1240LU25Q0059 Questions and Answers GAOA North Country Trail DPG.docx

DOCX document 646 KB Posted

Attached to
GAOA North Country Trail Maintenance Dakota Prairie Grasslands
Solicitation number
1240LU25Q0027
Issued by

About this file

This document is a Questions and Answers file for the GAOA North Country Trail Maintenance Dakota Prairie Grasslands project. The file contains two specific questions from a potential contractor: first, requesting photos showing the condition of existing trails that need repairs, and second, inquiring about gravel requirements for 221 trail locations. The agency response clarifies that there is no existing aggregate in areas designated for surfacing, indicating that new gravel will likely need to be hauled in for trail maintenance. Two images (image1.png and image2.png) are referenced, which presumably show trail conditions, though their specific contents are not detailed in the text. The project is associated with the Department of Agriculture Forest Service and involves maintenance of the North Country Trail within the Dakota Prairie Grasslands.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers GAOA North Country Trail Maintenance Dakota Prairie Grasslands project.

Do you have any photos that generally show the condition of the existing trail in some of the areas that need repairs?

Are you anticipating that additional gravel would need to be hauled to all 221 locations or would most locations only require re-grading the existing material at each location?

Yes “There is no existing aggregate in areas designated for surfacing.”