1240LU25Q0059 Attachment 2 Statement of Work..docx
DOCX document 932 KB Posted
- Solicitation number
- 1240LU25Q0027
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for a North Country Trail maintenance project in North Dakota, issued by the U.S. Forest Service. The contract consists of two primary items: Base Item involves restoring and resurfacing approximately 19,480 linear feet of the North Country Trail, including installation of Geogrid over 6,670 feet using Modified ND Class 13 Aggregate Surfacing Compacted in Place. Optional Item 1 includes restoring and resurfacing the West trailhead with 200 cubic yards of similar aggregate surfacing. The project is located in the Sheyenne Ranger District across Richland and Ransom Counties, with a construction magnitude between $100,000 to $250,000. Key technical requirements include equipment cleaning to prevent noxious weed spread, precise trail bed preparation, specific aggregate surfacing specifications, geogrid installation techniques, and strict adherence to environmental and traffic control guidelines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 – SCOPE OF CONTRACT
The contract consists of two items. The government intends to award all the items dependent on the bid prices. If the total quote exceeds the available funding, items shall be selected on a per item basis.
Base Item of this contract consists of restoring and resurfacing approximately 19,480’of the North Country Trail. Additionally, it includes the restoration, resurfacing and installation of Geogrid over 6,670’of the trail, all using Modified ND Class 13 Aggregate Surfacing Compacted in Place.
Optional Item 1 consists of restoring and resurfacing the West trailhead with 200cy of Modified ND Class 13 Aggregate Surfacing Compacted in Place.
This contract requires furnishing labor, equipment (fully operated), supervision, transportation, operating supplies, and incidentals to complete this project in accordance with the Plans, Drawings, Specifications, and Special Project Provisions of this contract. Contractor is required to get an Off Highway Vehicle Permit before construction begins.
The contractor shall be required to have a mapping program, like Avenza Maps, on their smart phone, tablet or GPS device that can read the pdf maps provided in the contract to display and locate the contract items.
C.2 – PROJECT LOCATION
The project is located on the Sheyenne Ranger District in Richland and Ransom County, North Dakota. See attached maps.
C.3 – MAGNITUDE OF CONSTRUCTION PROJECT
The Magnitude of Construction for this project is between $100,000 to $250,000
C.4 – GENERAL SPECIFICATIONS
Existing Facilities. In addition to the requirements of the Use of Premises Clause, AGAR 452.236-70, all existing facilities structures damaged by the Contractor shall be replaced or repaired by the Contractor at no additional cost to the Government. This includes any facilities inside or outside the project limits, including along any access routes. Do not trim or damage vegetation except with specific Contracting Officers (CO) approval.
Pollution and Erosion Control. During all operations under this contract, the Contractor shall exercise reasonable measures to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes, from the Contractor's operations, including camps, parking areas, and equipment maintenance areas shall be stored, collected, and disposed of in a sanitary and nuisance-free manner. Refuse shall be disposed of in State-approved landfills unless otherwise approved by the Contracting Officer
(CO).
Storage and Stockpiling. The Contractor shall confine storage of equipment, materials, and vehicles to within the limits delineated by the Contracting Officer. The Contractor shall be solely responsible for the loss of or damage to materials stored on Forest Service lands or elsewhere.
Worksite Cleanliness and Final Cleanup. Maintain the project work areas in a clean and orderly condition throughout the progress of work under this contract. All refuse, including garbage, rubbish, and solid or liquid wastes from the Contractor's operations shall be stored and collected in a sanitary manner and disposed of off Government property in a legal manner.
Maintain strict control of hazardous materials to prevent contamination of the site.
Noxious Weed Control. To prevent the potential spread of noxious weeds, the Contractor is required to furnish weed-free equipment. The Contractor’s equipment shall be cleaned to remove all dirt and plant parts and material that may carry noxious weed seeds into the construction area.
All subsequent move-ins shall be treated the same as the initial move-in. Prior to move-in the Contractor shall make equipment available to Forest Service inspection at an agreed location.
Submittals.
· Aggregate weed free certification.
· Aggregate Gradation Test
· Geogrid
Traffic Control – The Contractor shall exercise due caution and care during road maintenance operations to prevent undue conflict with public users of the roads.
• Perform work in a manner that ensures the safety and convenience of the public and protects the private property adjacent to the project. Accommodate public traffic on roads adjacent to and within the project until the project is accepted.
• All road and traffic related signing shall be in accordance with the Manual on Uniform Traffic Control Devices (MUTCD).
• A reflectorized "Slow Moving" vehicle emblem shall be attached to all motor patrols.
• The Contractor is to post warning signs on both ends of the section being worked to warn the road users of the work in progress. Signs will be moved, as needed, so that a sign does not precede machinery more than two (2) miles.
• If a berm is left in roadway overnight or weekends due to weather conditions or breakdowns, it shall be properly signed as a hazard and visibly illuminated at night.
C.6 TECHNICAL SPECIFICATIONS
101 – Mobilization
Description
Work. This work consists of moving personnel, equipment, material and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the costs associated with obtaining permits, insurance, and bonds. Mobilization is not intended to pay the costs of materials before they are used on the project site. Work also includes cleaning of all equipment used at the project site. Clean all construction equipment prior to entry on the project site. Remove all dirt, plant parts and material that may carry noxious weed seeds into the area. Only construction equipment inspected by the Forest Service will be allowed to operate within the project area. Treat subsequent move-ins of equipment the same as the initial move-in. Clean truck beds and dump boxes hauling to the project site prior to entering the work area.
Payment
Basis. Pay for the accepted work at the contract unit price for the PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS.
(a) Reimburse for bond premiums before issuing the Notice to Proceed if evidence of payment is received.
(b) When 5 percent or more of the original contract amount is earned from other PAY ITEMS, pay mobilization at the rate of 50 percent, or up to 5 percent of the original contract amount, whichever is less.
(c) When 10 percent or more of the original contract amount is earned from other PAY ITEMS, pay mobilization at the rate of 100 percent, or up to 10 percent of the original contract amount, whichever is less.
(d) Pay any unpaid amount for mobilization upon final acceptance of all work items.
Make payment under:
PAY ITEM PAY UNIT
101 Mobilization …………………………………………………………. .LS
102-Trail Surfacing Description
Preparation of Subgrade.
Restore the trail template to its original condition by removing slough and berm. Fill ruts and troughs and reshape back slopes. Restore drainage and other trail structures. Remove all duff, debris, stumps, roots, and excavation from within trail bed. The trail bed shall be smooth and free of irregularities. Place all excavated material, regardless of its nature, from within the trail way and uniformly spread 4 feet outside the trail way, on the downslope, not more than 4 inches in depth. Do not obstruct drainage or create piles, berms, or windrows of debris. During all phases of construction use reasonable measures to minimize damage to the soil including offsetting wheel tracts.
Slough and Berm Use suitable slough material within the trail way to restore the trail bed. Remove berm when daylight can be obtained with a maximum tread width of 5 feet unless otherwise DESIGNATED ON THE GROUND.
Fill Material and Borrow.
Use suitable material to fill ruts, troughs, and potholes in the tread that cannot be leveled and out sloped through performance of work.
Reshaping and Finishing Trailbed and Back slopes.
Provide a firm and uniformly finished trail bed in accordance with drawings. Leave no vertical backslopes. Provide a uniform and roughened surface on disturbed backslopes.
Surfacing Furnish, haul, water, place and compact the aggregate surfacing on the prepared trail bed. Surfacing material shall be free of excess moisture, frozen lumps, roots, sod, or other deleterious material. Do not furnish material that contains weeds or weed seed. The COR shall approve the physical characteristics and quality of the materials before placing on the trail.
Spreading and Compacting Use aggregate that is uniformly mixed at optimum moisture content and spread and compact in layers to the final thickness and width SHOWN ON THE DRAWINGS. Adjust the moisture content of the material to a moisture content suitable for compaction. Remove irregularities and produce a smooth, even surface. Obtain compaction by mechanical vibratory compactors over the full area until visual displacement ceases, but not fewer than three passes. A pass shall consist of one complete coverage of the surface. Obtain written approval of the trail bed by the COR before placing aggregate.
Handling Materials.
Stockpile, remove, transport, and spread aggregates in a manner that shall preserve gradation and avoid contamination. Do not intermingle stockpiles of aggregate having different gradations. Remnants of the aggregate stockpiles located along the trail shall be uniformly spread 4 feet outside the trailway limits, not more than 2 inches in depth. Do not obstruct drainage or create piles, berms, or windrows of debris
Haul Roads.
The Contractor shall maintain haul routes to pre hauling condition or better and inspect haul routes prior to hauling aggregate. Dust caused by hauling operations on roads that create a hazard to traffic or a nuisance to the public shall be treated with dust abatement as necessary to control the dust. On County roads the contractor shall coordinate with county road superintendents, to determine which dust control measures will be used. Contractor shall reduce speed to 25 miles per hour or less when hauling adjacent to occupied structures.
Tolerances.
Do not vary the total compacted thickness of the aggregate by more or less than ½ inch from the specified thickness or place it consistently below or above the specified depth. Do not vary the aggregate width by more than 3 inches from the specified width or place it consistently narrower or wider than the specified width. On flat trail way segments with no side slope, aggregate shall have a one-inch crown on the aggregate surface. In no case shall the final grade of the compacted aggregate be lower than the existing ground line.
Measurement. Measure the Section 102 pay items listed in the bid schedule according to section 906
The method of measurement is Compacted in Place quantities.
Payment
Basis. Pay for the accepted quantities in accordance with Section 906 at the contract unit price of each PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS.
Make payment under:
Pay Item Pay Unit
102 Trail Surfacing ……………………………………. LF
103-Geogrid
Placing and Overlapping Unroll the geogrid in the direction of travel so that the roll is parallel with traffic patterns. Adjacent geogrid roll should be shingled in the intended direction of aggregate spread. Cut and overlap the geogrid to accommodate curves. Overlap the geogrid 2’ at the ends.
Tensioning and Pinnning Place the geogrid flat and free of tension, stress, or wrinkles and without tearing or causing damage. Damaged geogrid will be rejected by the CO and replaced at the contractor expense.
Geogrids may be anchored in place to maintain overlaps and alignment over the coverage area. Before fully unrolling the geogrid, hold the geogrid in place with pins, staples or piles of aggregate.
Spreading and Compacting Aggregate Prepare all trail construction as required under Section 102. and the following: place the aggregate onto the geogrid from the edge of the geogrid or from previously placed aggregate. Don’t operate equipment directly on the geogrid. Turns and sudden stops should be avoided. The maximum thickness of any one layer shall be 6 inches loose thickness. Use approved methods to compact aggregate surfacing.
NOTE: The Geogrid may be Tensar HX5.5 Geogrid or an approved equal. An “equal” item shall comply with the salient physical, functional, and performance characteristics provided in the Description of work. (FAR 11.104 –Use of Brand Name or Equal Purchase Descriptions).
Measurement. Measure the Section 103 pay items listed in the bid schedule according to section 906
Use the method of measurement that is DESIGNATED IN THE SCHEDULE OF ITEMS.
Payment
Basis. Pay for the accepted quantities in accordance with Section 906 at the contract unit price of each PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS.
Make payment under:
Pay Item Pay Unit
103 Geogrid ……………………………………. LF
201-Trailhead Surfacing
Preparation of Subgrade.
Clear the existing Trailhead (TH) of vegetation and obstructions and place the excavation adjacent to the TH in approved locations. Do not damage vegetation designated to remain. If damage occurs, repair or replace the vegetation in an acceptable manner. Blade the full length and width of the TH (150’ x 75’) to provide adequate water runoff and restore the original cross section and grade. After the finish blading the TH shall be smooth, free of berms and ruts and shall be crowned or graded to drain (2%-6%). No existing surfacing or road material shall be wasted.
Spreading and Compacting.
Furnish, haul, water, place and compact 200 cy of aggregate surfacing evenly over the full length and width of the TH. Spread and shape the aggregate on the prepared surface in a uniform layer. Blade the surface during the compaction operations to remove irregularities and produce a smooth surface. Compact the aggregate on the TH by operating spreading and hauling equipment, or other approved methods, over the full width of each layer of the aggregate until visual displacement ceases.
Measurement. Measure the Section 201 pay items listed in the bid schedule according to section 906
Use the method of measurement that is DESIGNATED IN THE SCHEDULE OF ITEMS.
Payment
Basis. Pay for the accepted quantities in accordance with Section 906 at the contract unit price of each PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS.
Make payment under:
Pay Item Pay Unit
101 Trail Aggregate Surfacing ……………………………………. LF Trailway
Aggregate Surfacing Gradation Requirements
Modified North Dakota DOT class 13 specification
| Sieve Size |
| Percent Passing Designated Sieve |
| 1” |
| 100 |
| ¾” |
| 70-100 |
| No. 4 |
| 38-75 |
| No. 8 |
| 22-62 |
| No.30 |
| 12-45 |
| No. 200 |
| 10-17 |
L.A. Abrasion 50% maximum allowable percentage.
Shale 12% maximum allowable percentage.
Fractured Faces 10% minimum weight percent allowable.
Provide material consisting of sound, durable particles of gravel or sand which may include limited quantities of fine soil particles as binding material. Use material that is free of any deleterious material or organic material.
DPG SPS 301-1/25