Attachment 5 - Questions and Answers

RFQ # 12445521Q0186, Markham Springs Shower House Replacement

1- Where do I get the report on the asbestos removal of the old shower house?

The government has tested but does not have the results to provide at this time. The project should be priced with the assumption of no asbestos in the old shower house.

2- Does CXT give a plan of the new shower house or are there plans of the new precast building?

The government does not have a pre-existing agreement or quote from CXT with regards to this project’s new shower house to be provided. However, CXT provides plans and specifications on their buildings at:

http://www.cxtinc.com/buildings-docs.html

Quoting contractors should verify with CXT that they are quoting a shower house that meets the salient characteristics of Attachments 2 and 3 of this Request for Quote (RFQ). These two attachments provide the product requirements in Attachment 2, Statement of Work (SoW); and typical CXT “Ranier Style Building” specifications in Attachment 3. See the above link and discuss further with CXT as needed to ensure a mutual understanding prior to submitting final quote in response to this RFQ.

3- Does all material of the old shower house need to be removed offsite 100%, or is there any place for the concrete or blocks on site.

All material of the old shower house must be 100% removed off-site.