces, it specifies a few different blower motor types. What is the actual blower motor that is to be specified?
Single Speed, Multi Speed, or Variable Speed Answer: Multi speed
2) What is the type of furnace? Single Stage or 2 Stage?
Answer: 2 Stage
3) We spoke with the TPOC on site and he said that we may be able to stay in the Bunkhouse. Is this an Option?
Answer: No, the bunkhouse is not available.
4) The Technical Specs. Require the use of CPVC venting, however the existing venting is PVC. Should we adapt to the PVC with CPVC or follow the manufacturer installation guidelines that allow for PVC?
Answer: It is acceptable to follow manufacturer installation guidelines.
5) Can the existing line sets be modified & utilized or should new line sets be installed from the Coils to the Condensers?
Answer: New line sets are required and may be run on exterior building as noted on the plans.
6) On the Option Pricing a Hybrid Heat Pump is specified. Can we also provide pricing for a more cost-effective option as well. The specified heater is very costly.
Answer: Provide pricing for the specified water heater. An alternative may also be submitted in addition to what is specified. Provide cut sheets on the alternative.
7) The specifications for the condensers states many different motor options and compressor types. Can we get an exact specification such as single or two stage compressor and motor?
Answer: 2 Stage