Attachment 1 - Angelina-Sabine Questons and Answers.pdf

PDF 538 KB Posted

Attached to
Angelina-Sabine NF Grounds Maintenance
Solicitation number
12444223Q0025
Issued by

About this file

This document contains questions and answers regarding federal contract solicitation number 12444223Q0025 for grounds maintenance services at the Angelina-Sabine National Forest. The current contractor is Ricky Burton, though annual contract value is considered proprietary. Major changes from the previous contract are outlined in a pre-proposal bulletin. Contractors must adhere to biobased product and affirmative procurement requirements and ensure all insurance requirements in the solicitation are met. Roundup herbicide may not be used in rock beds or around fences.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. Question: Is insurance required for this effort?

Answer: All insurance requirements are in the solicitation such as FAR 52.228-5, Insurance and AGAR 452.228-71, Insurance. This list is not the exhaustive list of clauses regarding insurance.

Please read the solicitation and provide all insurance requirements.

2. Question: Is “Round Up” allowed to be used in the rock bed and around fences?

Answer: Contractors are to adhere to the Biobased products requirements as stated in FAR 52.223-1, Biobased Product Certification and 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. For a list of Biobased products, please visit https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml#

3. Questions: Who is the incumbent and what is the annual contract value?

Answer: The current contractor is Ricky Burton. The Government will not disclose the annual contract value. This is considered proprietary information.

4. Question: Were there any performance issues?

Answer: The Government will not disclose contractor performance.

5. Question: Were there any major changes from the last contract?

Answer: A list of major changes are noted Preproposal Bulletin Special Notice posted on Monday, July 17, 2023.

File details come from the government source that posted it. Updated .