A04_SOW_12445127B0005.pdf

PDF 567 KB Posted

Attached to
MORGANTOWN PAVEMENT RESTORATION
Solicitation number
12445127B0005
Issued by

About this file

This is a Statement of Work for the USDA Forest Service Northern Research Station's pavement restoration project at 180 Canfield Street, Morgantown, West Virginia.

The project requires crack sealing (2,000 linear feet), seal coating (45,950 square feet), and line painting (80 standard parking stalls, 6 ADA-accessible stalls, and hatched areas) of the facility's parking lots and driveway. All work must be completed within 90 calendar days from the Notice to Proceed, with work restricted to evening hours and seal coating and line painting limited to Friday, Saturday, and Sunday only. Contractors must attend a mandatory pre-bid meeting and be registered in the System for Award Management (SAM) prior to contract award. The contract is anticipated to be firm fixed price. All equipment, labor, and materials are contractor-supplied. Waste materials must be removed daily as the facility has no on-site waste disposal. No access to government-owned buildings is permitted. Specific technical requirements are detailed in referenced specifications covering pavement cleaning, flexible paving repair (crack sealing per ASTM D6690), seal coats (polymer-modified asphalt emulsion per ASTM D8099), and pavement markings (100% acrylic waterborne traffic paint per Federal Specification TT-P-1952). Environmental conditions restrict seal coating application to temperatures of at least 50°F and rising, with no application if rain is forecast within 24 hours or freezing temperatures within 48 hours. The Schedule of Items identifies pay units as lineal feet for crack seal and line striping, square feet for seal coat, and lump sum for mobilization.

View the file

Other files

File Type Posted
SF24.pdf PDF
C04_Solicitation_12445127B0005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

USDA Forest Service

Northern Research Station

MORGANTOWN PAVEMENT RESTORATION

180 Canfield Street, Morgantown, WV

Contents Project General Information

1.0 Scope of Work

2.0 Contractor Requirements

3.0 Technical Requirements / Tasks ........................................................................................................ Error! Bookmark not defined.

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

Attachment

Project

NRS MORGANTOWN PAVEMENT RESTORATION

General Information

1.0 Scope of Work

Project Contact

Contracting Officer’s Representative (COR) Patrick Meyer 304-919-8674

Patrick.R.Meyer@usda.gov

Background:

This project shall generally consist of, but not limited to the following: providing all labor, materials, tools, equipment, permits, testing, and reports required to crack seal, seal coat, and line paint parking lots of the USDA Northern Research Station Lab and Annex at the 180 Canfield Street, Morgantown, WV location as defined by the drawings and specifications

The intent of this project is to inspect the specified parking lots for areas needing maintenance or repairs to cracks within the asphalt before seal coating and line painting the entire parking lot(s) as originally laid out or as specified in the project drawings.

All work shall be completed within 90 calendar days from receipt of Notice to Proceed.

Care shall be taken so that no damage occurs to parked vehicles, grassy areas, and existing structures.

Waste Materials – all waste material must be removed from the site daily. This USDA facility has no waste / fill pile on campus.

Work Schedule –All work MUST be completed during the evenings with the sealcoating and line painting only taking place on Friday, Saturday, or Sunday. All work must be scheduled with the CO and COR.

Pre-Bid Meeting – All Prospective Bidders are to attend a mandatory pre-bid meeting.

Estimated Quantities:

Seal Coating: 45,950 SF Crack Sealing: 2,000 LF

Striping: 80 stalls, 6 ADA stalls, Hatched Areas All quantities are estimated and shall be field verified.

The following documents are incorporated into the statement of work and can be found as attachments to this solicitation: Specifications & Site Plan

2.0 Contractor Requirements

1. Report to the Contracting Officer, or his/her designated representative, any problem that may arise beyond the scope of this contract.

2. Providing adequate advance notice when using products that may produce noxious fumes or excessive noise that would impact daily operations.

mailto:Patrick.R.Meyer@usda.gov

3. Safety. The contractor shall comply with all OSHA standards for employee safety. It is the contractor’s responsibility to ensure its employees are properly trained and equipped for potential hazards.

4. Bidders MUST be registered in the System for Award Management (SAM) prior to award of contract. Website:

www.sam.gov

5. Damage to Contractor’s Property: The Government will not be responsible in any way for damage to the Contractor’s equipment or the Contractor’s employees’ personal belongings brought onto the Government premises during the performance of work and this contract.

6. Any damage to Government Property incurred during the implementation of this contract must be repaired or replaced by the contractor to the satisfaction of the Government representatives.

3.0 Government Furnished

Utilities (water, electric) may be available with the permission of the Government. Coordinate with COR.

4.0 Deliverables / Schedule

All equipment, labor and supplies are to be provided by the contractor that has been awarded the contract.

5.0 Travel

Not Applicable

6.0 Contractor’s Key Personnel

Contractor will be responsible for any personnel that are employed by them working on Federal property.

7.0 Security Requirements

No access to any government owned buildings shall be granted

Attachment

1. Main Building parking lot and driveway map

Site Map

180 Canfield Street, Morgantown, WV Parking Lot hatched

ITEM

NUMBER DESCRIPTION PAY

UNIT Quantity Unit Cost Amount

0001 Crack Seal LF 2000 0002 Sealcoat SQFT 46000 0003 Line Stripping LF 5440 0004 ADA Striping LF 6 0005 Mobiliazation LS 1

Total

LF - Lineal Foot SQFT - Square Foot Award anticipated to be a firm fixed price contract.

SCHEDULE OF ITEMS

Northern Research Station

PROJECT TITLE: MORGANTOWN PAVEMENT RESTORATION

SCHEDULE OF ITEMS

Period of Performance TBD

Anticipated Delivery Date TBD

Northern Research Station

NRS Morgantown Pavement Restoration

Specifications

01 10 00 – Summary

01 33 00 – Submittal Procedures

01 50 00 - Temporary Facilities and Controls

01 71 00 – Weed and Disease Prevention

01 74 19 – Construction Waste Management and Disposal

32 01 11 – Pavement Cleaning

32 01 17 – Flexible Paving Repair (Crack Sealing)

32 12 36 – Seal Coats

32 17 23 – Pavement Markings

32 90 00 – Seeding and Mulching

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Contractor's use of site and premises.

4. Coordination with occupants.

5. Work restrictions.

6. Specification and Drawing conventions.

1.2 PROJECT INFORMATION

A. Project Identification: NRS Morgantown Pavement Restoration

1. Project Location: 180 Canfield Street, Morgantown, WV

B. Owner: USDA Forest Service – Northern Research Station

1. Site Contact & Contracting Officer’s Representative: Patrick Meyer – Patrick.R.Meyer@usda.gov

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Please reference Statement of work and other Contract Documents.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.4 CONTRACTOR'S USE OF SITE AND PREMISES

A. Limits on Use of Site:

1. Limit use of Project site to areas immediately in the area of work, unless otherwise approved by COR. Do not disturb portions of Project site beyond areas in which are required to complete the contract work.

2. Driveways, Walkways, and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials unless approved by the COR.

mailto:Patrick.R.Meyer@usda.gov

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.

Repair damage caused by construction operations.

C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

B. A schedule is to be presented to COR and CO within 10 business days of Award.

C. Notify COR a minimum of two week prior to beginning work.

D. Work must be scheduled in distinct phases according to to preserve access, safety transitions, and parking availability.

1.6 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

2. At the end of each working day, work area to be cleaned.

B. On-Site Work Hours: Hours of work must be during the evenings and the Sealcoating and Line Painting MUST be completed during Friday, Saturday or Sunday. Permission to work outside these hours can be requested in writing and granted by the COR in writing.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify COR not less than seven days in advance of proposed utility interruptions.

2. Obtain COR written or verbal permission before proceeding with utility interruptions.

D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.

1. Notify COR not less than seven days in advance of proposed disruptive operations.

2. Obtain COR written permission before proceeding with disruptive operations.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

PART 2 - PRODUCTS

A. Reference Section: 32 01 17 – Flexible Paving Repair (Crack Sealing) B. Reference Section: 32 12 36 – Seal Coats C. Reference Section: 32 17 23 – Pavement Markings

END OF SECTION 01 10 00

SECTION 01 33 00 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.2 DEFINITIONS

A. Approval: Equivalent to “No Exception Taken”.

B. Approved or Approved Equivalent: To possess the same performance qualities and characteristics and fulfill the utilitarian function without any decrease in quality, durability or longevity. For equipment/products defined by the Contractor as "equivalent", substitution requests must be submitted to Contracting Officer’s Representative for consideration and be approved by the COR in writing. Approval shall constitute “No Exception Taken” and shall not be otherwise construed.

C. "No Exception Taken" constitutes that review is for general conformance with the design concept expressed in the Contract Documents for the limited purpose of checking for conformance with information given. Any action is subject to the requirements of the Contract Documents. Contractor is responsible for the dimensions and quantity and will confirm and correlate at the job site, fabrication processes and techniques of construction, coordination of the work with that of all other trades, and the satisfactory performance of the work.

D. Action Submittals: Written and graphic information and physical samples that require CO or COR’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

E. Informational Submittals: Written and graphic information and physical samples that do not require CO or COR’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.3 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Contract Name and Number.

2. Date.

3. Name of Contractor.

4. Name of firm or entity that prepared the submittal

5. Names of subcontractor, manufacturer, and supplier.

6. Category and type of submittal.

7. Submittal Purpose and description.

8. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

9. Drawing number and detail references, as appropriate.

10. Indication of full or partial completion.

11. Consecutive transmittal number.

12. Submittal and transmittal distribution record.

13. Other necessary identification.

14. Remarks.

1.4 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections as PDF electronic files and as indicated for samples and other physical submittals. Types of submittals are indicated in individual Specification Sections.

B. Submittals shall be transmitted via email to the COR & CO.

C. Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form acceptable to Government with links enabling navigation to each item.

2. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by COR.

D. Coordination: Coordinate preparation and processing of submittals with performance of construction activities

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Contracting Officer or COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

E. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's and COR’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

Contracting Officer or COR will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process intermediate review in same manner as initial submittal.

3. Resubmittal Review: Allow 15 days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Contracting Officer's consultants, Government, or other parties is indicated, allow 21 days for initial review of each submittal.

F. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Indicate date and content of previous submittal.

2. Indicate date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are approved in writing by the CO or COR (in a method acceptable to the specifications or as otherwise described by the CO).

G. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

H. Use for Construction: Retain complete copies of submittals on Project site. Use only final action or material submittals that are approved in writing by the Contracting Officer or

COR.

1.5 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Clearly mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

5. Submit Product Data in PDF electronic file.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated

2. Submit Shop Drawings in PDF Electronic Format.

C. Design Data/Product Data/Materials Submittals: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

D. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide original paper copy where a notarized signature is required.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents

E. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

7. Name of evaluation organization.

8. Date of evaluation.

9. Time period when report is in effect.

10. Product and manufacturers' names.

11. Description of product.

12. Test procedures and results.

13. Limitations of use.

1.6 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with contractor approval before submitting to Contracting Officer and COR.

B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform written approval method. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents

1.7 GOVERNMENT REVIEW

A. Contracting Officer’s Representative (COR) may approve technical submittals, unless otherwise indicated by the contract documents or determined in writing by the Contracting Officer (CO). COR may review each submittal instead of the CO.

B. Action Submittals: Will be reviewed and their approval status will be documented in a project submittal review XLS spreadsheet returned to the contractor. The specific material items will be included in this review document and notes for approval, disapproval, and resubmittal and any questions on items.

C. All submittals reviewed will be approved in the material review spreadsheet only. This will be returned to contactor with each submittal group reviewed.

D. No marked up copies of material cut sheets will be returned to the contractor.

E. Informational Submittals: Contracting Officer or COR will review each submittal and will not return it, or may return it if it does not comply with requirements. Contracting Officer or COR may forward each submittal to appropriate party. Contractor is responsible for compliance with contract requirements and all applicable laws and regulations regardless of whether mistakes were discovered by CO or COR review of informational submittals.

F. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from COR or Contracting Officer.

G. Incomplete submittals are unacceptable, will be considered nonresponsive, and may be returned for resubmittal without review.

H. Submittals not required by the Contract Documents may be returned by Contracting Officer or COR without action.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 33 00

SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Temporary traffic control, barricades, and pedestrian detours.

2. Project phasing, site access, and parking restrictions.

3. Protection of existing property, landscaping, and adjacent structures.

1.2 REFERENCES

A. Federal Highway Administration (FHWA):

1. Manual on Uniform Traffic Control Devices (MUTCD) – Current Edition.

B. State and Local Department of Transportation (DOT) Standard Specifications for Road and Bridge Construction.

1.3 SUBMITTALS

A. Traffic Control and Phasing Plan: Submit a detailed plan showing proposed sequence of operations, closing dates per phase, detour routes for vehicles and pedestrians, and locations of signs, barricades, and flaggers at least 14 days prior to commencing work.

1.4 PROJECT CONDITIONS & PHASING

A. Maintain access to existing facilities, adjacent businesses, and emergency services at all times unless otherwise coordinated in writing with the Owner.

B. Perform work in phases to minimize disruption. No phase shall completely isolate a facility without an approved alternative route.

C. Provide minimum 48-hour advanced written notification to Owner and tenants prior to closing any parking areas, driveways, or access points.

PART 2 - PRODUCTS

2.1 TEMPORARY TRAFFIC CONTROL DEVICES

A. Barricades, Signs, and Cones: Comply with MUTCD requirements.

1. Cones: Minimum 28 inches in height, bright orange, with retroreflective sleeves for night operations.

2. Barricades: Type I or Type II folding barricades with retroreflective sheeting.

B. Temporary Signage: Heavy-duty corrugated plastic or aluminum sheeted signs with bold black lettering reading "PARKING LOT CLOSED FOR SEAL COATING", "NO PARKING - TOW AWAY ZONE", and directional arrow detours.

Part 3 – Execution

3.1 INSTALLATION AND MAINTENANCE

A. Install traffic control devices before any work begins in an assigned phase.

B. Maintain all signs, cones, and barricades in a clean, visible, and upright position for the duration of the closure. Replace damaged items immediately.

C. Erect sturdy physical barriers around freshly crack-sealed or seal-coated areas to prevent tracking by vehicular traffic, pedestrian footprints, or wildlife.

3.2 REMOVAL

A. Remove all temporary facilities, barricades, and signage only when the underlying pavement coatings have completely cured, markings are dry, and the Owner has formally approved reopening the phase.

END OF SECTION 01 50 00

SECTION 01 71 00 - WEED AND DISEASE PREVENTION

PART 1 - GENERAL

1.1 SUMMARY

A. This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands.

PART 2 - PRODUCTS

2.1 WATER

A. Free of debris, organic matter, and other objectionable substances.

PART 3 - EXECUTION

3.1 GENERAL

A. Notify the COR in writing at least 10 calendar days before moving any construction equipment onto National Forest lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest lands.

B. Perform all work at a location designated on the plans or other locations approved in writing. Provide the COR with an opportunity for inspection.

3.2 EQUIPMENT

A. Use a high-pressure washing system.

B. For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.

C. For work at a commercial washing facility, use an approved facility.

3.3 WASHING

A. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.

3.4 INSPECTION

A. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.

Rewash the construction equipment as necessary or as directed.

END OF SECTION 01 71 00

SECTION 01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Disposing of nonhazardous construction waste.

1.2 DEFINITIONS

A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations.

Construction waste includes packaging.

B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.

C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner’s property.

PART 2 - EXECUTION

2.1 DISPOSAL OF WASTE

A. General: Remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn waste materials.

END OF SECTION 017419

SECTION 32 01 11 - PAVEMENT CLEANING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Mechanical scraping and sweeping of asphalt surfaces.

2. High-pressure air blasting of cracks and joints.

3. Removal of vegetation from cracks, joints, and pavement edges.

4. Chemical priming and isolation of petroleum/oil grease spots.

1.2 SUBMITTALS

A. Product Data: Submit manufacturer's technical data sheet for oil spot primer showing compatibility with the specified seal coat material.

1.3 QUALITY ASSURANCE

A. Surface Acceptance: A clean, dry surface is an absolute prerequisite for asphalt coatings.

The COR must inspect and approve the prepared surface immediately prior to any crack seal or seal coat application.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Oil Spot Primer: 100% acrylic-based or polymer-modified emulsion specifically formulated to seal and isolate petroleum, oil, grease, and gasoline stains on asphalt pavement prior to seal coating.

B. Herbicide: EPA-registered, commercial-grade non-selective systemic herbicide formulated to eliminate vegetation within cracks and joints without staining or degrading adjacent asphalt.

PART - EXECUTION

3.1 PREPARATION & VEGETATION REMOVAL

A. Apply herbicide to all weeds and grass growing within cracks, joints, and pavement transitions at least 48 hours prior to mechanical cleaning.

B. Manually or mechanically scrape out dead roots, soil, and organic matter from cracks to a minimum depth of 1/2 inch.

3.2 MECHANICAL CLEANING

A. Power Sweep or Power Broom the entire asphalt surface to remove loose aggregate, dirt, dust, and organic debris.

B. Use high-pressure power washers if necessary to remove caked mud or clay. Allow pavement to dry completely for a minimum of 24 hours before applying coatings.

C. Use high-pressure compressed air (minimum 90 psi) to blow out all routed or cleaned cracks immediately ahead of the crack-sealing crew to eliminate fine dust layers.

3.3 OIL SPOT TREATMENT

A. Scrub heavily contaminated oil and grease stains with a wire brush to remove caked surface buildup. Wipe clean.

B. Apply oil spot primer neat (undiluted) with a stiff brush or roller, completely covering the stain and overlapping onto clean asphalt by at least 2 inches. Allow to dry completely to a hard, tack-free film before seal coat application.

END OF SECTION 32 01 11

SECTION 32 01 17 - FLEXIBLE PAVING REPAIR (CRACK SEALING)

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Routing, cleaning, and preparation of cracks in asphalt paving.

2. Application of hot-applied, polymer-modified rubberized joint and crack sealant.

1.2 REFERENCES

A. ASTM D6690 – Standard Specification for Joint and Crack Sealants, Hot-Applied, for Concrete and Asphalt Pavements (Type II or Type III as specified).

1.3 SUBMITTALS

A. Product Data: Manufacturer’s specifications and application instructions for hot-applied sealant.

B. Certificates: Manufacturer's certification that the material meets or exceeds ASTM D6690 requirements.

C. Equipment Data: Documentation verifying the use of an oil-jacketed, double-boiler melting kettle with mechanical agitation.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials in original, unopened boxes bearing the manufacturer’s label, product name, batch number, and recommended safe heating temperature range.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Hot-Applied Rubberized Crack Sealant: Single-component, polymer-modified asphalt composition meeting ASTM D6690 Type II. Material must remain flexible down to -20°F and resist tracking/flow up to 140°F.

B. Detackifying Agent / Blotter: Commercial liquid detackifier or clean, fine masonry sand to prevent tracking if traffic must be maintained immediately following installation.

2.2 EQUIPMENT

A. Router: Mechanical rotary cutter capable of creating a clean, vertical-walled reservoir.

B. Melting Kettle: Double-jacketed, oil-heated kettle equipped with continuous mechanical agitation, a built-in calibrated thermometer, and a recirculating pump system. Direct-fired kettles are prohibited.

C. Heat Lance: Compressed air/propane heat lance capable of producing a high-velocity stream of hot air (minimum 2000°F) to remove residual moisture and warm the crack walls.

PART 3 - EXECUTION

3.1 APPLICATION CRITERIA & RESERVOIR PREPARATION

A. Scope: Seal all open cracks measuring between 1/8 inch and 1 inch in width. Cracks narrower than 1/8 inch do not require routing unless specified; cracks wider than 1 inch shall be treated as pothole repairs/patching.

B. Routing: Route all cracks between 1/8 and 1/2 inch wide to form a clean, uniform reservoir measuring 1/2 inch wide by 1/2 inch deep (+/- 1/8 inch).

C. Cleaning & Drying: Blow out all cracks with compressed air. If moisture is present, utilize the heat lance to completely dry and pre-heat the internal crack surfaces. Do not overheat or char the asphalt binder.

3.2 SEALANT APPLICATION

A. Heat material in the oil-jacketed kettle to the manufacturer’s exact recommended application temperature (typically 370°F to 390°F). Do not exceed the safe heating temperature.

B. Apply sealant utilizing a hand-held wand directly into the bottom of the crack reservoir, filling from the bottom up to eliminate air voids.

C. Strike off the excess sealant immediately using a V-shaped or U-shaped squeegee to form a tight, neat "overband" configuration. The finished overband must be centered over the crack, extending no more than 1 inch past each crack edge, and must not exceed a thickness of 1/16 inch above the pavement surface.

[Squeegee Strike-off] ______| ___ \_/ \_/ ___ |______ <-- Asphalt Surface | | |Sealant| | | <-- Routed Reservoir (1/2" x 1/2")

D. Protect work from traffic until the material has cooled completely and lost its tack.

Apply blotter if immediate traffic release is mandatory.

END OF SECTION 32 01 17

SECTION 32 12 36 - SEAL COATS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Application of a premium, polymer-modified asphalt emulsion seal coat over existing asphalt pavement.

1.2 REFERENCES

A. ASTM D8099 – Standard Specification for Asphalt Emulsion Pavement Sealer.

1.3 SUBMITTALS

A. Product Data: Technical data sheets for the asphalt emulsion sealer, AND additive/latex modifier.

B. Mix Design: Submit the formal job mix formula showing the exact proportions of emulsion, water, and additive per 100 gallons of sealer.

1.4 ENVIRONMENTAL REQUIREMENTS

A. Apply seal coat only when the ambient air temperature and the pavement surface temperature are at least 50°F and rising.

B. Do not apply seal coat if rain is forecast within 24 hours of application, or if freezing temperatures are anticipated within 48 hours.

C. Do not apply under high wind conditions or in thick, heavy fog.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Asphalt Emulsion Pavement Sealer: High-molecular-weight, polymer-modified refined asphalt emulsion complying with ASTM D8099. Material must contain no coal tar unless specifically approved by the Owner in writing.

B. Latex Modifier / Additive: A rubberizing polymer liquid copolymer additive designed to speed up drying, increase blackness, and improve sand retention.

C. Water: Potable, clean water free of harmful minerals, iron, or organic chemicals.

PART 3 - EXECUTION

3.1 APPLICATION SYSTEM

A. Application Rate: Apply a minimum of two uniform coats.

1. First Coat: Apply at a rate of 0.12 to 0.15 gallons per square yard.

2. Second Coat: Apply at a rate of 0.08 to 0.12 gallons per square yard.

3. Total system minimum coverage: 0.20 gallons per square yard.

B. Methods:

1. Squeegee application is preferred for the first coat to deeply force material into the surface voids; spray application may be used for the second coat to provide a uniform, textured finish.

C. Allow the first coat to dry sufficiently to sustain foot traffic without tearing or tracking before applying the second coat (minimum 2 to 4 hours depending on humidity).

3.1 CLEANUP & CURING

A. Hand-apply with handheld squeegees adjacent to concrete curbs, gutters, sidewalks, and building foundations to prevent overspray or staining. Immediately clean up any accidents.

B. Allow the final coat to cure for a minimum of 24 hours prior to reopening the pavement phase to vehicular traffic.

END OF SECTION 32 12 36

SECTION 32 17 23 - PAVEMENT MARKINGS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Layout and painting of parking stalls, drive lanes, crosswalks, arrows, and ADA symbols.

1.2 REFERENCES

A. Federal Specification TT-P-1952 – Paint, Traffic and Airfield Marking, Waterborne.

B. Americans with Disabilities Act (ADA) Accessibility Guidelines.

1.3 SUBMITTALS

A. Product Data: Technical data sheets for paint formulations and color charts.

B. Certificates: Certification showing compliance with local VOC (Volatile Organic

Compound) regulations.

PART 2 - PRODUCTS

2.1 PAINT MATERIALS

A. Traffic Paint: 100% acrylic, fast-drying, waterborne traffic paint conforming to Federal Specification TT-P-1952, Type I or Type II.

B. Colors:

1. Parking Stall Lines: White or Yellow (to match existing layout or as noted on drawings).

2. ADA Accessible Stalls: International Accessibility Blue with White outlines/symbols.

3. Fire Lanes & No Parking Zones: Traffic Red.

PART 3 - EXECUTION

3.1 APPLICATION & LAYOUT

A. Layout: Accurately layout and chalk-line all markings according to the original pavement pattern or new design plans. Parking stalls must be uniform, square, and comply with ADA dimension requirements.

B. Surface Condition: Pavement surface must be completely dry and free of loose dust, oil, or un-cured seal coat. The underlying seal coat must be cured to a hard film (minimum 4 to 12 hours) before layout painting begins.

C. Application Equipment: Use a professional, self-propelled airless spray marking machine equipped with guide sights and sharp line cut-off valves to ensure clean edges without mist or overspray.

D. Film Thickness: Apply paint at a minimum wet film thickness of 15 mils (which dries to approximately 10 mils dry film thickness). Lines must be exactly 4 inches wide with clean, crisp edges and uniform opacity.

E. Stencils: Use high-quality, sharp-edged plastic or aluminum stencils for all arrows, lettering, and ADA symbols.

F. Protection: Keep traffic completely off painted lines until dry to the touch (typically 30 to 45 minutes under standard weather conditions).

END OF SECTION 32 17 23

SECTION 329000 SEEDING AND MULCHING

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes seeding, mulching, and fertilizing.

B. The areas to be seeded and mulched shall be all areas disturbed by contract operations, and as otherwise indicated.

1.2 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Product certificates.

1.3 QUALITY ASSURANCE

A. Installer's Field Supervision: Require Installer to maintain an experienced full-time supervisor on Project site when planting is in progress.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Seed, Fertilizer: Deliver, store, and handle materials according to manufacturer’s recommendations. Materials must be kept dry until ready to use.

1.5 METHOD OF MEASUREMENT

A. Seeding and Mulching is incidental to the project work unless otherwise specified.

PART 2 – PRODUCTS

2.1 PLANTING MATERIALS

A. Topsoil Source: Reuse surface soil on-site or import where not available on site. Topsoil source must be approved by COR.

B. Seed Mix:

1. To be approved by COR prior to placement

C. Mulches:

1. Straw Mulch: Provide air-dry, clean, mildew- and weed-free, threshed straw of wheat, rye, oats, or barley.

2. Straw mat netting for erosion control. Excelsior single sided straw mulch blanket with biodegradable netting as manufacturer by AEC Premier strawAE3000 or approved equal.

PART 3 – EXECUTION

3.1 PREPARATION

A. Finish Grading: Grade planting areas to a smooth, uniform surface plane with loose, uniformly fine texture. Grade to within plus or minus 1/2 inch of finish elevation.

B. Restore areas if eroded or otherwise disturbed after finish grading and before planting.

3.2 SEEDING

A. Sow seed at the rate of 15lb/acre. Apply Fertilizer at rate required by contract documents, if required by contract documents.

B. Rake seed lightly into top 1/8 inch of topsoil, roll lightly, and water with fine spray.

C. Protect seeded areas by spreading straw mulch. Spread uniformly at a minimum rate of 2 tons/acre to form a continuous blanket 1-1/2 inches in loose depth over seeded areas.

Spread by hand, blower, or other suitable equipment. Straw mat netting shall be installed according to manufacturer’s recommendations.

D. Hydro-seeding using the above seeding rates is also acceptable method of seeding.

E. Seeding shall be completed between April 1-June 1 for spring plantings and Sept.1- October 15 for fall planting.

F. Temporary seeding during winter months may be required and shall consist of winter wheat at 30lb/acre and straw mulch at one ton per acre.

END OF SECTION

ADP851.tmp
Project
General Information
1.0 Scope of Work
2.0 Contractor Requirements
3.0 Government Furnished
4.0 Deliverables / Schedule
5.0 Travel
6.0 Contractor’s Key Personnel
7.0 Security Requirements
Attachment
Unit Cost2000:
Amount2000:
Unit Cost46000:
Amount46000:
Unit Cost5440:
Amount5440:
Unit Cost6:
Amount6:
Unit Cost1:
Amount1:
AmountTotal: