Amendment to Solicitation 1240LT27Q0029

This document is an Amendment (No. 0001) to a solicitation issued by the USDA Forest Service for the Lowline Area Burned Fence Construction Project. The amendment, dated November 23, 2026, extends the quote submission deadline from December 3, 2026 to December 8, 2026 at 9:00 a.m. Mountain Time. Quotes must be submitted via email to Janice King (janice.king@usda.gov) and Lucas Dahlman (lucas.dahlman@usda.gov). The contracting officer is Lucas J. Dahlman, issued from the USDA-FS CSA Intermountain 8 office located in Ogden, Utah. The amendment incorporates responses to 54 contractor questions, provides clarifications to the Statement of Work Section C.5 (Restrictions of Work), includes a topographic map of the project area, and lists seven contractors who attended the November 9, 2026 site visit. The government anticipates contract award no later than January 30, 2027.

The project involves constructing approximately 16,414 feet of four-strand wildlife-friendly fence in Gunnison County, Colorado, to replace fencing damaged by the 2023 Low Line Fire. The contract period runs January 15, 2027 through September 15, 2027, with actual work commencing around June 2027 upon snow melt. Key specifications include capped/sealed steel pipe posts (2-3/8" minimum, 4.7 lbs/linear foot), steel t-posts every 16.5 feet, approximately 16–20 braces, 4 gates, 2 water gaps, and four strands of wire at specified heights. The contractor must clear up to 10 feet of right-of-way, remove old fencing materials, and perform site restoration. The disclosed magnitude range is $100,000–$250,000. Approximately 75% of the fence line is accessible by ATV/UTV, with limited portions requiring foot access. The contractor is responsible for materials procurement, hauling, installation, and all damage restoration. Progress payments are available; retainage may be withheld up to 10 percent until satisfactory progress is achieved.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT27Q0029

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

OGDEN UT 84401-2310

324 25TH ST

USDA-FS CSA INTERMOUNTAIN 8

11/23/20260001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

10/29/2026

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PROJECT: Lowline Area Burned Fence Construction Project

POC's Janice King, Contract Specialist, at janice.king@usda.gov and Lucas Dahlman, Contracting Officer, at Lucas.dahlman@usda.gov

Submit Quotes to the POC's above by the updated due date and time.

The purpose of this Amendment is as follows: SEE THE SUMMARY OF CHANGES attached to this

Solicitation for details.

1) To update and extend the due date for Quotes from 12/03/2026 to 12/08/2026 at 9:00 a.m.

Mountain Time to allow additional time for bid submission.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

LUCAS J. DAHLMAN

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 21CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

1240LT27Q0029/0001

2) To provide answers to questions from contractors. See below the attached Questions and

Answers.

3) To incorporate changes in the SOW (Statement of Work) at Section C.5,Restrictions of Work -See below the attached document.

4) To provide a MAP to respond to questions. See below the attached - Lowline Fence Reconstruction

Project MAP

5) To provide the participates for the Site Visit held on 11/09/2026. See below the attached Site

Visit Document.

6) To provide the Contact's information to obtain the kmz/kml file to answer question #28. Software used in Sam.gov does not support this file.

Contractors must use Google Earth to view this document after obtaining it from the COR. See #28.

7) All other terms and conditions remain the same. SEE THE SUMMARY OF CHANGES attached to this Solicitation for details.

Period of Performance: 01/15/2027 to 09/15/2027

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Summary of Changes PROJECT: Lowline Area Burned Fence Construction Project

SOLICITATION #: 1240LT27Q0029 - Amendment One (A0001)

Quotes: Quotes shall be submitted via email to Janice King at janice.king@usda.gov and to Lucas Dahlman at lucas.dahlman@usda.gov no later than December 8, 2026, at 9:00 a.m. Mountain Time. This time date has been amended to allow contractors more time to prepare and submit bids. Due to the close proximity to the due date for submission of quotes, additional questions may not be answered. Please include the solicitation’s name and number that is listed in the title above in the subject line of the email containing your bid.

The purpose of this Amendment is as follows:

1) To update and extend the due date for Quotes from 12/03/2026 to 12/08/2026 at

9:00 a.m. Mountain Time to allow additional time for contractors’ bid submission.

2) To provide answers to contractor’s questions – See below the attached Q & A’s.

3) To incorporate changes in the SOW (Statement of Work) at Section C.5, Restrictions of Work - See below the attached document.

4) To provide a MAP to respond to contractor’s questions – See below the attached:

Lowline Fence Reconstruction Project MAP

5) To provide the participates for the Site Visit held on 11/09/2026 – See below the attached Site Visit Document.

6) To provide the contact's information for the kmz/kml file to answer question #28.

Software in Sam.gov does not support the upload of this document. Contractors must use Google Earth to view this document after obtaining from the COR. See #28.

7) All other terms and conditions remain the same.

mailto:janice.king@usda.gov mailto:lucas.dahlman@usda.gov

LOWLINE AREA BURNED FENCE CONSTRUCTION PROJECT

PRE-BID QUESTIONS AND ANSWERS LOG

Project Location: GMUG NF, Gunnison, CO 81230 Date: November 20, 2026

Q# Question Response 1 What does access to the work site look like Primary access is through private property to reach National Forest Land.

Access can also be Access will be agreed to between the USFS, contractor, and private land owner.

Access can also be made via the Low Line Trail from FSR 727.

2 Can I use a drone to view the work site

Drone use for commercial purposes on National Forest land requires a special use authorization and could be applied for separately from this bid/contract.

3 Can I weld on site? What if there are fire restrictions in place?

Yes, welding can be done on site with proper fire mitigations in place. If fire restrictions were to be put in place, off site fabrication would be encouraged and the USFS may provide a permit to continue to weld under these restrictions, depending on conditions.

4 Exact count of H braces, etc. I must provide, or can I provide an estimate?

Fence construction must meet the specifications of the contract. The exact number of H-braces, post, etc. may be included in the technical approach section, but is not required.

5 Is there a required order on what should be removed/replaced?

No, there is no requirement for the order of operations.

6 Can I use a masticator or similar machinery to clear the fence line?

Yes. Proposed machinery to be utilized should be outlined in the technical approach. Additional mitigations may be required depending on the type of equipment proposed.

7 Do I need to clear 10 feet on both sides of the fence?

No, up to 10 feet can be cleared along one side or the other of the fence line to allow for access.

8 Is there anything we should NOT clear 10 feet from the fence line

Live, green trees should be retained unless necessary to allow access along the fence line.

9 When does the snow melt out and the work site accessible?

Generally access can be made in early June, but can vary depending on the amount of snow and temperatures.

10 Can on-site materials be used to create fence stays/ other materials

Yes, dead woody material can be utilized on site to create fence stays/posts as long as it meets contract specifications.

11 Can existing fence stays be piled and mulched?

Yes, this would have to be communicated with USFS staff and completed to their specifications.

12 Should any water crossings be corduroyed?

Best Management Practices should be used at any stream crossings or in areas of soft soils such as alternate routes, temporary bridges, or corduroy structures. Any temporary structure will be removed once they are no longer needed to complete work.

13 We would like to confirm whether the scheduled pre-bid meeting/site visit is mandatory.

While the site visit scheduled for November 9, 2026, is not mandatory, attendance is highly encouraged and recommended.

14 Will you clarify whether there is equipment access along the proposed fence line? Specifically, would we be able to utilize a skid steer and ATVs/UTVs to transport materials and complete construction, or are portions of the fence accessible only by foot?

While access will be difficult, it is possible to get a UTV/ATV and skid steer along a majority of the fence. A few of the steep areas will be foot only.

Clearing of debris along the line will need to be completed prior to moving equipment.

15 Is it possible to get terrain pictures of the fenceline? Even just cell phone pictures from whoever is doing the site tour?

See the response below to question #16.

16 Is it also possible to get a more detailed fenceline/ topo map?

See Attachment below: Lowline Area Burned Fence Reconstruction Project.

17 Is the current fence to be removed all barbed wire or is it also a mix of field fence/woven wire?

All barbed wire, no woven wire.

18 Unfortunately, we aren't able to make it to today's site visit. If there are any photos or video from the site walk, or if the walk is being recorded, we would really appreciate a copy so we can get a better feel for the terrain, access, and existing fence conditions.

See the response below to question #19.

19 We are happy to view the project on our own if there is open access/permission to view the fence line. Could you let us know if this is possible?

Access for any additional site visits will need to be via hiking/horse/mountain bike on the Low Line Trail from FSR 727.

20 Do you anticipate that the awarded contractor will be able to access the site (Fence line) by vehicle? Or do you anticipate the site will be accessible only via

ATV,UTV?

It is anticipated that the work site will be accessed through private property that allows for full size truck and trailer to reach the start of the fenceline. A majority of the fence line will be accessible by ATV/UTV only with some portions being only foot accessible.

21 Are there any concerns regarding road conditions, terrain, high-clearance equipment, or other access limitations that contractors should be aware of when planning the work?

Work will not be allowed to commence until road conditions are suitable to minimize impacts to both private and federal lands. 4x4 with clearance is recommended and an ATV/UTV will be the only mode of viable transportation for some portions of the fence. Access will be through private property, and camping will be available on Forest Service lands to minimize traffic and impacts on the private property.

22 I wanted to ask if it’s possible to visit the site. I understand there was a site visit already but I was unable to make it. I am very interested in quoting this project if it’s possible for me to look at it. I understand if it’s not possible.

Access for any additional site visits will need to be on an individuals own time and can be accessed via hiking/horse/mountain bike on the Low Line Trail from FSR 727.

23 Are the trees still burned and standing?

Yes, the work site is in the Lowline fire burn scar which burned in 2023. There are still burned trees standing in the burn scar.

24 Can we take a skidsteer and side by sides in or is it too steep.

Skidsteers and side by sides can be utilized in the majority of the work area, but there may be areas that are too steep or wet to utilize them.

25 Can we clear the trees and brush to make way for the new fence

Yes, up to 10 feet can be cleared along the fenceline to allow access and space for the new fence.

26 Approximately how many gates and braces

Approximately 16 braces and 4 gates.

27 Can we leave the old burned wooden fence posts there to decompose

Yes, the old wooden fence posts can be scattered and left on site. All wire and t-posts must be removed.

28 Is it possible to get either a kmz file made of the fenceline to show elevation changes across the fencelines?

29 As far as the bid bond goes does it need to be addressed to the GMUG or to USDA?

USDA – FOREST SERVICE- CSA

INTERMOUNTAIN 8 (SEE THE

SOLICITATION at BOX#7); Submit with bid via email.

30 Will the agency negotiate contractor access through the private parcels?

The USFS has a working relationship with the landowners that provide access. The USFS will participate in conversations to provide access to the work site.

31 Are partial payments available once materials are on site and accepted?

Progress payments are available based on the terms of the contract. Material acceptance and payments will be based on delivery and COR acceptance.

32 Approx what percent of the fenceline would be accessible to a tracked skid steer or UTV?

The lower portion with hike in access obviously wouldn't but that’s fine I can bring pack mules for that.

Approximately 75% depending on equipment types and conditions.

33 What is the timeline for awarding the contract?

The Government anticipates making an award on this project no later than January 30, 2027, if not sooner.

34 What is the funding schedule? Progress payments are available based on the terms of the contract.

35 How much of the fence do you lay down in the winter: the top line only, or the whole fence?

The whole fence will be able to be lay down and not just the top wire.

36 Is there a maximum budget for the project?

Per page one of the Solicitation: the Disclosure of Magnitude range is:

$100,000 - $250,000.

37 PRIORITY CLARIFICATIONS: SITE

ACCESS, POST MATERIAL, H-

BRACE, AND GATE DESIGN

Site access constraints and exact material specifications are our

a) The USFS has a working relationship with the landowners that provide access. The USFS will participate in conversations to provide access to the work site through private lands. The Lowline trail is the only accessible trail

Contact the COR, Jack Statkebaum. at Email:

jack.starkebaum@usda.gov or by Phone at: (970)641-0471 for this file.

Software in www.Sam.gov does not support this file.

mailto:jack.starkebaum@usda.gov main areas of concern, as they will dictate our operational logistics, equipment selection, and final pricing. We want to confirm the following priority items before finalizing our quote:

Site Access & Equipment Logistics - Main Area of Concern (SOW Section 6.0; Attachment 2.

SOW pages 4–5; Solicitation page 4): a) Access Through Private Property & Alternatives: The solicitation notes that access is limited from the east through private property in Section 31 and Section 24 of T15S, R87W. Has the Forest Service secured, or is it able to arrange, contractor access through this private property for vehicles, equipment, and material delivery, particularly to the northern fence segments?

Transporting all materials and equipment solely up the Low Line trail from the CR 727 trailhead is our primary operational concern for this project. If the eastern route is unavailable, please confirm if the Low Line trail is the only approved access, or if the Forest Service can provide or approve any alternatives for improved access.

b) Equipment Restrictions (OHV & Compact Equipment): Recognizing that the Low Line trail is too narrow for full-size vehicles, please confirm if OHVs (ATVs/UTVs) or compact track equipment (such as a mini skid steer) are permitted for material transport up the trail and along the fence line corridor itself (including within the General Roadless portion). c) Staging: May materials be staged at the trailhead or in USFS storage?

to the work site entirely via National Forest System Lands.

b) Skid steers and ATV’s can be taken on the lowline trail if accessed via private lands. ATV access is not feasible on the lowline trail via 727.

c) Materials cannot be staged at the Mill Creek winter trailhead as the BLM manages that trailhead. Locations on USFS land can be identified for staging/storage of materials.

The USFS can negotiate storage of materials at an off-site location.

38 Post Material and H-Brace Assembly Design (SOW Section 3.0, page 4; Attachment 4, page 1;

see attached mockup all_metal_h_brace_mockup.png):

The written SOW requires 2-3/8" steel pipe (4.7 lbs/lf), but the diagrams in Attachment 4 show wood posts and 4" horizontal members. a) Please confirm the written SOW governs and that capped/sealed 2-3/8" steel pipe weighing at least 4.7 lbs per linear foot is the required material for all line, brace, corner, and gate posts, and that the wood posts shown are stock illustrations.

b) If all-metal H-braces are required, must the horizontal cross member also be 2-3/8" steel pipe, and what is the required attachment method (welded, bolted, or saddle-clamped)?

c) For the diagonal member, do you require a welded 2-3/8" steel pipe diagonal brace or a tension brace wire with a twist stick? If tension wire is used on steel posts, please clarify any required attachment hardware to properly anchor and tension the wire.

a) Steel pipe is the required material to be used.

b) Yes, the horizontal cross member must be metal and the attachment method can be any

c) Wire or metal is fine.

Attachments should be any method that sufficiently secures the wire to provide tension.

39 Gate Design (SOW Section 3.0, page 4; Attachment 4, Attachment B): Assuming the H-brace design selected in Question 2 (above question) can also be used at the gates, we will assume 12-ft gates are a matching 4-strand wire gate (not the 3-wire stock image shown) with wooden stays and wire-loop gate closers on 2-3/8" steel pipe posts. If you have a specific gate design or updated drawings, please provide them.

Gate should be the same specs as the fence, 4 strand wire that can be opened and moved easily by the public for access.

A new diagram will not be provided, the current diagram was primarily to demonstrate spacing for post layout. A 4 wire fence is the requirement as described in C.1

40 Brace/Gate Post Setting Method & Additional Pipe Specs (SOW Section 3.0, page 4): SOW Section

3.0 states that hydraulically driven line posts set at least 48" deep do not require concrete. May brace, Hydraulicly driven posts are fine. No concrete needed.

Braces, corners, grates, end posts can be hydraulicly driven without concrete similar to line posts.

corner, gate, and end pipe posts likewise be hydraulically driven to 48" minimum depth without concrete, or must they be set in concrete (30" minimum depth, 24" deep x 8" diameter)? Also, beyond the 2-3/8" diameter and 4.7 lbs/ft minimum, are there any other pipe specifications you would like us to follow, such as wall thickness/grade or a specific cap/seal type?

There are no additional pipe specifications beyond 4.7 lbs/ft and no specifications for method or type of cap/seal type.

41 ADDITIONAL TECHNICAL &

SCOPE CLARIFICATIONS

Counts, Locations, and GIS Data (SOW Section 3.0, page 4;

Attachment 3 Map): Could you share the gate count, an estimated number of H-brace assemblies to be installed, and any water-gap counts or locations so we can price materials accurately? Also, would it be possible to release GIS shapefiles prior to the December 3 quote due date?

There are approximately 16-20 braces, 4 gates, and 2 water gaps. All material needs are determined by on the ground conditions.

42 Water Gaps & Creek Crossings (SOW Section 3.0, page 4;

Attachment 3 Map): Which water-gap design applies where the fence lines cross drainages such as Price Creek and Middle Creek, and how should crossings be built without impacting streams?

Lengths of the water gaps are minimal and a design similar to the wire gate specs should be utilized to provide for lay-down during off season.

43 Wire Specifications (SOW Section 3.0, page 4): SOW Section 3.0 specifies 12.5-gauge smooth wire at 16" and 42" and 12.5-gauge barbed wire at 24" and 30". We plan to use 2-point barbed wire for the two center strands. Please confirm whether 2-point or 4-point barbed wire is required, whether 12.5-gauge 2-strand twisted barbless cable is acceptable for the 16" and 42" smooth-wire strands (or if single-

Either 2 point or 4 point barbed wire is acceptable.

Yes, 12.5-gauge 2-strand twisted barbless cable is required.

There are no requirements for wire coatings, tensile grade, etc.

strand smooth wire is required), and if there are any other wire specifications (such as coating/galvanizing class or tensile grade) we need to follow.

44 Lay-Down Attachment & Termination Details (SOW Section 3.0, page 4; see attached CPW Lay- Down Diagram cpw_laydown_fence_diagram.png):

We assume the entire fence will fully lay down (with H-braces remaining permanent, and the wooden posts shown in the attached CPW diagram replaced by 2-3/8" steel pipe and T-posts per SOW Section 3.0). Please clarify: a) Must the lay-down fence terminate with a stay and wire loop at each 2-3/8" steel pipe line post (99-ft spacing), or can the wire run continuously across multiple 2-3/8" steel pipe posts assuming lay-down clips are used?

b) Please confirm that the wire is left untensioned ("wires not stretched" as shown in the CPW diagram).

a) Wire can run continuously and lay down clips can be utilized

b) Wire is left untensionsed

45 Old Fence Disposal (Attachment 1 SOI Item 2; Attachment 2 SOW pages 3–4): Are any hazardous materials expected in the existing fence removal, and is there a required disposal location or documentation?

There should be no hazardous materials and there is no required disposal location.

46 Camping & RVs (SOW Sections 4.0 and 6.0): The SOW states camping will be available on NFS land at USFS-designated sites. Are RVs or camp trailers permitted at these sites, or is camping limited to tents? Also, can the designated sites be reached by truck and trailer?

Camping can be permitted on USFS ground to include RV’s. Depending on the agreed to camping site, access can be reached by truck and trailer, and may be accessed via private land.

47 Existing Concrete Removal (SOW Section 3.0, page 4): If any existing posts are set in concrete, does the scope of this quote include

No, there is no concrete expected to be encountered or removed.

removal of the old concrete footings?

48 Right-of-Way Clearing Scope (SOW Section 3.0, page 4): The SOW states that the contractor is responsible for "clearing a right-of-way along fence line not to exceed 10 feet in width." Because portions of the fence line pass through heavily timbered and burned areas, please clarify the intended extent of clearing: (a) whether the 10-ft width is measured as a total corridor centered on the fence line (approximately 5 ft on each side);

(b) whether clearing is limited to cutting and removing downed trees across the fence line; (c) whether standing trees, including fire-killed or hazard snags within the corridor, are to be felled; (d) whether brush removal is required within the corridor; and

(e) the preferred method for handling cut material (e.g., lopped and scattered on site, piled, or removed from the project area).

a) 10 feet total on either side of the fence. Primarily to provide access for work to be completed

b) Standing trees can be removed up to 10 ft from the fenceline in order to provide access to complete work

c) Standing tree and snags can felled/removed

d) Brush can be removed along the fence corridor in order to provide access to complete work

e) Lopped and scattered

49 Fence Alignment Tolerance (SOW Section 2.0): The SOW states that "Reconstruction will follow the prior existing line" and recommends replacing affected sections to the nearest anchor point (H-brace). Please confirm whether the new fence must be constructed on the exact existing alignment, or whether minor field adjustments (for example, offsets of up to approximately 5 ft) are acceptable to avoid trees, rock, or difficult terrain, provided that the end points and H-brace anchor locations remain unchanged. If minor adjustments are acceptable, please advise whether COR approval in the field would be required.

Fence alignment may be adjusted up to 5 ft on either side of the existing fence alignment, so long as it does not decrease the total fence length (i.e.

“cutting a corner”) and the fence continues in a straight alignment. Any additional realignments should be approved by the COR.

ADMINISTRATIVE &

SOLICITATION CLARIFICATIONS

Quote Due Date & Submission Method (Solicitation pages 1, 3, 11; SAM.gov): Please confirm quotes are due December 3, 2026 at 9:00 AM MT (SAM.gov public notice shows December 3, 2027) and that email-only submission to you both is acceptable.

Quotes shall be submitted via email to Janice King at janice.king@usda.gov and to Lucas Dahlman at lucas.dahlman@usda.gov no later than December 3, 2026, at 9:00 a.m.

Mountain Time. The date on the www.Sam.gov public notice will be updated to December 3, 2026, at 9:00 a.m. Mountain Time.

51 Insurance Requirements (Solicitation page 9, FAR 52.228- 5): What insurance types and dollar limits are required under

FAR 52.228-5?

(a) Workers’ compensation and employer’s liability. Contractors are required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they must be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 must be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)

(b) General liability.

(1) The contracting officer must require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.

(2) Property damage liability insurance must be required only in special circumstances as determined by the agency.

(c) Automobile liability. The contracting officer must require automobile liability insurance written on the comprehensive form of policy. The policy must provide for bodily injury http://www.sam.gov/ and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States must provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies must be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

(d) Aircraft public and passenger liability. When aircraft are used in connection with performing the contract, the contracting officer must require aircraft public and passenger liability insurance. Coverage must be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger liability bodily injury must be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(e) Vessel liability. When contract performance involves use of vessels, the contracting officer must require, as determined by the agency, vessel collision liability and protection and indemnity liability insurance.

52 Period of Performance & Pre- Work Schedule (Solicitation pages 1, 3, 10; SOW page 4): The performance period starts January 15, 2027, while the SOW notes groundwork begins summer 2027.

Can the contractor set the start date within seasonal windows, when is the pre-work meeting expected, and is any retainage withheld under AGAR 452.232-

The Period of Performance is 01/15/2027 – 09/15/2027.

Submittals may be submitted as early as January 15, 2027. Work can begin when snow has melted and the ground has dried enough to allow access to the work site without causing damage to roads or soils. This is generally around June 1 but can vary quite a bit depending on snow and temperatures.

71?

Retainage: (l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer must authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and must release to the contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment must be made for the completed work without retention of a percentage.

53 Buy American Documentation (Solicitation page 8, FAR 52.225- 9): We plan to supply US-made materials. Please confirm what documentation or certifications (such as mill test reports or manufacturer certificates of origin) are required for steel pipe, T-posts, and wire under FAR 52.225-9.

Provide documentation or certification for the origin of new T-posts, and wire (i.e. provide the name and address of the company in which these items were purchased.) These items should be American made.

54 I could not attend the site visit but have a question about the drill stem pipe. I assume this refers to the pipe being oilfield type of tubing or drill pipe which I am familiar with? Does it have to be brand new drill pipe or can it be good used pipe? Also, is there a local supplier of such drill pipe as I am not sure of any oilfield pipe suppliers in the area?

Pipe can be new or used in good condition. The contractor is responsible for acquiring materials from whichever vendor they choose.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

The project will consist of constructing approximately 16,414 feet of four wire fence in the vicinity of the 2023 Low Line Fire, Gunnison County, Colorado (see attached map). The purpose and need are to replace existing fences damaged by the 2023 Low Line Fire with a friendly wildlife fence and provide removal of old and damaged fence materials.

• Line posts will be capped/sealed steel pipe 2-3/8 or larger weighing at least 4.7 lbs. per linear foot installed every 99-feet at a 30-inch minimum depth with concrete at least 24 inches deep by 8 inches in diameter mounded above the hole to shed water (rock cribs as needed in saturated or sandy soils). NOTE: A hydraulically driven steel pipe does not require concrete at the base but must be set at least 48 inches or more below ground level.

• Braces will be capped/sealed steel pipe 2-3/8 or larger weighing at least 4.7 lbs. per linear foot installed at all corners, gates, horizontal direction changes, and steep vertical angle changes in the line. Maximum distance between braces will be no greater than 1320 feet on level terrain.

• 5.5-foot steel t-posts will be installed every 16.5 feet.

• Fence will be constructed to have the ability to lay-down during off season. Either clips or wire loops can be used to support the fence in the upright position at a minimum of every 16.5 feet.

• 2-3-inch by 48-inch wooden stays will be installed between posts every 5.5-feet affixed with either staples or wire ties with the ability to swing free of the ground.

• The height and material of the four wires will be 16 inches (12.5ga smooth wire), 24 inches and

30 inches (12.5ga barbed wire), and 42 inches (12.5ga smooth wire).

• Contractor is responsible for purchasing the material, hauling materials, and installation of the fence. The US Forest Service may provide storage of materials if notified in advance.

• Contractor will be responsible for clearing a right-of-way along fence line not to exceed 10 feet in width.

• Contractor will be responsible for removal and disposal of all old fencing material and trash.

• For additional information on wildlife friendly fencing construction, water gaps, anchoring, gates, etc. see CPW “Fencing with wildlife in mind” brochure and NRCS protocol https://cpw.state.co.us/Documents/LandWater/PrivateLandPrograms/FencingWithWildlifeInMind .pdf and WY NRCS 382 Fence Implementation Requirements

C.2 Project Location & Description The project area is located 13 miles north of Gunnison, Colorado to the north of the Mill Creek drainage on portions of the Beckwith, Squirrel Creek, and Price grazing allotments. Access is limited from the east through private property in Section 31 and Section 24. Rolling-to-steep terrain through spruce-fur, aspen forest, and open meadows.

From Gunnison, Colorado travel north on CO-135 for 3.5 miles and turn left onto CR 730. Travel for 8.9 miles and turn left onto CR 727. Travel for 3.5 miles to Low Line trailhead parking. Hike 1.2 miles north on Low Line trail to reach southernmost section of fence.

https://cpw.state.co.us/Documents/LandWater/PrivateLandPrograms/FencingWithWildlifeInMind.pdf https://cpw.state.co.us/Documents/LandWater/PrivateLandPrograms/FencingWithWildlifeInMind.pdf

C.3 Maps Maps showing the vicinity and road locations are included, see attached.

C.4 Estimated Start Date & Contract Time Start, June 2027 once conditions are permissible. Complete 2027 NLT Sept 15.

C.5 Restrictions on Work

• No marsh or any other kind of wetland or riparian habitat will be impacted. No perennial water bodies or streams discharging into water bodies will be impacted by equipment, fill or contaminants of any kind. Best Management Practices should be used at any stream crossings or in areas of soft soils such as alternate routes, temporary bridges, or corduroy structures. Any temporary structure will be removed once they are no longer needed to complete work.

• Equipment including ATV’s and trailers shall be sprayed prior to entering the forest and is subject to inspection in the project area by the Forest Service representative or Contracting Officer to ensure equipment is clean of mud and any possible noxious weed seeds.

• In the event of archeological discovery, the contractor shall immediately notify the FS of all antiquities and other objects of historic or scientific interest, including but not limited to historic or prehistoric ruins or artifacts discovered in connection with the project. These discoveries shall remain intact and in place until directed otherwise by the USFS.

• Damage and Restoration Requirements. The Contractor shall be solely responsible for preventing and minimizing damage to private lands and National Forest System lands during the performance of the work. The Contractor shall be liable for any and all damage caused by its operations, employees, subcontractors, agents, or equipment, including but not limited to road rutting or degradation, damage to culverts, fences, gates, signage, drainage features, vegetation, timber, and other natural resources.

• Any damage resulting from negligent, improper, avoidable, or unnecessary operations shall be promptly repaired, restored, or replaced by the Contractor at no cost to the private landowner or the U.S. Forest Service. Restoration efforts shall return affected areas as closely as practicable to their pre-existing condition and shall be completed in accordance with all applicable landowner requirements.

• All repair, restoration, and remediation work required under this contract shall be fully completed no later than September 15, 2027.

C.6 Licenses and Insurance

C.7 Camping and Housing

• Camping will be available on NFS land in sites designated by USFS personnel collectively decided on in advance.

• Garbage removal and a portable sanitary facility is required at contractor campsites.

• Food will be secured away from wildlife.

C.8 Technical Requirements

C.8-1 Definitions None

C.8-2 Specifications N/A

C.8-3 Contractor-Furnished Equipment N/A

C.8-4 Government-Furnished Property N/A

Attachment 1- Specs for Brace designs and horizontal braces

Attachment 2- Specs for 12’ wire gates.

LO

W

LINE

PriceC reek

Middle Creek

10200

10000

10000

10000

96 00

Squirrel Cree k

10200

9400 9400

M ILL C

ASTLE MILL

CASTLE

10200

Squ irrel Creek

Pri ce Cre ek

MiddleCreek

10000 10000

LOW

LIN

E

Squirr el Creek

Gra ys

Gu l ch

7B 2

7 727.2 A

Li ttle

M l

L it tle

Mi ll C ree k

Mil l Creek

9800 7727B

Mid dle Cre ek

Grays Gu lch

Cunningham Reservoir

MILL CREEK NORTH

B2

Esri, NASA, NGA, USGS, FEMA, USDA,U.S. Forest Service

Lowline Area Burned Fence Reconstruction Project

Legend

Fence line for reconstruction

0 0.5 10.25 Miles

November 11. 2026

LOWLINE AREA BURNED FENCE CONSTRUCTION PROJECT

Sign-In Sheet

Project Location: GMUG NF, Gunnison, CO 81230 Date: November 9th, 2026

# Name Company Phone Number Email Address

Dylan Newbert Alpine Earthworks 720-272-7760 dylan@alpine-earthworks.com

Tyrell Buffalo Timberline Ent. 719-207-2438 timberlinesnowremoval@gmail.com

Luke Bryars MBX Builders 512-239-8852 luke@mbxbuilders.com

Robert Parker Parker Specialized 970-417-7009 parkerspecializedllc81413@gmail.com

Carl Rankin Agman Fencing 970-417-7009 carl9623@gmail.com

Wayne Irving Gunnison Fence 970-639-0697 gunnisonfence@gmail.com

Noah Grouse Alpha Building 970-863-1754 abdgunnison@gmail.com

1240LT27Q0029
SUMMARY of Changes_LOWLINE FENCE
Summary of Changes_Final_11.20.26
FINAL_Lowline_PreBid_Questions_and_Answers_Log JK4
Low Line Fence SOW
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.8 Technical Requirements
C.8-1 Definitions
C.8-2 Specifications
C.8-3 Contractor-Furnished Equipment
C.8-4 Government-Furnished Property
Lowline Fence Reconstruction Project Map 110726
SITE VISIT SIGN IN SHEET

File details come from the government source that posted it. Updated .