Questions and Answers 12444323Q0038 06-08-2023

1. What is the name of current contractor? What is the annual cost of current contract ? Has the current solicitation changed from current contract?

a. There was not a contract for this requirement at this location last year.

2. Is there a site visit scheduled?

a. Please contact Katherine Defayette at katherine.defayette@usda.gov or David Donahue at david.p.donahue@usda.gov to schedule a site visit. Thank you.

52.237-1 Site Visit (APR 1984) Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

mailto:katherine.defayette@usda.gov mailto:david.p.donahue@usda.gov