12444023Q0007 Amendment 001 Questions and Answers.docx
DOCX document 16 KB Posted
- Attached to
- Conasauga Janitorial Services
- Solicitation number
- 12444023Q0007
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12444023Q0007_Attach _1_ Statement of Work.docx | DOCX document | |
| 12444023Q0007_Attach_5_Experience_Questionnaire.docx | DOCX document | |
| 12444023Q0007_Attach_3_Pricing Exhibit_08FEB23.xlsx | XLSX spreadsheet | |
| 12444023Q0007_ Attach_2 _Conasauga Floor Plans.pdf | ||
| 12444023Q0007_Attach_4 SCLS WAGE DETERMINATION 09FEB23.pdf | ||
| 12444023Q0007_Combined_Synopsis_Solicitation_ Conasuga_ Janitorial.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 001: Posting of Questions & Answers Solicitation #12444023Q0007 Q&A Conasauga Ranger District Janitorial Services
1. What is the cleanable SQFT of the facility?
Answer: Chatsworth office – 86 x 68 = 5,848 sq ft.
Villanow Work Center - 40 x 20= 800 sq ft.
2. Would it be possible to schedule a site visit? If yes, what date would work best for you?
Answer: Yes, to schedule a site visit please reach out to Kim Winkler:
Kimberley.winkler@usda.gov
3. Is this a new contract or a repeat of one that has been completed before?
Answer: This will be a repeat of the one completed before.
4. How much was the previous contract awarded for?
Answer: The total (base + 4 option years) obligated contract amount is $37,550.28 for services from 06/01/2018 to 03/31/2023
5. Is there any way we could provide past performance from our subcontractor instead?
Answer: In order for past performance of proposed subcontractors, or other teaming partners to be considered, that firm must be proposed to perform 25% or more of the contract value. Formal Teaming or Joint Venture agreements must be provided if submitting past performance information or a teaming partner. If past performance for a subcontractor, or other teaming partner is submitted, the following must be included; 1) signed teaming agreement 2) proposed role of subcontractor/teaming member 3) annual % of work to be performed by the subcontractor/teaming member.
6. When are both locations (Chatsworth & Villanow) need to be cleaned?
Answer: Villanow Work Center: Once a week Chatsworth: Twice per week
7. How much are you paying out on both jobs separately?
Answer: The total (base + 4 option years) obligated contract amount is $37,550.28 for services from 06/01/2018 to 03/31/2023