CLARIFICATIONS.pdf

PDF 133 KB Posted

Attached to
USDA Forest Service - Hebgen Lake District Office Network Cabling and IT Room Improvements
Solicitation number
1240LU26Q0132
Issued by

About this file

This is a Questions and Answers (Q&A) document for a federal contract solicitation issued by the USDA Forest Service for IT infrastructure work at a facility in West Yellowstone, Montana (331 U.S. 191).

The project involves installation of 51 new Category 6 data cable runs with termination, labeling, testing, and certification; procurement and installation of networking hardware including Meraki routers (MX-67 or MX-75), Meraki switches (MS 120-8FP or MS 130-8FP), and Meraki wireless access points (MR 36); installation of a new IT equipment cabinet with UPS, PDU, shelving, and cable management; relocation of existing network equipment into the new cabinet; and removal of all existing Category 5 cabling and legacy equipment. The project magnitude is estimated at less than $25,000. Performance bonds and payment bonds are not required. Work must be completed within 60 days after Notice to Proceed, during the performance window of November 1, 2026 to December 31, 2026. A dedicated 120V, 20-ampere electrical circuit already exists. Approximately two-thirds of the new cable runs pass through crawl spaces with vertical clearances of 24 inches (south) and 32 inches (north); the crawl space is not classified as a plenum and contains no asbestos or standing water. Contractors are encouraged to coordinate site visits with Wendi Urie, District Ranger, at (406) 404-5126. Contractors bear responsibility for obtaining electrical permits and must be licensed in a state (with any state license acceptable except for electrical work requiring Montana licensing). Contractors may propose cabling systems for approval provided components are compatible across systems, and subcontractors may satisfy manufacturer authorization and experience requirements. Equipment procurement includes Cisco switches and routers owned by LEC (Landscape Ecosystem Center) and USDA Enterprise equipment for patching user devices. Government will provide four wireless access point units; contractors are responsible for identifying WAP locations and cabling but not for furnishing or installing WAP devices. Weather delays may warrant time extensions for work completion.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLARIFICATIONS

1. Bonding requirements: Please confirm whether performance and payment bonds, as well as a bid guarantee, are required for this acquisition, given the stated project magnitude of less than $25,000. No bonds required.

2. Electrical work: Is a dedicated 120V, 20-amp circuit already available at the IT room, or should the contractor assume that installation of the new circuit is required in the base price?

120VAC dedicated circuit is existing.

3. Existing IT equipment: Should the existing equipment shown in the IT room photograph remain operational and in place, with the contractor working around it, or is any relocation or removal of existing equipment expected? Existing equipment shown in IT room should be installed in new cabinet. Contractors should limit system downtime as much as practicable.

4. Site visit: Is a site visit available or recommended for prospective offerors, particularly to assess the crawl space conditions and existing cable pathways before submitting pricing? There is no formal scheduled site visit, contractors are encouraged to contact the district and coordinate a site visit prior to submitting pricing but is not required. Contact Wendi Urie, District Ranger at (406) 404-5126, wendi.urie@usda.gov

5. Cabling quantities: The Statement of Work specifies 51 new Category 6 runs. Should offerors assume that all 51 runs are to be fully installed, terminated, labeled, tested, and certified as part of the base requirement? Yes.

6. Travel and site conditions: Are there any Government provided facilities, access arrangements, or other site support available to contractors working at the West Yellowstone location? Contractors will need to coordinate work during normal working hours M-F 0800 – 1700 and have access granted by local district personnel.

7. For the existing cabling that is no longer in use, is the contractor required to completely remove the cabling, or may it be cut/removed back to the ceiling, floor, or wall penetration locations? Yes, remove old cabling.

8. Are the Rack/cabinet dimensions specified in the documents mandatory, or would an equivalent rack with dimensions varying by approximately 1/8” to 7/8” in any dimension be acceptable, provided it meets all functional and secure-access requirements? Minor variation would be OK if all existing equipment fits in rack.

9. Are plans available? No, not currently.

10. Crawl space / plenum classification: Approximately two-thirds of the new Cat 6 runs pass through a crawl space per the Statement of Work. Can you confirm whether this crawl space mailto:wendi.urie@usda.gov functions as a return-air plenum for the building's HVAC system? This determines whether plenum-rated cable is required by code versus standard riser-rated cable, and materially affects our pricing. Not a plenum.

11. Crawl space clearance: What is the approximate vertical clearance of the crawl space where cabling will be routed? This affects our crew safety planning and installation schedule.

S. crawlspace 24”, N. crawlspace 32”

12. Additional site photos: Given the distance to the site, a pre-award visit isn't practical for

us. Could you provide a few current photos of the crawl space along the cable pathways and the IT room area? See attached photos.

13. Parking and staging: Is on-site parking and a staging/laydown area available for our crew's vehicle and materials during the installation? Yes, on-site parking and staging site available.

14. Hazardous materials: Is there any known hazardous material (e.g., asbestos-containing insulation) in the crawl space or in the areas where the old cabling will be removed? NO ASBESTOS in crawl space or in areas where the old cabling will be removed.

15. On-site point of contact: Who should we coordinate with directly for scheduling and site access once the contract is awarded, if different from the Contracting Officer? Coordination point is CO/COR.

16. Performance window: The solicitation lists a Period of Performance of 11/1/2026 to 12/31/2026. Given West Yellowstone's winter conditions during that window, is there any flexibility in scheduling, or any blackout dates we should plan around? Performance window will be updated.

17. Electrical permit: Will the Government handle any local electrical permit required for the new dedicated 120VAC/20A circuit, or is obtaining that the contractor's responsibility? No, permits are contractor’s responsibility.

18. Drop count confirmation: Can you confirm that 51 is the current, final count of data drops shown on Attachment 3, and that no revised floor plan exists? Confirmed.

19. Crawl space: About two-thirds of the runs appear to route through the crawl space. Please describe the approximate clearance height, the access point(s), and any known hazards such as asbestos, standing water, or pests. No asbestos or standing water. Crawl spaces commonly have spiders and other types of insects.

20. Manufacturer authorization: ADI Guidelines 1.20D asks for proof of manufacturer-authorized installer status at the time of proposal. Is this mandatory for this award, and if so, is a specific cabling manufacturer or system warranty required? CIO

21. Cable type: Should the horizontal Cat6 cable be plenum-rated (CMP) or riser-rated (CMR), and is a specific manufacturer required? CIO

22. Electrical circuit: Does a dedicated 120V, 20-amp circuit already exist at the new cabinet location? Also, Schedule of Items line 5 reads "12vac." Please confirm this should read 120VAC.

120VAC dedicated circuit existing.

23. Schedule: The documents reference completion 7 days after award, 60 days after notice to proceed, and a period of performance ending 12/31/2026. Please confirm which date governs completion. 60 days after NTP.

24. Cat 6 cabling – For AP and work stations, do we have a # of APs needed and # of data drops?

25. Can the Government confirm that all 51 cable drops are single-port Cat6 data drops with no voice, security, or specialty cabling requirements? CIO

26. Is procurement of APs our responsibility? YES ADI STANDARD HARDWARE INCLUDES:

A. Meraki Router- MX-67 or 75

B. Meraki Switch MS 120-8FP or MS 130-8FP

C. Meraki Wireless Access Point MR 36

D. Meraki Licenses for Equipment1. If additional switches or Access (AP’s) are required, please notify the CIO

27. “All structured cabling installed must be home-run back to the new data cabinet for termination and management” Will there need to be a switch procurement for this as well since the IT cabinet? New CIO

8/26/2025 ADI & POTS Phone Lines Page - 3/16

1.04 USDANET HARDWARE DEVICES

A. LEC owned -Cisco Network Switch 8 port

B. LEC owned -Cisco Catalyst 8200 router

C. LEC owned - ADVA Provider Network interface device

D. USDA Enterprise Cisco switch 12,24or 48 port switches for patching user devices

28. “i. Removal and disposal of all no longer necessary cabling.” has this already been predetermined or will this need to be identified. All replaced.

29. Can the Government clarify the quantity and type of abandoned cabling that will require removal and disposal. All Cat 5.

30. Is removal limited to abandoned communications cabling, or does it include legacy rack equipment, patch panels, and cabinet hardware? All equipment.

31. Are existing cable pathways, sleeves, conduits, and penetrations available for use, or should new pathways be included in the proposal? Existing pathways available for use.

32. Are there any restricted work areas or hazardous-material considerations that could affect cable routing? Crawl space. No hazmat.

33. Are there suspended ceilings? No.

34. The project requires 51 Cat 6 runs, while the ADI guide identifies Cabinet Option C for installations with more than 18 runs. Is Option C required, or may the contractor select any of the three listed cabinet options? Select most appropriate.

35. Are the cabinet, UPS, PDU, shelf, and fan models listed in the ADI guide required, or are equivalent products acceptable? Equivalent products acceptable.

36. The ADI guide requires an authorized installer for the approved end-to-end solution. Please identify the required cabling manufacturer/system and the manufacturer authorization that must be submitted with the quote. Contractors should propose a system for approval; products must be compatible across systems.

37. Please specify the required cable rating and connectivity components, including CMP versus CMR cable, cable and jack colors, outlet and faceplate configuration, patch-panel configuration, labeling requirements, and acceptable pathway/support methods. Please also identify the applicable ceiling types and air-handling conditions. CIO

38. Are Cat 6 patch cables required at both the field/device side and rack side? If so, please specify the quantity, length, and color required for each side. Only rack side.

39. Please identify which of the 51 runs serve wireless access points. Is the contractor’s responsibility limited to cabling, termination, labeling, and testing, or does it include furnishing or installing WAP devices? Please also identify the required field-end termination and mounting method for the WAP cabling. I.D. WAPs. Does not include furnish/install WAP device. WAP locations identified on site plan in hallways.

40. Is surface-mounted Wiremold or equivalent surface raceway acceptable at exposed or non-drywall locations? Yes.

41. May existing penetrations be reused? If new or existing penetrations are disturbed, is a specific manufacturer-rated firestopping system required? Reuse existing; no specified fire stopping system.

42. Is the contractor responsible for relocating, racking, reconnecting, or repatching the existing network, ISP, fiber, or telephone equipment into the new cabinet? YES Must the existing network remain operational during construction, and if a cutover is required, what outage window will be permitted? Existing network must remain operational during construction.

Outage window for cutover should be as minimal as possible.

43. After the new cabinet is installed, should the existing rack, patch panels, backboard, and associated hardware shown in the IT-room photograph be removed and disposed of or left in place? Dispose off site.

44. Please clarify which existing cables are considered “no longer necessary.” Will the Government identify and authorize the cables to be removed before demolition begins?

Replace all existing Cat5 cables.

45. Should bidders include a new dedicated 120V, 20A circuit, or is an existing compliant circuit available? If a new circuit is required, please provide the approximate distance from the proposed cabinet to the electrical panel. Distance from panel NO, 120V, 20A dedicated circuit existing.

46. Is the exterior service-provider conduit described in the ADI guide included in this project?

No.

47. The SF 1442 states that performance and payment bonds are not required, but FAR 52.228- 15 is marked as applicable. Please confirm whether performance and payment bonds will be required. No bonds required.

48. Buy American (FAR 52.225-1/52.225-2 and 52.225-9): Will the UPS, PDU and wall cabinet (Schedule Items 3, 6, 7) be treated as construction material under 52.225-9 or as supplies under 52.225-1? The UPS models named in the ADI Guidelines (Tripp Lite SMART2200RMXL2UTAA, APC SMX2000RMLV2U) are TAA-compliant but generally not U.S.-manufactured. Will the Government accept these models, or should quoters list them as foreign end products/materials under the Buy American Certificate? Yes they are acceptable.

49. Cabling scope: Please confirm (a) 51 single-port CAT6 drops per Attachment 3 and which of them, if any, are wireless access point locations (ceiling or high-wall); (b) whether patch cords are required (ADI 1.23 recommends two per drop) or Government-furnished; (c) whether any of the cable route passes through an air-handling plenum requiring plenum-rated cable; and (d) that cabinet option (C), 42"x24"x36", is acceptable and that the new cabinet replaces the existing pegboard location shown in Attachment 5. The four WAP units are government provided. Locations are labeled on the site plan(ceiling or high-wall acceptable) in the hallways.

No cable routes pass through an air-handling plenum. Cabinet replaced existing.

50. Existing equipment and cutover: Is the contractor responsible for relocating the existing Government and provider equipment shown in Attachment 5 (router/ONT, switches, phone equipment) into the new cabinet and cutting users over to the new cabling? If so, what outage windows apply (after-hours or weekend work allowed?), and should the existing patch panels and pegboard be removed under SOW item (i)? Notify staff of planned outages. Remove existing equipment and pegboard.

51. Electrical and grounding: Is breaker space available in the panel serving the basement IT room, and approximately how far is the IT room from the main service/building ground (this sets the TMGB bonding conductor size per the ADI table)? Item 5 reads "12vac"; please confirm 120 VAC, 20 A. Will the Forest Service require a Montana state electrical permit for work at this federal facility? 120V, 20A dedicated circuit existing for IT room.

52. Please confirm that email submission is sufficient, YES despite the SF 1442 cover-page language concerning sealed offers and copies. In addition to the Schedule of Items, experience/past performance narrative, and amendment acknowledgments, must we submit a signed SF 1442, technical approach, bill of materials, drawings, installation plan, or separate representations and certifications? Are there file-format, attachment-size, or page limits?

• Completed schedule of Items

• A document demonstrating recent and relevant experience and past performance in respect to the size and scope of this particular project. See page 19 for specific information to include.

• Acknowledge Amendments (per the instructions in Block 11 on the SF-30) if applicable.

53. Does the stated project magnitude of “less than $25,000” represent an estimated range or a maximum available budget? Estimated range.

Manufacturer authorization and qualifications

54. ADI 1.20(D) requires an authorized installer of the “approved end-to-end solution,” with manufacturer authorization provided at proposal submission. Which cabling manufacturers/product systems are approved? May bidders propose a system for approval, and must the cable, jacks, patch panels, and patch cords belong to the same manufacturer’s system?

Contractors should propose a system for approval; products must be compatible across systems.

55. What evidence satisfies the manufacturer authorization requirement: a company installer/partner certificate, manufacturer letter, individual technician credentials, or another document? Must authorization be held by the prime contractor, or may an authorized installation subcontractor satisfy it? All of the above would satisfy this req’mt; authorized installation subcontractor satisfies req.

56. ADI 1.20(A) requires licensing in the state where work is performed. Please identify the credentials expected for this project. For low-voltage cabling work exempt from individual electrical licensing under Montana law, will documentation of that exemption, together with any applicable construction contractor business license, satisfy the requirement? Any state license is OK, except for electrical work.

57. ADI 1.20(C) specifies at least five years of experience. Must that experience belong to the prime company, or may the qualifications of proposed personnel or subcontractors satisfy it?

What evidence is required? Subcontractors ok.

58. ADI 1.20(E) includes fiber installation, splicing, light-meter, and OTDR qualifications. Are these required for this Cat 6 project even if no fiber work is included? Please identify the specific personnel certifications or acceptable equivalent evidence required for the copper work. Fiber qualifications not req’d for cat 6 project.

59. The ADI Guidelines contain both requirements and recommendations for typical installations. Please identify which provisions apply to this project, particularly where they extend beyond the project-specific SOW. Are outside conduit, trenching/boring, fiber extensions, or POTS-in-a-Box work included? Only provisions related to the installed equipment are applicable.

60. Does “51 new Category 6” mean 51 individual cable runs/terminated ports, rather than 51 outlet locations containing multiple cables? Please confirm the workstation and wireless-access-point port counts and whether WAP cables terminate at jacks or directly at device plugs. 51 individual cable runs / terminated ports. Identify WAP (wireless access point) locations Four WAP locations are identified on the site plan in the hallways. High wall or ceiling mounts are acceptable.

61. Please specify the required cable jacket/fire rating, shielded or unshielded construction, termination scheme, outlet configuration, patch-panel capacity, and spare capacity. Must bidders provide two patch cords per cable run as recommended in ADI §1.23? If so, what lengths are required? CIO

62. Which cabinet option—A, B, or C—is required? The guide associates option C with more than 18 cable runs/users, while the SOW permits selection among three options. Please confirm the required cabinet capacity, dimensions, shelves, cable management, fans, security features, and whether equivalent products are acceptable. All are acceptable. Equivalent products are acceptable.

63. Does an existing dedicated 120V, 20A circuit with a suitable receptacle already serve the IT room? If not, please identify the panel location, available breaker capacity, approximate route length, and required receptacle location/type. May the prime subcontract this work to a qualified, Montana-licensed electrical contractor? Yes, a dedicated 120V, 20A circuit with a suitable receptacle already serves the IT room. Yes, MT contractor.

64. Please identify the existing building grounding/bonding provisions and the approximate distance from the new cabinet/TMGB to the building grounding connection. Does the project require upgrades to the building grounding system or installation of additional ground rods if existing conditions do not meet ADI §1.11? No upgrades to building grounding. Ground to existing ground rod.

65. Is the existing wall/backboard suitable for the selected cabinet and equipment weight?

Please identify any required wall reinforcement, firestopping, finish restoration, or other building work, and any known hazardous-material conditions or restrictions affecting drilling, penetrations, or cable removal. Wall is suitable for equipment weight. No hazmat conditions.

66. Which existing cables must be removed, and how will active cables be identified and protected? Does removal include abandoned supports, outlets, or patch panels? Please confirm disposal requirements and whether existing equipment relocation, reconnection, WAP mounting, or network configuration is included. CIO

67. Is a pre-bid site visit available or required? Please confirm the correct address: the SOW lists 330 Gallatin Road, while solicitation page 4 lists 331 U.S. 191. Both addresses point to the correct location in Google Maps; 331 US 191 is correct.

68. Please confirm the required Category 6 test standard/revision and link configuration for Level III certification testing. What tester calibration evidence and report formats are required?

Please also specify the as-built drawing contents, labeling convention, acceptance process, and required materials/labor or manufacturer system warranty. CIO

69. For the five required past performance projects, may separately completed projects or task orders under the same client/master agreement be submitted as individual references, provided each has its own scope, dates, value, and verifiable customer contact? Yes.

70. CAT6 quantity: The SOW specifies 51 new CAT6 cable runs. Is an estimated total footage available, or should bidders determine the required length from the referenced floor plan?

Estimate lengths from floor plan.

71. CAT6 specifications and color: Please confirm the required cable color, shielded or unshielded construction, jacket rating (plenum or riser), conductor gauge, and whether solid bare copper is required. Is moisture-resistant or outdoor-rated cable required for the crawl-space installations? CIO

72. Faceplates and termination materials: Please confirm the required faceplate type, color, material, gang size, and number of ports per faceplate. Please also specify the quantities of faceplates, CAT6 keystone jacks, and back boxes or surface-mount boxes. CIO

73. Patch cords and patch panels: Please confirm the required patch cord quantities, lengths, and colors for both ends of each connection, along with the patch panel quantity, type, and port capacity. CIO

74. Cable pathways and supports: Please confirm whether existing pathways may be reused and specify any required conduit, raceway, or cable supports, including their types, sizes, and estimated quantities. CIO

75. IT cabinet and accessories: Which of the three cabinet sizes listed in the SOW should bidders provide? Please confirm the required quantity and the number of shelves and cable managers.

Choose best option for the work.

76. UPS and PDU: Please confirm the required quantities, UPS capacity and runtime, mounting arrangement, and PDU plug and receptacle types. CIO

77. Backboard and grounding: Please confirm whether one fire-rated 4ʹ × 8ʹ plywood backboard Yes and one telecommunications main grounding busbar Yes are required. Please also specify the grounding conductor size and approximate connection distance. Grounding: CIO

78. Dedicated electrical circuit: Please confirm whether a suitable dedicated 120V, 20A circuit is already available. If a new circuit is required, what is the approximate distance from the electrical panel to the cabinet? Yes.

79. Equipment supply and cable removal: Please identify any Government-furnished equipment, confirm whether network switches and wireless access points must be supplied by the contractor, and provide the approximate quantity of existing cabling to be removed. CIO

80. Wall Construction: Could you please confirm the wall composition where the 4' × 8' fire-rated plywood backboard and IT cabinet will be installed? Specifically, is the wall constructed of drywall with metal studs, wood studs, or concrete masonry? 2X4 wood framing w/ drywall.

81. Ceiling Environment: Could you please confirm whether the facility has standard drop-tile ceilings (plenum or non-plenum), open/exposed ceilings, or hard ceilings? Additionally, please clarify whether plenum-rated cabling is required. Hard ceiling in IT room only, rest of basement is open ceiling.

82. Manufacturer authorization: ADI Guidelines 1.20.D states the contractor "must be an authorized installer of the approved end-to-end solution," with proof at time of proposal. The SOW and Schedule of Items name no manufacturer. Please confirm this provision does not apply to this copper-only Category 6 project and that any TIA-568 compliant Category 6 components, installed and Level III certified per the SOW, are acceptable. If a specific manufacturer is required, please name it. Contractors should propose a system for approval;

products must be compatible across systems.

83. State licensing: ADI 1.20.A requires licensing in the state where work is performed. Is the site under exclusive federal jurisdiction? If not, is a Montana Construction Contractor License required at time of quote or only prior to performance, and does this requirement apply to subcontractors? Licensed in A State.

84. Electrical: Is a dedicated 120V 20A circuit already present in the IT room? Yes.

85. Schedule and weather: We plan to begin immediately after award in order to complete the work before deep winter. Given the Nov 1 to Dec 31 performance window, will the Government allow time extensions for weather delays? Yes.