12445523Q0053 WMF Auto Fee Machine electric
Questions & Answers As of 5/16/2023
Q1. At the Welch Dickey Trailhead site, is the padmount transformer, vault, and cover existing, supplied by contractor, or supplied by utility company? On the schedule of values it’s listed. However, there is no information or specification regarding the components.
A1. The contractor will be responsible for supplying the cement vault and covers, digging the hole and setting the vault. NHEC will set the padmount. They will need to work in Tandem with NHEC to perform this work as the vault will intercept conductors that NHEC will shut off prior to the excavation.