UNITED STATES FOREST SERVICE, ROCKY MOUNTAIN REGION 2, ROAD AND BRIDGE CONSTRUCTION SERVICES MATOC
Solicitation number
1240LU24R0013
Issued by

About this file

This document contains specifications for the construction of roads and bridges on federal highway projects, including details on project terms, format, and definitions, scope of work, control of work, control of materials, acceptance of work, legal relations, prosecution and progress, measurement and payment, and other technical requirements. It appears to be a set of standard construction specifications that would be incorporated into a federal contract opportunity.

The related federal contract opportunity is a solicitation from the United States Forest Service (USFS), Rocky Mountain Region 2, for an Indefinite Delivery-Indefinite Quantity (IDIQ), Multiple Award Task Order Contract (MATOC) for road and bridge construction and related services. The geographic scope is limited to USFS Region 2 Forests and Grasslands, under NAICS code 237310 with a $45 million size standard. The MATOC will include a base two-year period with three one-year option periods, for a total of five years. Task orders will range from $2,000 to $3,000,000 with a $50,000,000 shared ceiling limit. The solicitation will be issued as a total small business set-aside, with a minimum of ten individual MATOC contracts to be awarded. Interested offerors must be registered in the System for Award Management (SAM.gov). The solicitation is anticipated to be available on SAM.gov in late July 2024.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES

ON FEDERAL HIGHWAY PROJECTS

Specification List

Project Name: S. Cottonwood Creek

Bridge # 344-3.04, Pike-San Isabel

National Forest Title Date Prepared 9/15

(Latest Revision Date)

Specification Number:

101 Terms, Format, and Definitions 2014

FSSS 101 Terms, Format, and Definitions 9/15

102 Bid, Award, and Execution of Contract 2014

FSSS 102 Bid, Award, and Execution of Contract 9/15

103 Scope of Work 2014

FSSS 103 Scope of Work 9/15

104 Control of Work 2014

FSSS 104 Control of Work 9/15

105 Control of Material 2014

FSSS 105 Control of Material 9/15

106 Acceptance of Work 2014

FSSS 106 Acceptance of Work 9/15

107 Legal Relations and Responsibilities to the Public 2014

FSSS 107 Legal Relations and Responsibilities to the Public 9/15

108 Prosecution and Progress 2014

FSSS 108 Prosecution and Progress 9/15

109 Measurement and Payment 2014

FSSS 109 Measurement and Payment 9/15

151 Mobilization 2014

152 Construction Survey and Staking 2014

FSSS 152 Construction Survey and Staking 9/15

153 Contractor Quality Control 2014

FSSS 153 Contractor Quality Control 9/15

154 Contractor Sampling and Testing 2014

FSSS 154 Contractor Sampling and Testing 9/15

155 Schedules for Construction Contracts 2014

FSSS 155 Schedules for Construction Contracts 9/15

156 Public Traffic 2014

FSSS 156 Public Traffic 9/15

157 Soil Erosion Control and Sediment Control 2014

FSSS 157 Soil Erosion Control and Sediment Control 9/15

201 Clearing and Grubbing 2014

FSSS 201 Clearing and Grubbing 9/15

202 Additional Clearing and Grubbing 2014

203 Removal of Structures and Obstructions 2014

FSSS 203 Removal of Structures and Obstructions 9/15

204 Excavation and Embankment 2014

FSSS 204 Excavation and Embankment 9/15

207 Earthwork Geosynthetics 2014

Specification LIst Page 1 of 2

208 Structure Excavation and Backfill for Selected Major Structures 2014

FSSS 208 Structure Excavation and Backfill for Selected Major Structures 9/15

209 Structure Excavation and Backfill 2014

211 Roadway Obliteration 2014

FSSS 211 Roadway Obliteration 9/15

251 Riprap 2014

FSSS 251 Riprap 9/15

301 Untreated Aggregate Courses 2014

FSSS 301 Untreated Aggregate Courses 9/15

314 Stockpiled Aggregates 2014

FSSS 314 Stockpiled Aggregates 9/15

552 Structural Concrete 2014

FSSS 552 Structural Concrete 9/15

554 Reinforcing Steel 2014

FSSS 554 Reinforcing Steel 9/15

555 Steel Structures 2014

556 Bridge Railing 2014

562 Temporary Works 2014

563 Painting 2014

FSSS 563 Painting 9/15

564 Bearing Devices 2014

FSSS 564 Bearing Devices 9/15

605 Underdrains, Sheet Drains, and Pavement Edge Drains 2014

611 Water Systems 2014

FSSS 611 Water Systems 9/15

617 Guardrail 2014

FSSS 617 Guardrail 9/15

624 Topsoil 2014

FSSS 624 Topsoil 9/15

625 Turf Establishment 2014

FSSS 625 Turf Establishment 9/15

633 Permanent Traffic Control 2014

635 Temporary Traffic Control 2014

FSSS 635 Temporary Traffic Control 9/15

636 Traffic Signal, Traffic Counter, Lighting, and Electrical Systems 2014

FSSS 636 Traffic Signal, Traffic Counter, Lighting, and Electrical Systems 9/15

FSSS 703 Aggregate 9/15

FSSS 709 Reinforced Steel and Wire Rope 9/15

FSSS 711 Concrete Curing Material and Admixtures 9/15

FSSS 714 Geosynthetic Material 9/15

FSSS 717 Structural Metal 9/15

FSSS 719 Paint 9/15

Note: All of the specifications cited are applicable to this project. The Forest Service Supplemental Specifications (FSSS) must be incorporated into the FP-14 specifications.

Other specifications referred to within these specifications (even though not specifically listed herein) are also fully applicable to this project.

Specification LIst Page 2 of 2

101 - Terms, Format, and Definitions

101.01_nat_04_02_2004

101.01 Meaning of Terms.

Add the following:

Delete all references in FP-14 to Transportation Acquisition Regulations (TAR). For Timber

Sales, delete all references in FP-14 to Federal Acquisition Regulations (FAR).

101.03_nat_04_02_2004

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NEC

WCLIB

WWPA

ALSC

WWPI

NLGA

NSLB

NLMA

RIS

SPIB

American Forest and Paper Association

Mine Safety and Health Administration

National Electrical Safety Code

West Coast Lumber Inspection Bureau

Western Wood Products Association

American Lumber Standards Committee

Western Wood Preservers Institute

National Lumber Grades Authority

Northern Softwood Lumber Bureau

Northeastern Lumber Manufacturer’s Association

Redwood Inspection Service

Southern Pine Inspection Bureau

101.04_nat_04_29_2004

101.03 Abbreviations.

Add the following to (b) SI Symbols:

mp Milepost ppm Part Per Million

Forest Service Supplemental Specifications

(FSSS)

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line

(including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition

Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or

“design change” as used in the Timber Sale Contract.

Design Quantity-- “Design quantity” is a Forest Service method of measurement from the FS-96

Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Lump Sum Quantity-- “Lump sum quantity” (“LSQ”) – These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the

Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36

CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, methods of measurement, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Figure 101-1—Illustration of road structure terms.

R ig h t o f

W a y

R o a d si d e R o a d s id e

C le a ri n g W id th

R o a d w a y C le a ri n g L im it

X Y

G ro u n d

L in e

T ra v e le d

W a y

C L B e rm

S u rf a c e

C o u rs e B a s e

C o u rs e

F ill

S lo p e

B a c k S lo p e

D ra in a g e D itc h

G ro u n d L in e

S u b g ra d e

R o a d

B e d

S h a p e s a n d d im e n s io n s w ill v a ry t o f it lo c a l c o n d iti o n s

S e e d ra w in g s f o r ty p ic a l s e c tio n s

X a n d

Y d e n o te c le a ri n g o u ts id e o f ro a d w a y

N o te

Right - of - Way Line

Right - of - Way Line

Clearing Limit

Shoulder

Shoulder

102 - Bid, Award, and Execution of Contract

102.00_nat_03_27_2004

102 Delete

Delete Section 102 in its entirety.

103 - Scope of Work

103.00_nat_04_02_2004

103 Delete

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work

104.01_nat_03_27_2004

104 Control of Work.

Delete sections 104.01 and 104.02.

104.03_nat_03_23_2004

104.03 Specifications and Drawings.

Add the following:

(c) As-Built-Plans. Furnish one set of as built plans. The Government will provide one set of contract plans to be used exclusively for recording the as-built details of the project. Use red pencil or red ink to record the information on the as-built plans.

Note all additions or revisions to the location, character, and dimensions of the prescribed work shown on the contract plans. Line out all details shown that are not applicable to the completed work. Check off details shown that were incorporated into the completed work without change.

Retain the plans at the project site and, as work progresses, continually update them to reflect the as-built details. Upon request, make the plans available to the CO to review for compliance with these specifications.

Show the following types of changes on the as-built plans:

(1) Typical section(s)

(a) Revisions in dimensions

(b) Revisions in materials

(2) Plan and profile

• Revisions to the alignment

• Changes in the construction limits

• Revisions in location, type, and grade of road approaches

• Location and type of utilities

• Location, size, and type of underdrains

• Skew of culverts

• Channel changes

• Location of monuments and permanent references

• Locations for all aerial and underground crossings of utilities

• Location, length, and type of fencing

• Revisions to grades, elevations, and stationing of intersection PIs

• Equations

• Culvert diameter, length, type, and stationing. On culvert extensions, indicate the length of the existing pipe and the length of the extension.

• Location, length, stationing, and type of retaining walls

• Location, length, stationing, and end treatment of guardrail

(3) Bridge

(a) Stationing of bridge ends

(b) Revisions to footing and seal elevations

(c) Pile length, size, type, and tip elevation

(d) Any changes in plan or dimensions including any major changes in reinforcing

(4) Miscellaneous

(a) Revisions to parking areas or turnouts

(b) Final location, type and length of curbs, sidewalks, etc.

Furnish the as-built working plans to the CO before the final inspection. Correct all details found during the final inspection that are not shown on the as-built plans and return to the CO within 5 days.

104.04 Coordination of Contract Documents.

Replace with the following:

The special contract requirements, standard specifications, and plans are contract documents. A requirement in one document is binding as though occurring in all contract documents. The contract documents are intended to be complementary and to describe and provide for a complete contract. In case of discrepancy, calculated and shown dimensions govern over scaled dimensions. The contract documents govern in the following order:

(a) Special contract requirements;

(b) Standard specifications; and,

(c) Plans.

104.05_nat_03_23_2004

Add the following subsections:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

104.07 Other Contracts.

The contractor shall schedule activities to coordinate and cooperate with other contracts, when applicable.

105 - Control of Material

105.02_nat_03_26_2004

105.02 Material Sources.

105.02(a) Government Provided Sources.

Add the following:

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.02(c) Contractor-located sources.

Add the following:

All certifiable material (e.g., soil, gravel, seed, mulch etc.) transported onto National Forest

System land or incorporated into the work will be weed-free. The Contracting Officer may request written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed-free status must be appropriate for the weeds of concern in the local area.

All seed and mulch materials must be certified weed free.

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work

106.01 Conformity with Contract Requirements.

Delete Subsection 106.01 and substitute the following:

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more restrictive.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the

Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Three methods of determining conformity and accepting work are described in Subsections 106.02 to

106.04 inclusive. The primary method of acceptance is specified in each Section of work.

However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

(1) Sampling method;

(2) Number of samples;

(3) Sample transport;

(4) Test procedures;

(5) Testing laboratories;

(6) Reporting;

(7) Estimated time and costs; and

(8) Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.

Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.

If the validity of the Government test results cannot be determined, the Contractor and

Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

(1) Have the work accepted at a reduced price; or

(2) Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.05 Statistical Evaluation of Work and Determination of Pay Factor (Value of Work).

Replace the entire section with the following:

Statistical evaluation of the work will not be required. All specifications referring to this

Subsection shall instead be referred to Subsections 106.02 through 106.04 as appropriate for the work performed.

106.07_nat_04_02_2004

106.07 Partial and Final Acceptance

Delete subsection 106.07.

107 - Legal Relations and Responsibility To the Public

107.02 Protection and Restoration of Property and Landscape.

Add the following:

Work within the channel shall only be performed between August 1 and October 15.

107.05 Responsibility for Damage Claims.

Delete subsection 107.05.

107.06 Contractor’s Responsibility for Work.

Delete the following:

“except as provided in Subsection 106.07”.

107.08_nat_03_24_2004

107.08 Sanitation, Health, and Safety.

Add the following:

Perform all operations in a prudent, conscientious, safe and professional manner. Ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29

CFR 1910.120. Notify the Forest Service of all hazardous material that may be brought onto the

National Forest.

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

107.09 Legal Relationship of the Parties.

Delete subsection 107.09.

107.10_nat_03_24_2004

107.10 Environmental Protection.

(c) Dirt, plant, and foreign material

Noxious weed control requirements:

Clean all construction equipment prior to entry onto the project area. Remove all dirt and plant parts and material that could carry noxious weed seeds into the project area. Only construction equipment so cleaned and inspected by the Forest Service will be allowed to operate within the project area. Treat all subsequent move-ins of construction equipment in the same manner as initial move-ins. “Construction equipment” does not include personal vehicles, paving equipment or support equipment that remains on the main travel route.

Prior to the initial move-in, the contractor shall make all construction equipment available for inspection by the Forest Service at an agreed upon location. Provide the Forest Service at least

48 hours advance notification when equipment is ready for inspection.

New infestations of noxious weeds, of concern to Forest Service and identified by either

Contractor or Forest Service, on the Project Area or on the haul route, shall be promptly reported to the other party. Contractor and Forest Service shall agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found.

107.11 Protection of Forests, Parks, and Public Lands:

Fire Precautions. Specific fire precautionary measures listed below shall be applicable during

Contractor’s Operations in “Fire Precautionary Period” described as between June 1 st and August st . Contracting Officer may change the dates of Fire Precautionary Period by advance written notice, if justified by unusual weather or other conditions. Required tools and equipment shall be kept in serviceable condition and immediately available for fire fighting at all times during

Contractors Operations in Fire Precautionary Period.

Substitute Precautions. Forest Service may authorize substitute measures or equipment, or waive specific requirements by written notice, if substitute measures or equipment will afford equal protection or some of the required measures and equipment are unnecessary.

Emergency Precautions. Forest Service may require the necessary shutting down of equipment on portions of Contractor’s Operations, as specified by the emergency fire precautions as listed below.

Fire Control. Contractor shall, both independently and in cooperation with Forest Service, take all reasonable and practicable action to prevent and suppress fires resulting from Contractor’s

Operations and to suppress any forest fire in the project area. Contractor’s independent initial fire suppression action on such fires shall be immediate and shall include the use of all necessary personnel and equipment at Contractor’s disposal on site.

Fire Suppression Costs. Contractor’s obligations for cost of fire suppression vary according to three classifications of fires as follows:

Operations Fire. An “Operations Fire” is a fire caused by Contractor’s Operations other than a Negligent Fire. Forest Service shall under 16 USC 572, perform fire suppression activities on Operations Fires. Contractor agrees to reimburse Forest Service for such cost for each Operations Fire, subject to a maximum of the cost to suppress the fire.

Negligent Fire. A “Negligent Fire” is a fire caused by negligence or fault of Contractor’s

Operations, including, but not limited to, one caused by smoking by persons engaged in

Contractor’s Operations during the course of their employment, or during rest or lunch periods; or if Contractor’s failure to comply with the fire prevention requirements results in a fire starting or permits a fire to spread. Damages and the cost of suppressing Negligent Fires shall be borne by Contractor.

Other Fires on Construction Project Area. Forest Service shall pay Contractor, at fire fighting rates common in the area or at prior agreed rates, for equipment or personnel furnished by Contractor at the request of Forest Service, on any fire on Project Area other than an Operations Fire or a Negligent Fire.

Other.

1. Smoking and Lunch Fires. Smoking is prohibited except inside a building, developed recreation site, vehicle, or while seated in an area of at least three feet in diameter that is barren or cleared of all flammable materials. 36 CFR 261.52(d).

The building of camp, lunch, warming and other fires within the sale area and vicinity is prohibited, except at established camps or at other safe places where all flammable material has been cleared away sufficiently to prevent the start and spread of wildfires. Forest Service may, upon written request of Contractor, designate specific places where campfires may be built for purposes of heating lunches.

2. Spark Arrester and Mufflers. Operating or using any internal combustion engine, on any timber, brush, or grass covered land, including trails and roads traversing such land, without a spark arrester, maintained in effective working order, meeting either (I) Department of

Agriculture, Forest Service standard 5100, "SPARK ARRESTERS FOR INTERNAL

COMBUSTION ENGINES," (current edition); or (II) the Society of Automotive Engineers

(SAE) recommended Practices J335, "MULTIPOSITION SMALL ENGINE EXHAUST

SYSTEM FIRE IGNITION SUPPRESSION," (current revision) and J350, 36 CFR 261.52(j), is prohibited.

Passenger carrying vehicles, pickups, medium and large highway trucks (80,000 GVW) will be equipped with a factory designed muffler system which is specified for the make and model of the respective vehicle/truck or with a muffler system that is equivalent or that exceeds factory specifications.

Exhaust systems shall be properly installed and continually maintained in serviceable condition.

3. Fire Extinguishers and Tools on Equipment. While in use, each internal combustion engine including tractors, trucks, yarders, loaders, welders, generators, stationary engines, or comparable powered equipment shall be provided with at least the following:

(a) One fire extinguisher, at least 5#ABC with an Underwriters Laboratory (UL) rating of

3A - 40BC, or greater.

(b) One shovel, sharp, size O or larger, round-pointed with an overall length of at least 48 inches.

(c) One axe, sharp, double bit 3-1/2#, or one sharp pulaski.

Extinguishers, shovels, axes, and pulaskis shall be mounted so as to be readily available from the ground. All tools shall be maintained in a serviceable condition.

4. Power Saws. Each gasoline engine power saw shall be provided with one chemical-pressurized fire extinguisher of not less than 8-ounce capacity by weight, and one size O or larger, round-pointed shovel with an overall length of at least 48 inches. The extinguisher and shovel shall be maintained in good working order. The extinguisher shall be with the power saw operator and immediately available for use at all times. The extinguisher shall not be affixed to the saw. The shovel shall be readily available to the operator of the saw at all times. Having the shovel with the gas can used to refuel the saw may be considered "readily available" if not more than 200 feet from the saw. During periods of critical fire danger, Forest Service may prescribe other precautionary measures.

Any fueling or refueling of a power saw shall be done in an area which has first been cleared of material which will carry fire. The power saw shall be moved at least 10 feet from the place of fueling or refueling before starting.

5. Blasting and Welding. The use of fuses in blasting shall not be permitted except near power lines where the danger of accidental detonation is present, and then only by special written permission of Forest Service. Whenever the relative humidity falls below 50 percent, Contractor shall place a watchman at each point where blasting is done who shall remain on duty for at least one hour after blasting is finished, and who shall be equipped with a shovel and a water-filled backpack can equipped with hand pump. During periods when the relative humidity falls below

20 percent, blasting shall be discontinued unless authorized, with special provisions, in writing by Forest Service. Blasting shall not be permitted in any area not cleared to mineral soil without advance written approval of Forest Service and with such special precautions as may be required.

Prima Cord shall not be used in clearing operations, and in other areas where timber has been felled and slash not burned.

Unless otherwise directed in writing by Forest Service, all flammable material shall be cleared for 10 feet around any piece of equipment being welded. In addition, Contractor shall provide a fire extinguisher of a size and type designed to extinguish a fire in the flammable materials surrounding the spot being welded.

In order to determine the relative humidity, Contractor shall either (a) provide and maintain weather instruments, that will measure relative humidity, in the area where blasting will occur; or (b) provide communications to obtain weather data from Forest Service.

Explosives shall be stored at all times in a locked box marked "Explosives. "Powder and blasting caps shall be stored in separate boxes.

6. Storage of Flammables. Gasoline, oil, grease and other highly flammable material shall be stored either in a separate building, or at a site where all debris is cleared within a radius of 25 feet. Storage buildings or sites shall be a minimum distance of 50 feet from other structures. Storage buildings shall be adequately posted to warn of the flammables and to prohibit smoking in or around the building.

7. Camp Fire Protection. The grounds around all trailers, buildings, other facilities constructed or placed on or near the project area shall be kept free of flammable material for a distance of at least 20 feet from the wall of such structure.

Stovepipes of all wood burning stoves shall be equipped with suitable roof jacks and serviceable spark arresters. Stovepipes shall be no closer than 2 feet from any wood or other flammables unless adequately protected by metal or asbestos shield.

8. Equipment Cleaning.

Entering, crossing, and leaving the stream channel with the Contractor’s or his agent’s equipment shall be at locations(s) approved in advance by the CO. The number of crossings and length of time equipment operates within the river channel shall be kept to the minimum necessary for the purposes of constructing the bridge. The equipment shall be cleaned of all anti-freeze, grease, hydraulic fluid, brake fluid, steering fluid, oil, or fuel prior to entering the water influence zone. The Contractor shall notify the CO, so the Government can inspect the cleaning operation prior to commencing work at the project site. Equipment cleaning shall be done outside the water influence zone as approved by the CO or off National Forest lands, in accordance with all federal, state and local laws. The Contractor shall inspect the equipment daily for leaks prior to use.

Equipment maintenance or refueling shall be done outside the water influence zone as approved by the CO or off National Forest lands. Under no circumstances will the Contractor allow unauthorized crossings by the public. All equipment used in the river or crossing the river shall not leak anti-freeze, grease, hydraulic fluid, brake fluid, steering fluid, oil, or fuel. Equipment shall be immediately removed from the water influence zone, if leaks are discovered. The CO may inspect any equipment prior to or during its use. The Contractor's Hazardous Spill Plan shall include provisions for mitigating any spills or leaks within the river's water influence zone.

DURATION OF THIS PLAN

This plan will apply to any and all subcontractors and their employees. The contractor will be responsible to see that all subcontractors and their employees are made aware of the contents.

This plan will be in force for the duration of the above-referenced project.

FIRE RESTRICTIONS

Contractor will follow all fire restrictions that may occur by Special Order during the contract time period. Special Authorization by an approved Forest Service Official must be received and attached as part of the Contract prior to restricted actions taking place.

108 - Prosecution and Progress

108.00_nat_03_24_2004

Delete Section 108 in its entirety.

109 - Measurement and Payment

109.01 Measurement of Work

Replace the sixth paragraph with the following:

Submit measurement notes to the CO as directed. For lump sum items, submit documentation to support invoiced progress payment.

109.02_nat_03_25_2004

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

(c) Cubic Yard

Delete methods (2) and (4).

Measurement Terms and Definitions.

Replace the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109.05 Scope of Payment.

Replace the last paragraph with the following:

The quantities shown in the bid schedule are contract quantities unless designated otherwise.

Limit pay quantities to those shown on the bid schedule or otherwise authorized before performing the work. Payment will be made for contract quantities unless designated otherwise on the bid schedule. For designated quantities to be measured for payment and for quantities to be adjusted according to Section 109.02(b), measure quantities as directed in each associated

Standard Section or Special Contract Requirement.

109.06_nat_03_24_2004

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

152 - Contractor Survey and Staking

152.00_nat_04_29_2004

Construction Requirements

152.04 General.

When indicated on the plans, a preliminary survey line has been established on the ground. The project location line (road centerline) is established by offsets from this preliminary line.

Delete the last sentence in fourth-from-last paragraph and replace with the following:

Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations.

152.04(c) Material.

Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.

Do not use aerosol spray paints.

Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.

152.05 Survey and Staking Requirements.

(b) Centerline establishment.

Replace the last sentence with the following:

Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 50 feet.

(d) Slope and reference stakes:

Replace section with the following:

Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.

Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.

Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.

Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.

Use the designated method to establish the slope stake catchpoint.

• Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.

• Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.

(e) Clearing and grubbing limits.

Add the following:

Establish clearing limits on each side of the location line (road centerline) by measuring the required horizontal or slope distances shown in the stake notes. Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.

After establishing clearing limits, move the location line (road centerline) stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line (road centerline)

(g) Culverts.

Delete this section

(h) Bridges.

Replace the subsection with the following:

Set adequate horizontal and vertical control, reference lines, and reference points for the bridge, abutment footings, abutment bearing seats, wing walls, and other major components. Establish the bridge control, reference lines, and reference points by setting hubs and guard stakes beyond the clearing limits on each side of the channel. Record the following reference stakes:

(1) Station or coordinates of actual point where the abutment centerline of bearing intersects the road centerline and the skew angle;

(2) Reference points and lines for the location and angles of both abutment footings including their elevations;

(3) Reference points and lines for wingwalls and abutment wall locations including all elevations and angles shown on the plans;

(4) Reference points and lines of all girder elevations necessary for placement of deck slab;

(5) Reference points and lines for all bridge rail post locations;

(6) Reference points and lines for all approach rail post stations and offsets;

(7) Reference points and lines for all top of embankment stations and offsets, and;

(8) Riprap coordinates and elevations.

Perform this work after clearing is completed and within the tolerances established in Table 152-1 under

Precision Class A (Bridges). The structural component’s control is established as a local network and the tolerances are relative to that network.

(l) Miscellaneous survey and staking.

Cattleguards

Drain Dips

Erosion Control Measures

Bypass Road and Bridge

Replace Table 152-1 with the following two tables:

Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.

Precision

Class

Minimum

Position

Closure Angular Accuracy (±)

L-Line Tangent

Control Points a

Vertical Closure b

A

(Bridges) 1/10,000

2 sets, direct/reverse

10 second rejection limit

N/A

0.02 ft or

0.02ft/1000ft c

B 1/5,000

2 sets, direct/reverse

20 second rejection limit

0.1 ft

0.02 ft or

0.02ft/1000ft

C 1/1,000 1 set, direct/reverse

1 minute rejection limit

0.2 ft 0.5ft/1000ft

D 1/300

Foresight and backsight;

15 minute rejection limit

0.4 ft 1.0ft/1000ft

E 1/100

Foresight and backsight;

30 minute rejection limit

0.8 ft 1.0ft/1000ft

a. Accuracy of offset measurement.

b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.

c. Use greater value.

Table 152-2 Cross section and slope stake tolerances.

Item Tolerances

A B C D E

Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves

(±)2 o (±)3 o (±)3 o (±)5 o (±)5 o

Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed

0.5 ft 1.0 ft 2.0 ft 2.0 ft 3.0 ft

Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater.

0.1 ft or

0.4%

0.15 ft or 0.6%

0.2 ft or

1.0%

0.2 ft or

1.0%

0.3 ft or

1.0%

Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater:

Slope reference stakes and slope stakes.

Clearing limits

0.1 ft or

0.4%

1.0 ft

0.15 ft or 0.6%

1.0 ft

0.2 ft or

1.0%

1.0 ft

0.2 ft or

1.0%

1.5 ft

0.3 ft or

1.0%

2.5 ft

152.06 Payment

All surveying required to complete the project shall be included in the following items:

15205 Bridge survey and staking Lump Sum

15212 Slope, reference, and clearing and grubbing stakes; method 1, tolerance A Lump Sum

15255 Grade finishing stakes, aggregate surface, tolerance A Lump Sum

153 - Contractor Quality Control

153.02_nat_03_24_2004

153.03 Quality Control Plan (QCP).

Add the following:

Submit proposals in writing for using alternate AASHTO or State approved test methods for approval. Alternate methods may be allowed based on documented equivalence to the method specified.

153.05 Sampling and Testing

The contractor shall submit to the CO current documentation of the calibration and inspection of the testing equipment to be used for the project. The documentation shall include inspection date, inspector, calibration number, and the method of calibration. All testing equipment shall be calibrated and inspected tagged with the inspection date, inspector, and calibration number. The lab testing equipment and density testing equipment shall be calibrated and inspected on a yearly basis. The concrete testing equipment shall be calibrated and inspected every four months.

Material testing shall be performed at the frequency required in the subsection titled Acceptance within each applicable standard specification section.

The Contractor shall provide testing of the structural backfill material to determine optimum moisture content and maximum density according to the method required within each applicable standard specification section.

The Contractor shall provide testing of the structural backfill material to determine plasticity index, gradation, liquid limit, and/or soil classification.

All retests shall be performed at the Contractor’s expense and are incidental to this pay item.

153.06 Certifications

Replace the last sentence with the following:

The QCP shall include certifications of testing and sampling personnel.

153.07 Records and Control Charts.

Delete all but the first two sentences of paragraph (a). Delete all of paragraph (b).

154 – Contractor Sampling And Testing

Delete this section in its entirety.

155 - Schedules for Construction Contracts

155.00_nat_03_23_2004

Replace Section 155 with the following.

155.01 This work consists of scheduling and monitoring all construction activities. See FAR Clause 52.236-15

Schedules for Construction Contracts.

155.02 Submit 3 copies of a construction schedule at least 7 days before work commences.

156 - Public Traffic

Delete Section 156 in its entirety and replace with the following:

Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels 633

Retroreflective sheeting 718.01

Temporary concrete barrier 618

Temporary plastic fence 710.11

Temporary traffic control devices 718.22

156.03 General. Unless otherwise directed in the project documents, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will safely and adequately accommodate traffic. When the road can accommodate traffic, delays may not exceed 30 minutes at any one time.

Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a plan for the satisfactory handling of traffic (including emergency access) has been approved by the CO. Post construction signs and traffic control devices in conformance with

MUTCD. Assure that all required signs are in place and approved prior to beginning work on project.

If the Contractor allows public traffic to use a new road segment being constructed prior to completion, it will be considered an existing road for traffic control purposes.

Do not construct detours outside of the clearing limits or use alternate route detours without the approval of the CO.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the

MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits shall be approved in writing by the Contracting

Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove or cover devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services

Association, the National Safety Council, the International Municipal Signal

Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6E. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 See Subsection 109.05.

Measure traffic control under Section 635.

Measure diversion/detour construction, required by the contract, under the applicable Sections.

alamp Cross-Out

157 – Soil Erosion and Sediment Control

157.04 General.

Delete the entire subsection and replace with the following:

Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.

Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.

When erosion control measures are not functioning as intended, immediately take corrective action.

157.06 Filter Barriers.

Silt fence shall be straw wattles, logs, or rolls.

157.07 Sediment Retention Structures.

Replace with the following:

Sediment basins (when required) may be excavated or geotextile sediment bag(s) may be used in accordance

SCR 714.03. The size of geotextile sediment bag shall be 15’x 15’. Install geotextile sediment bag(s) on a slope so incoming water flows downhill through the bag without creating more erosion. Strap the neck of the geotextile bag tightly to the discharge hose. The outlet of the geotextile sediment bag(s) shall have riprap over geotextile fabric to prevent erosion. Sediment basins and geotextile sediment bag(s) shall be periodically relocated for construction operations or as directed by the CO. The contractor shall obtain data from the geotextile sediment bag and pump manufacturers to ensure they are compatible (i.e., the pump(s) providing the flow to the geotextile sediment bags does not produce a higher flow rate than the maximum rate which the geotextile sediment bag can filter and discharge). To increase the efficiency of filtration, the contractor may place the geotextile sediment bag(s) on an aggregate (crushed rock) base or hay bale bed to maximize water flow through the surface area of the bag. The aggregate base or hay bales, if installed, shall be removed with any relocation of the geotextile sediment bag or from National Forest lands upon conclusion of the dewatering operations. Hay bales shall be certified weed free materials. Sediment basin areas shall be reclaimed with grading, seeding and mulch, as required.

The geotextile sediment bag is full when it no longer can efficiently filter sediment or pass water at a reasonable rate. Flow rates will vary depending on the size of the geotextile bag, the type and amount of sediment discharged into the geotextile bag, the type of ground, rock or other substance under the bag and the degree of the slope on which the bag lies. Under most circumstances geotextile bag may accommodate flow rates of 1500 gallons per minute. Use of excessive flow rates or overfilling geotextile sediment bag with sediment may cause ruptures of the bags or failure of the hose attachment straps. Ruptured or disposed bags shall be replaced by the

Contractor at no additional expense to…

This is the start of the file's text. The full file is on GovTribe.