Question and Answer Document Coranando.pdf
PDF 96 KB Posted
- Solicitation number
- 12444326Q0080
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Question and Answer document for Solicitation 12444326Q0080 regarding Coronado Range Fence Materials. The document clarifies four key discrepancies identified by prospective contractors between various solicitation documents.
The document confirms that wire stays must be 42 inches in length, resolving a conflict between the Statement of Work quantity tables and the Specifications and Schedule of Items. It clarifies that the Nuts & Bolts line item (½ inch x 1½ inch) is intended for use with the braces and is separate from bolts referenced with brace angle iron posts. Regarding unloading procedures, the document states there is no guarantee that a forklift will be available at each district location; however, contractors may use their own forklift for unloading palletized materials, and liftgate/hand-unload delivery is not required. Finally, the document resolves a delivery address conflict by establishing that the Schedule of Items contains the correct delivery locations for Safford, Sierra Vista, and Santa Catalina districts, and these locations govern over the addresses shown on the SF-1449 form.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30 Amendment 1.pdf | ||
| Attachment 1-Schedule Of Items .pdf | ||
| SF 30 Amendment 2.pdf | ||
| Attachment 2-Statement of work Specifications.pdf | ||
| Original 1449.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answer Document Solicitation 12444326Q0080 / Coronado Range Fence Materials
1. Wire stays: the SOW quantity tables state 42-in., while the Specifications and Schedule of Items state 36-in. Please confirm the required length. The wire stays need to be 42-in.
2. Bolts: please confirm whether the “Nuts & Bolts” line (½ in. x 1½ in.) is separate from the bolts referenced with the brace angle iron posts or covers them. The Nuts and Bolts are the ones for the braces
3. Unloading: please confirm whether each district can offload palletized material (forklift available), or whether liftgate/hand-unload delivery is required. There is no guarantee a forklift will be available. Contractors may use their own forklift to unload.
4. Delivery addresses: the Schedule of Items and SF 1449 show different addresses for Safford, Sierra Vista and Santa Catalina. Please confirm the correct delivery address for each district.
The Schedule of Items contains the correct delivery locations; however, the SF-1449 reflects the incorrect locations. The Schedule of Items delivery locations govern.