This is a Questions and Answers document for solicitation 12445225Q0008 regarding data and ethernet port installation at the Chattahoochee-Oconee National Forest Supervisor's Office in Gainesville, GA. The document contains two key questions and responses exchanged between a potential vendor and USDA Forest Service Contracting Officer Penny Zortman.

The Q&A clarifies that the project requires only low voltage work for ethernet ports, with no power requirements needed. A second question about data rack requirements was partially answered, with the Contracting Officer indicating that the COR (Travis or Julian) would provide additional information about data rack specifications within the next day. The document includes a notification of a site visit scheduled for January 21, 2025 at 9am, and questions were due by January 22, 2025 at 1pm via email to Jose Allende and Penny Zortman.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

You don't often get email from brett@graingercs.com. Learn why this is important

From: Zortman, Penny - FS, SC To: Brett Stephen Cc: Allende, Jose - FS, SC; Wiggins, Robert - FS, GA; Johnson, Julian - FS, GA; Hemingway, Travis - FS, GA Subject: RE: [External Email]RFI Chattahoochee-Oconee SO Data & Ethernet Port Installation 12445225Q0008 Date: Thursday, January 23, 2025 2:07:45 PM Attachments: image001.png image002.png image003.png image004.png

Good morning. Sorry for the delay in getting a response for your questions. People were out of the office. So to answer your questions:

1. The title of this project states "Data & Ethernet". The drawings for each room state "ethernet" and "Outlet" for power. Are there any power requirements for this project?

Or is it only low voltage? Only low voltage is needed for the Ethernet ports

2. There is no requirement about what is needed at the data rack itself. Could you clarify what is needed? In regards to the Data Rack, the COR Travis or Julian will send more info within the next day. They are researching further.

Penny Zortman, MBA, Veteran Contracting Officer Forest Service Forest Service penny.zortman@usda.gov 4931 Broad River Road Columbia, SC 29212 www.fs.usda.gov

Caring for the land and serving people

From: Brett Stephen <brett@graingercs.com> Sent: Monday, January 20, 2025 2:42 PM To: Zortman, Penny - FS, SC <Penny.Zortman@usda.gov> Cc: Allende, Jose - FS, SC <Jose.Allende@usda.gov> Subject: [External Email]RFI Chattahoochee-Oconee SO Data & Ethernet Port Installation 12445225Q0008

[External Email] If this message comes from an unexpected sender or references a vague/unexpected topic;

Use caution before clicking links or opening attachments.

Please send any concerns or suspicious messages to: Spam.Abuse@usda.gov https://aka.ms/LearnAboutSenderIdentification mailto:Penny.Zortman@usda.gov mailto:brett@graingercs.com mailto:Jose.Allende@usda.gov mailto:Robert.Wiggins@usda.gov mailto:Julian.Johnson2@usda.gov mailto:travis.hemingway@usda.gov mailto:penny.zortman@usda.gov https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.fs.usda.gov%2F&data=05%7C02%7CJose.Allende%40usda.gov%7C476e3f7f40ba44f1635108dd3be135ee%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638732560643256892%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=RThk8M4wLmqMPpIY9Y%2FxDuvqnsEG8CGgUCuAT2SQ6u4%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fusda.gov%2F&data=05%7C02%7CJose.Allende%40usda.gov%7C476e3f7f40ba44f1635108dd3be135ee%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638732560643280590%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=zbLeRSD0MOrUizHeBWaibD5N0c1La7%2BB66sKi5FIMKk%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Ftwitter.com%2Fforestservice&data=05%7C02%7CJose.Allende%40usda.gov%7C476e3f7f40ba44f1635108dd3be135ee%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638732560643294673%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=KtPVHabAkansEv5mZoH6%2BjbS5%2BCGi8oFLXJXc5ggSd0%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.facebook.com%2Fpages%2FUS-Forest-Service%2F1431984283714112&data=05%7C02%7CJose.Allende%40usda.gov%7C476e3f7f40ba44f1635108dd3be135ee%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638732560643308240%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=xshMCsbTdNg4cf23q5VMf2RLp2HyzhzHDPnHVDeArew%3D&reserved=0