COMMENTS MATRIX FOR USDA-FS ISSUANCES: 12445123B0006 Redding Campground Waterline
(Please read instructions on back before completing form.)
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ R/ P
SD FORM 818, JAN 09 PREVIOUS EDITION IS OBSOLETE
3-8-23 pre-bid meeting
Bidder Comment: Can the new 2-inch and 3-inch HDPE waterlines may be installed in the same trench?
Resolution: Where feasible, the new 2-inch and 3-inch HDPE waterlines may be installed in the same trench and shall be separated with bedding material a minimum of 4 inches apart.
meeting Bidder Comment: Can pneumatic pressure testing will be used?
Resolution: Pneumatic pressure testing will not be allowed.
Bidder Comment: How do you want the replacement of valve box and 2” gate valve at the existing filter house installed?
Resolution: For replacement of valve box and 2” gate valve at the existing filter house (Sheet 2 of the Plans), a new valve and valve box shall be installed on the existing waterline outside of the filter house. Connection to existing waterlines inside the filter house shall not be required.
Bidder Comment: Do you want the existing valve and valve box located approximately 25 feet north of Redding Access Road replaced?
Resolution: Existing valve and valve box located approximately 25 feet north of Redding Access Road shall be removed and disposed of and shall not be replaced.
Bidder Comment: What are the material specifications for the control cable and control cable conduit?
Resolution: The material specifications for the control cable and control cable conduit shall be:
- Conduit: ½-in Non-Metallic Schedule 40 PVC Conduit
- Control Cable: Southwire Manufacturer #22957501 THHN/THWN, 14 AWG, 15
AMP, 600 Volt, 19 Strand Wire, Chemical & Moisture Resistant (Or Equivalent)
- Will need two equivalent lengths of this cable from the existing filter house to the existing water tank
COMMENTS MATRIX FOR USDA-FS ISSUANCES: 12445123B0006 Redding Campground Waterline
(Please read instructions on back before completing form.)
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ R/ P
SD FORM 818, JAN 09 PREVIOUS EDITION IS OBSOLETE
INSTRUCTIONS FOR COMPLETING SD FORM 818
COORDINATING OSD COMPONENT: Use this form to provide consolidated critical and substantive comments to the OSD Component that originated the issuance. Complete the classification header and footer, columns 1 through 5, and the first two entries in column 6. REVIEW THE COMMENTS, RESOLVE ANY CONFLICTING VIEWS, AND CONFIRM THAT THE COMPLETED MATRIX ACCURATELY REPRESENTS YOUR COMPONENT’S POSITION. Upload the form to the DoD Directives Program Portal IN MICROSOFT WORD FORMAT, with a scanned copy of the sign SD Form 106, “DoD Directives Program Coordination Record,” or coordination memorandum.
ORIGINATING OSD COMPONENT: Use this form to consolidate comments from all coordinators and to record adjudication of the comments. (To add comments from an SD 818 submitted by a coordinator, use the “Copy” and “Paste” tools on the Microsoft Word Standard Toolbar.) When consolidating comments, place them in the order of the pages/paragraphs they apply to (e.g., all comments from all coordinators that apply to page 1, paragraph 1.a., should be grouped together as the initial entries; all comments that apply to page 1, paragraph 1.b., should be grouped together next, and so on). Complete column 7 and the third entry in column 6. Adjust the classification header and footer and columns 1 and 2 as appropriate.
CLASSIFICATION – Enter the highest classification of the comments. If all are unclassified, mark the header and footer accordingly and ignore the column.
COLUMN 1 – Enter the number of the comment. Enter comments in the order of the pages/paragraphs they apply to.
COLUMN 2 – Enter the classification of the comment. If all comments are unclassified, mark the header and footer accordingly and ignore the column.
COLUMN 3 – Enter the appropriate information.
COLUMN 4 – Enter the appropriate information.
COLUMN 5 – Enter the appropriate information.
COLUMN 6 – Enter the comment type. Place only one comment per row. Do NOT include administrative comments concerning non-substantive aspects of an issuance, such as dates of references, organizational symbols, and/or grammatical errors.
(C) CRITICAL: When a Component has one or more critical comments, that Component’s coordination shall reflect a nonconcur. THE JUSTIFICATION FOR CRITICAL COMMENTS
MUST IDENTIFY:
– Violations of the law or contradictions of Executive Branch policy or of policy established in DoD issuances. The GC, DoD, or his or her representative shall identify legal objections as critical comments.
– Unnecessary risks to safety, life, limb, or DoD materiel; waste or abuse of DoD appropriations; or imposition of an unreasonable burden on a Component’s resources.
(S) SUBSTANTIVE: Substantive comments are made when a section in the issuance appears to be or is potentially unnecessary, incorrect, misleading, confusing, or inconsistent with other sections, or when a Component disagrees with the proposed responsibilities, requirements, and/or procedures. A substantive comment is usually not sufficient justification for a Component to nonconcur on an issuance. Several substantive comments when taken together may be grounds for a nonconcurrence.
COLUMN 7 – COORDINATING COMPONENT: Enter the comment in the area provided. Enter your justification for the comment and your requested or recommended changes in the area provided.
YOU MUST PROVIDE CONVINCING SUPPORT FOR CRITICAL COMMENTS IN THE JUSTIFICATION.
– ORIGINATING COMPONENT: Enter your justification for disposition of the comment in the area provided. Include any related communications with the coordinating Component. You must provide convincing support for rejecting critical comments.
COLUMN 8 – Enter whether you accepted (A), rejected (R), or partially accepted (P) the comment. Your justification for disposition of the comment in column 6 must be consistent with this entry.