This document contains details about a pre-solicitation for an Indefinite Delivery-Indefinite Quantity (IDIQ), Multiple Award Task Order Contract (MATOC) for road and bridge construction and related services issued by the United States Forest Service (USFS), Intermountain Region (Region 4). The solicitation will be issued as a total small business set-aside with a minimum of 10 individual contract awards. The contract will have a 2-year base period and three 1-year option periods for a total of 5 years. Task orders will range from $2,000 to $3,000,000 with a $50,000,000 shared ceiling limit. The selection process will be conducted in accordance with FAR Part 15 source selection procedures. Seed projects will be included in the proposal package and used for price evaluation, with the intent that they will be issued as the first task orders. Site visit information for 5 seed projects is provided, including locations, dates, and high-level project descriptions. The solicitation is anticipated to be available on SAM.gov in fall 2024.

View the file

Other files

File Type Posted
Causey Reservoir Parking Lot_Plans.pdf PDF
Upper Green River_Plans.pdf PDF
Upper Green River_FSSS.pdf PDF
CoveMountain_Plans.pdf PDF
Charleston Jabridge_Plans.pdf PDF
CoveMountain_FSSS.pdf PDF
Charleston Jabridge_FSSS.pdf PDF
North Fritz_FSSS.pdf PDF
North Fritz_Plans.pdf PDF
R4 Seed Project Site Visit Schedule 241003.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R4 Road and Bridge - Brief Seed Project Descriptions

Charleston Jarbidge

The project consists of removing the existing Charleston-Jarbidge Road Bridge and installing a 128” x 83” corrugated metal pipe-arch culvert in the same location. Public vehicle access must be maintained during the entire project, so a rock ford and road approaches shall be constructed and maintained just upstream of the existing bridge prior to the bridge removal.

Location: Charleston, NV

Latitude, Longitude: 41.7038, -115.483787

Site Visit Date and Time: 10/9/24 at 12:00 pm (PT)

Cove Mountain Reroute and Reconstruction

The project consists of two road reroutes, road decommissioning, road reconditioning, constructing rolling dips, placement of aggregate surface coarse and a culvert installation.

Location: Pinto, UT

Latitude, Longitude: 37.5547, -113.52722

Site Visit Date and Time: 10/17/24 at 1:00 pm (MT)

North Fritz Creek Culver Replacement

The project consists of removing a 4’ diameter corrugated metal pipe and replacing it with 16’- 4” span bottomless box culvert.

Location: Dubois, ID

Latitude/ Longitude: 44.4134, -112.7376

Site Visit Date and Time: 10/16/24 at 10:00 am MT

Upper Green River Corridor

The project includes road reconditioning, culvert replacement and placement of government furnished aggregate surfacing on 3 miles road.

Location: Cora, WY

Latitude, Longitude: 43.22171, -110.008137

Site Visit Date and Time: 10/10/24 at 1:00 pm (MT)

Causey Reservoir Parking Lots and Boat Ramp

The project includes reconstructing 2 parking lots and constructing a new boat ramp.

Location: Huntsville, UT

Latitude/ Longitude: 41.29705, -111.584918

Site Visit Date and Time: 10/15/24 at 1:00 pm (MT)