Q and A 5-16-23.pdf

PDF 57 KB Posted

Attached to
White Mountain NF Auto Fee Machine electric installs Federal contract opportunity
Solicitation number
12445523Q0053
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to White Mountain NF Auto Fee Machine electric installs, newest first.
File Type Posted
Sol_12445523Q0053.pdf PDF
Attachment 3 Wage Determination NH20230018 Grafton County.pdf PDF
Attachment 1 2023-02-03 SOW_AFM.pdf PDF
Attachment 2 Wage Determination NH20230016 Carroll County.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12445523Q0053 WMF Auto Fee Machine electric

Questions & Answers As of 5/16/2023

Q1. At the Welch Dickey Trailhead site, is the padmount transformer, vault, and cover existing, supplied by contractor, or supplied by utility company? On the schedule of values it’s listed. However, there is no information or specification regarding the components.

A1. The contractor will be responsible for supplying the cement vault and covers, digging the hole and setting the vault. NHEC will set the padmount. They will need to work in Tandem with NHEC to perform this work as the vault will intercept conductors that NHEC will shut off prior to the excavation.