This is a Schedule of Items pricing form and Independent Government Estimate (IGE) template for a firm fixed price construction contract related to dam maintenance and erosion repair at the Hoosier National Forest, Tell City Ranger District in Indiana.
The project, titled "TCRD Indian Lake and Tipsaw Lake Dam Erosion Repair" (Requisition No. 1174253), involves ten line items covering both auxiliary spillway repairs and site restoration work. Specific deliverables include repair of the Indian Auxiliary Spillway and Tipsaw Auxiliary Spillway, placement of rip rap on Indian Lake Dam face, delivery of aggregate materials in varying sizes (260 tons of #53 aggregate, 40 tons of #2 aggregate, and 700 tons of 24-inch rip rap), installation of 930 square yards of geotextile fabric, seeding and mulching of 3 acres, mobilization services, and optional debris removal. The period of performance runs from September 3, 2026 to October 1, 2026, with an anticipated delivery date of October 1, 2026. Offerors must provide unit prices and total line item costs for all ten items; quotes that do not include pricing for all line items will not be considered. The award will be a firm fixed price contract issued by the Department of Agriculture Forest Service, with questions directed to lawrence.jackson@usda.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
INSTRUCTIONS: HOW TO USE THIS FORM
| Independent Government Estimate (IGE) |
| No specific format is required for an IGE; however this must be an independent estimate and not a reiteration of a contractor quote. The selected format should generally be in the same level of detail and manner that the Schedule of Items pricing we request from contractors. The estimate should state any underlying assumptions or rationale used in formulating the estimate. Initially the CO will use the IGE to determine the estimated value of the procurement and to identify the appropriate procurement thresholds applicable to the solicitation. Later the IGE is compared to prices received to evaluate an offeror’s understanding of the government requirements and in supporting a price reasonableness determination. |
EXPLANATION OF TABS
| Stand Alone IGE: | Use if the below do not apply to your requirement. |
| Stand Alone IGE w/options: | Use if you have a requirement where you know you have an ongoing/recurring need year after year. |
| IDIQ: | Use if you have a need that is reoccurring or multi-year requirement. |
| Task Order: | Use if you want to issue a order against an existing contract or agreement. |
Dam Maint Project 1
| FILL OUT THE AREAS IN RED BELOW |
| SCHEDULE OF ITEMS |
Hoosier National Forest, Tell City RD PROJECT TITLE: TCRD Indian Lake and Tipsaw Lake Dam Erosion Repair WORKPLAN ACQUISITION PLAN/REQUISITION NO: (1174253)
| Period of Performance (Required for Services and A&E) | 9/03/26- 10/01/26 | ||||
| Anticipated Delivery Date (Required for Supply and Construction) | 10/1/26 | ||||
| SCHEDULE OF ITEMS | |||||
| ITEM | |||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | Unit Price | Total Cost |
| 0001 | Indian Auxillary Spillway Repair | LS | 1 | ||
| 0002 | Tipsaw Auxillary Spillway Repair | LS | 1 | ||
| 0003 | Indian Rip Rap Placement | LS | 1 | ||
| 0004 | Aggregate #53 | Tons | 260 | ||
| 0005 | Aggregate #2 | Tons | 40 | ||
| 0006 | Aggregate 24" Rip Rap | Tons | 700 | ||
| 0007 | Geotextile Fabric | SY | 930 | ||
| 0008 | Seeding and Mulching | Acres | 3 | ||
| 0009 | Mobilization | LS | 1 | ||
| 0010 | Optional Debris Removal | LS | 1 | ||
| LS - Lump Sum, SY - Square Yards |
Ton - Tons, Ac - Acres Award anticipated to be a firm fixed price contract.
| Each offeror shall identify their quoted unit price and total line item price for each district to be considered for contract award. | |
| All work on the line item schedule must be included in the quote. Quotes that do not provide pricing for all line items for the area(s) indicated will not be considered. | |
| Contractor Name ____________________ | UEI#_____________________ |
Signature___________________________ Date_____________________