Amendment 0001 Tip-Saw Goldenrod solicitation signed.pdf

PDF 449 KB Posted

Attached to
Tipsaw - Goldenrod Group Shelter and Electrification Hoosier National Forest
Solicitation number
12445521Q0151
Issued by

View the file

Other files

File Type Posted
12445521Q0151 Combined RFQ Tipsaw.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445521Q0151 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 13

09/08/20210001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/20/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JOHN V. SWIZDOR

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of Amendment 0001 is to 1) update Schedule of Items B.1 Hoosier National Forest Tipsaw Goldenrod Group Shelter, and 2) answer questions from the site visit held on

9/1/2021.

TIPSAW PRIMROSE & GOLDENROD SITE ELECTRIFICATION Schedule of Items remains the same as well as all other terms and conditions.

Please return a signed copy of the Amendment 0001 with your quote by 0700 CT on 09/13/2021 acknowledging the changes as written above.

Period of Performance: 10/04/2021 to 01/30/2022

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

08SEP2021

Solicitation 12445521Q0151 Hoosier National Forest Tipsaw - Goldenrod Group Shelter and Electrification Page 2 of 5 Amendment 0001

The following Schedule of Items B.1 Hoosier National Forest Tipsaw Goldenrod Group Shelter shall be deleted in its entirety in the solicitation and replaced with the following:

(v) Schedule of Items/Price Schedule

Group Shelter

Description Qty

Qty Craft Hours Unit Material Labor Equipment Total

Beams, 8 X 12 (7.70 BF per LF)

40 B1 LF

Purlins, 4 X 6 (2.10 BF per LF)

160 B1 LF

Posts, 8 X 8 per LF 66 B1 LF

Trusses, Hardware plate (includes all hardware--plates, lag bolts, machine bolts, etc.)

30 B1 EA

Chords 9 B1 EA

Tusses, Vertical or diagonal web

9 B1 EA

Pine 1X8 Wood Facia 45 B1 LF

Pine 5/4 x 12" Wood Sub Facia

45 B1 LF

2x8 solid sawn wood planking with V-joint on visible side above

700 C8 SF

Semi-Transparent stain (as a protective coating for all wood surfaces)

1800 SF

Trusses, 20' to span 480 B1 SF

Tipsaw - Goldenrod Group Shelter and Electrification Page 3 of 5 Amendment 0001

Description

Qty Craft Hours Unit Material Labor Equipment Total

Metal sheet roofing (includes 15% coverage loss) 6' to 12' lengths (metal eave is part of roof cost)

700 R1 SF

Metal sheet roofing, Ridge cap, formed, plain

20 R1 LF

Sidewall flashing, plain 72 R1 LF

Ice and water shield, high temperature, 225 SF roll

72 -- SF

Column bases, heavy duty 8 X 8 (CB88)

6 BC EA

**Subtotal: 01 General Requirements

CONCRETE

Floor slab assemblies, 4" thick slab

375 -- SF

Reinforcing steel tied in columns, stairs and walls,3/4 diameter, #6 rebar (1.50 lb per LF)

160 RB LF

columns, stairs and walls,3/8 diameter, #3 rebar (.38 lb per LF)

100 RB LF

columns, stairs and walls, 1/2 diameter, #4 rebar (.67 lb per LF)

150 RB LF

Tipsaw - Goldenrod Group Shelter and Electrification Page 4 of 5 Amendment 0001

Description

Qty Craft Hours Unit Material Labor Equipment Total

Excavation with wheel loader, 24 wide bucket, Heavy or wet soil (25 LF per hour)

150 B8 LF

Backfill trenches with D- 3 crawler dozer, (25 CY per hour)

5 B8 CY

Compaction of vibrating rammers, (20 CY per hour)

5 BL CY

**Subtotal: 02 Concrete

GRAND TOTAL

General Requirements and Concrete:

Solicitation Question and Answers

1. Question The location of the #2 shelter for electric purposes?

Answer: “I showed them in the field, if you look at sheet E-01 the second shelter location would be in the circle marked Primrose.”

2. Question: It seems some items may be missing in the Shelters Schedule of Items?

Answer: “I stated an updated Schedule of Items will be post.”

3. Question: It was asked about boring or trenching across the road and the backfill material required?

Answer: “I stated I would have to confirm with the plans, on sheet E-01 note 8 refers to boring or cutting and trenching. If cutting and trenching is the method used the road section will be backfilled with aggregate.”

Tipsaw - Goldenrod Group Shelter and Electrification Page 5 of 5 Amendment 0001

4. Question: Confirming the location of the Shelter to be constructed.

Answer: “The proposed shelter to be constructed with be marked in the field prior to construction, the location shown on the Electric Plan E-01 is a representation and does not show the exact location. The structure location will be closer the parking spaces with the “F” electric line and camping spur 13 as shown on the Electric plan.”

5. Question: Water lines were observed on site in the location of the proposed shelter, and electric line locations.

Answer: Forest Service will provide known locations of waterlines that they have knowledge of at time of construction.

6. Question: Can you tell me if there are any completed shelters onsite, like the one in this project, that we could look at there in the Tipsaw Lake area?

Answer: There are no shelters currently located at this site.

7. Question: Is the construction site marked at all so that we could evaluate it for access questions related to materials and concrete?

Answer: The location will be staked by Friday 9/10/2021.

12445521Q0151 Amendment 0001 Tip Saw Goldenrod SF30.pdf
Amendment 01 Tip Saw Body.pdf