| Norway Beach Recreation Area WW System Decommissioning | | | | | | | | |
| Schedule of Values (SOV) Form. | | | | | | | | |
| To be Completed by Contractor: | | | | | | | | |
| Item Number | BASE CONTRACT/BID ITEMS: | Estimated Quantity | Unit of Measure | CONTRACTOR NAME: | | | | |
| | | | SOV Unit Price | SOV Item Total Price | SOV Item Percent Complete | SOV Item Pay Amount | Bid Item Pay Amount |
| DIVISION 1 - GENERAL REQUIREMENTS | | | | | | | |
| 1 | Mobilization | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | $0.00 |
| 2.1 | Construction Surveying and Staking | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 2.2 | Contractor Sampling and Testing | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 2.3 | Temporary Facilities and Traffic Control | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 2.4 | Closeout Procedures - Includes Permit Record Submittals, Materials Submittals and Final Clean-up. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 2 | TOTAL FOR ITEM NUMBER 2: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
| DIVISION 2 - DEMOLITION AND PARTIAL DEMOLITION | | | | | | | |
| 3.1 | Building Demolition and Disposal - Garage | 392 | SF | $0.00 | $0.00 | 0.0% | $0.00 | |
| 3.2 | Building Demolition and Disposal - Storage Shed | 240 | SF | $0.00 | $0.00 | 0.0% | $0.00 | |
| 3.3 | Building Demolition and Disposal - Vault Toilet | 20 | SF | $0.00 | $0.00 | 0.0% | $0.00 | |
| 3 | TOTAL FOR ITEM NUMBER 3: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
| 4.1 | Wastewater Treatment Lagoon Cells - Liquid Sludge Waste Testing, Mixing, Pumping, Transportation and Disposal. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 4.2 | Wastewater Treatment Lagoon Cells - Synthetic Liner Cleaning | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 4 | TOTAL FOR ITEM NUMBER 4: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
| 5.1 | Wastewater Collection System Stucture Decommissioning: Sawcut Bituminous Pavement Full-Depth for MH #2 at Day Use Parking and MH #3 & MH #5 at Chippewa CG. | 105 | LF | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.2 | Wastewater Collection System Structure Decommissioning; Remove Bituminous Pavement for MH #2 at Day Use Parking and MH #3 & MH #5 at Chippewa CG. | 640 | SF | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.3 | Wastewater Collection System Structure Decommissioning; Sanitary Manhole Full or Partial Removal including partial pipe removal, equipment removal and pipe sealing; 23 Structures. | 23 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.4 | Wastewater Collection System-Decommission Lift Station #2 | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.5 | Wastewater Collection System-Decommission Lift Station #3 | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.6 | Wastewater Collection System-Decommission Submarine Lift Station and Wet Well | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.7 | Wastewater Collection System Stucture Decommissioning; Two-way Sanitary Cleanout decommissioning including partial pipe removal and pipe sealing; 10 Structures. | 10 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5.8 | Remove and Salvage submersible pumps, pump mounts, lifting rail systems, pump controls, float switches and float switch wires from Lift Station #2 and Lift Station #3 | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5 | TOTAL FOR ITEM NUMBER 5: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
| 6.1 | Lagoon WW Treatment Area Structure Decommissioning; Pipe sealing inlet pipes to MH#15 and MH#16; Pipe sealing outlet pipe from Irrigation Pump Station Valve MH; 3 Structures. | 3 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| 6.2 | Lagoon WW Treatement Area Structure Decommissioning; Cleaning/flushing of all manholes within the Lagoon WW Treatment Plant (MH#15, 16, 17, 18). Cleaning/flushing of Special Structures within the Lagoon WW Treatment Plant (Truck Dump Station, Irrigation Pump Station Valve MH, Chlorine Contact Chamber). Cleaning/flushing of all piping within the Lagoon WW Treatment Plant. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 6.3 | Lagoon WW Treatment Area Structure Decommissioning; Chlorine Contact Chamber-Abandon in-place including grouting, concrete floor restoration and pipe sealing. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 6.4 | Lagoon WW Treatment Area Structure Decommissioning; Irrigation Field Sprinkler Head-Full Removal including support post and pipe sealing. | 4 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| 6 | TOTAL FOR ITEM NUMBER 6: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 26 - ELECTRICAL
| 7.1 | Decommission 3-Phase Electrical Service at Lift Station #2. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 7.2 | Decommission 3-Phase Electrical Service at Lift Station #3. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 7.3 | Disconnect Submarine Lift Station Electric Service from Power Source. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| 7 | TOTAL FOR ITEM NUMBER 7: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 31 - EARTHWORK
| 8.1 | Embankment Placement - Sanitary Structure Decommissioning Backfill (Compacted Volume) | 250 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| 8.2 | Granular Borrow Material - Sanitary Structure Decommissioning Backfill (Compacted Volume) | 250 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| 8.3 | Class 5 Aggregate - Sanitary Structure Decommissioning Backfill (Compacted Volume) | 25 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| 8.4 | Topsoil Borrow - Sanitary Structure Decommissioning (Placed Volume) | 133 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| 8 | TOTAL FOR ITEM NUMBER 8: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 32 - SITE RESTORATION
| 9.1 | Bituminous Asphalt Patch - 3 inch depth | 640 | SF | $0.00 | $0.00 | 0.0% | $0.00 | |
| 9.2 | MNDOT Seed Mix 35-221 Applied at 36.5 Pounds per Acre (Sanitary Structure Sites) | 0.37 | ACRE | $0.00 | $0.00 | 0.0% | $0.00 | |
| 9.3 | MNDOT Type 6 Mulch Applied at 3,000 Pounds per Acre. (Sanitary Structure Sites) | 0.37 | ACRE | $0.00 | $0.00 | 0.0% | $0.00 | |
| 9.4 | MNDOT Type 3 Fertilizer Applied at 300 Pounds per Acre. (Sanitary Structure Sites) | 0.37 | ACRE | $0.00 | $0.00 | 0.0% | $0.00 | |
| 9 | TOTAL FOR ITEM NUMBER 9: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
TOTAL ALL BASE BID ITEMS: $0.00
| Item Number | OPTIONAL CONTRACT/BID ITEMS: | Estimated Quantity | Unit of Measure | CONTRACTOR NAME: | | | | |
| | | | SOV Unit Price | SOV Item Total Price | SOV Item Percent Complete | SOV Item Pay Amount | Bid Item Pay Amount |
| DIVISION 1 - GENERAL REQUIREMENTS | | | | | | | |
| O1.1 | Temporary Erosion Control (silt barrier) Lagoon WW Treatment Area | 695 | LF | $0.00 | $0.00 | 0.0% | $0.00 | |
| O1.2 | Temporary Erosion Control (staw bale check dam) Lagoon WW Treatment Area | 6 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| O1 | TOTAL FOR OPTION ITEM 1: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 2 - DEMOLITION AND PARTIAL DEMOLITION
| O2 | Abandon and Seal eight (8) groundwater monitoring wells per MDH regulations. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | $0.00 |
| O3 | Remove 2,275 LF of 6 Ft. Chain Link Fence including gate, wood posts and brace rails. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | $0.00 |
| O4 | Wastewater Treatment Lagoon Cells - Synthetic Liner Removal and Disposal | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | $0.00 |
| O5.1 | Lagoon WW Treatment Area Structure Decommissioning; Sanitary Manhole Full or Partial Removal including partial pipe removal, equipment removal and pipe sealing; 6 Structures. | 6 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.2 | Lagoon WW Treatment Area Structure Decommissioning; Truck Dump Station Full Removal including pipe removal and equipment removal. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.3 | Lagoon WW Treatment Area Structure Decommissioning; Irrigation Pump Station and Valve Manhole-Full Removal including pipe and concrete pipe support removal and pipe sealing. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.4 | Lagoon WW Treatment Area Structure Decommissioning; Concrete Aerator Docking Station at Cell #1-Full Removal including jib crane, pipe, valve and valve box | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.5 | Lagoon WW Treatment Area Structure Decommissioning; Concrete Aerator Docking Station at Cell #2-Full Removal including jib crane, pipe, valve and valve box | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.6 | Lagoon WW Treatment Area Structure Decommissioning; Wood Aerator Storage Rack-Full Removal. | 2 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.7 | Lagoon WW Treatment Area Structure Decommissioning; 4 Ft. x 4 Ft. x 4" Concrete Splash Block- Full Removal. | 6 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.8 | Lagoon WW Treatment Area Structure Decommissioning; Concrete Aerator Tie-Down Anchors- Full Removal including electrical service connections for aerator units. | 11 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| O5.9 | Remove and Salvage Floating Lagoon Aerator Pump Units | 5 | EACH | $0.00 | $0.00 | 0.0% | $0.00 | |
| 5 | TOTAL FOR ITEM NUMBER 5: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 26 - ELECTRICAL
| O6.1 | Decommission 3-Phase Electrical Service at WW Treatment Lagoon Site. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O6.2 | Furnish and Install Single Phase Electrical Service at WW Treatment Lagoon Site. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O6.3 | Electrical Upgrades at WW Treatment Lagoon Site to convert from 3-Phase Electrical Service to Single Phase Electrical Service. | 1 | LS | $0.00 | $0.00 | 0.0% | $0.00 | |
| O6 | TOTAL FOR OPTION ITEM NUMBER 6: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 31 - EARTHWORK
| O7.1 | Common Excavation - Lagoon Site Grading (In-Place Volume) | 1280 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| O7.2 | Embankment Placement - Lagoon Site Grading (Compacted Volume) | 4445 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| O7.3 | Granular Borrow Material - Lagoon Site Grading (Compacted Volume) | 3165 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| O7.4 | Topsoil Borrow - Lagoon Site Grading (Placed Volume) | 494 | CY | $0.00 | $0.00 | 0.0% | $0.00 | |
| O7 | TOTAL FOR OPTION ITEM NUMBER 7: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
DIVISION 32 - SITE RESTORATION
| O8.1 | MNDOT Seed Mix 35-221 Applied at 36.5 Pounds per Acre (Lagoon Site) | 1.23 | ACRE | $0.00 | $0.00 | 0.0% | $0.00 | |
| O8.2 | MNDOT Type 6 Mulch Applied at 3,000 Pounds per Acre. (Lagoon Site) | 1.23 | ACRE | $0.00 | $0.00 | 0.0% | $0.00 | |
| O8.3 | MNDOT Type 3 Fertilizer Applied at 300 Pounds per Acre. (Lagoon Site) | 1.23 | ACRE | $0.00 | $0.00 | 0.0% | $0.00 | |
| O8 | TOTAL FOR OPTION ITEM NUMBER 8: | 1 | LS | | $0.00 | | $0.00 | $0.00 |
TOTAL ALL OPTIONAL BID ITEMS: $0.00