C04 Attachment 3 Project Manual for BRF FY26 Roofing Projects.docx
DOCX document 124 KB Posted
- Solicitation number
- 1240LT27Q0015
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Project Manual containing bid specifications for roofing projects at three U.S. Forest Service locations on the Bitterroot National Forest in Montana: Stevensville Ranger Station, West Fork Ranger Station, and Darby Ranger Station. The manual specifies three primary roofing system types with detailed technical requirements for products, installation procedures, and execution standards.
For preformed roofing and standing seam metal systems, contractors must supply zinc-coated or aluminum-coated steel panels in 24 gauge with mechanically formed lock seams, factory-applied sealant, and minimum 20-year labor and material warranty. Panels must comply with ASTM A 446 G90 coating designation, feature standing seams of at least 2.5 inches for lower slopes and 1.75 inches for steeper slopes, and include leak barriers complying with ASTM D1970 and UL 790 Class A standards. For asphalt shingles, specifications require impact-resistant, laminated-strip architectural shingles complying with ASTM D3462/D3462M with UL 2218 Class 4 impact resistance, capable of resisting 80 mph wind speeds, and featuring a minimum 30-year labor and material warranty. For cedar shingle roofing at the Darby Visitor Center (a historic building), contractors must provide Western Red Cedar Number One Grade edge grain heartwood shingles certified by the Cedar Shake and Shingle Bureau, install them with triple coverage construction using hot-dipped zinc-coated box nails, and comply with the Secretary of Interior's Standards for Rehabilitation of Historic Buildings. Cedar shingle specifications include detailed requirements for ice barriers, flashing materials, ridge caps, roof anchors meeting OSHA and ANSI Z359.1-07 standards, and decorative elements such as double-coursing and staining with Amteco TWP 318. The manual establishes the Contracting Officer Representative as Shawn Boelman, Bitterroot NF Facilities Engineer, and mandates that all work proceed only after substrate preparation is complete and weather conditions comply with manufacturer recommendations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL FOR:
BRF FY26 ROOFING PROJECTS
Stevensville, MT 59840 Darby, MT 59829
Date: June 29, 2026
BID SPECIFICATIONS
PROJECT INFORMATION SHEET
BRF FY26 ROOFING PROJECTS
PROJECT LOCATION
Stevensville Ranger Station 88 Main Street Stevensville, MT 59808
West Fork Ranger Station 6735 West Fork Road Darby, MT 59829
Darby Ranger Station 712 North Main Street Darby, MT 59829
CONTRACTING OFFICER REPRESENTATIVE:
U.S. Forest Service Shawn Boelman Bitterroot NF – Facilities Engineer shawn.boelman@usda.gov
BTR FY26 ROOFING PROJECTS
TABLE OF CONTENTS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 410 PREFORMED ROOFING AND SIDING………………………………………………………………..2 7 310 ASPHALT SHINGLES……………………………………………………………………………………….4
07 312 CEDAR SHINGLES……………………………………………………………………………………… 6
SECTION 07410
PREFORMED ROOFING AND SIDING
1.0 DESCRIPTION OF WORK: This specification covers the furnishing and installation of preformed roofing panels. It is the Contractors responsibility to verify all field dimensions. Products shall match existing materials and/or shall be as directed by the Contracting Officer. Installation procedures shall be in accordance with the product manufacturer's recommendations. Demolition and removal of materials shall be as required to support the work.
1.1 Wind Uplift Resistance: Roofing system to comply with U.L.90 requirements.
1.2 Submittals: Provide complete product submittal with shop drawings.
1.3 Roof system shall have a minimum of a 20-year labor and material warranty.
2.0 PRODUCTS:
2.1 Standing Seam Roofing:
2.1.1 General: Roof-covering panels shall be fabricated of zinc-coated steel conforming to ASTM A 446, G90 coating designation or aluminum-coated steel. Panels shall be supplied in 24 gauge. Roof covering shall be sized as required for span and loading. Panels shall have configurations designed for mechanically formed lock seams for securing adjacent sheets. Sealant for standing seams shall be factory-applied. Width of sheets shall provide not less than 12 inches of coverage in place. Height of standing seam shall be not less than 2-1/2 inches for slopes less than 3 inches in 12 inches, and not less than 1-3/4 inches for slopes 3 inches in 12 inches or greater.
2.1.1.2 Color Coating: Color finish shall consist of either a synthetic resin base coating applied to a pretreated and primed surface or a dry film coating material bonded to the metal substrate with adhesive. Dry film thickness of color coat shall be not less than 0.8 mil for exterior surface finish.
2.1.2 ACCESSORIES
Leak Barrier: mineral surfaced, 36”- wide, complying with ASTMD1970, UL Listed ANSI/UL 790 Class A system.
Roof Deck Protection: Synthetic Roofing Felt, 36” or 48”-wide, Type II, complying with ASTM D226 Type II, ASTM D8257, and ASTM D4869
2.1.3 Accessories shall include flashing, trim, caps, and similar accessories of not less than the minimum thicknesses specified for roofing. Accessories of zinc-coated steel used with aluminum-coated steel shall be painted. Molded closure strips shall be closed-cell or solid-cell synthetic rubber, neoprene, or polyvinyl chloride premolded to match configuration of the covering.
2.1.4 Panel Clips shall be of two-piece construction with movable tabs.
Clips shall provide for at least 2 inches of panel movement. Tabs shall be designed to be folded into the lock seam.
2.1.5 Fasteners shall be zinc-coated steel or corrosion-resisting steel.
2.1.5.1 Screws shall be not less than No. 14 diameter if self-tapping type and not less than No. 12 diameter if self-drilling and self-tapping type.
2.1.5.2 Blind Rivets shall be stainless steel.
2.1.5.3 Bolts shall be not less than 1/4-inch diameter, shouldered or plain shank, as required, with proper nuts.
3.0 EXECUTION
3.1 PREPARATION OF SUBSTRATE
A. Remove existing metal roofing and any underlayment covering the roof sheeting.
B. Cover knotholes or other minor voids in substrate with sheet metal flashing secured with roofing nails.
C. Do not install metal roofing until all vent stacks and other penetrations through roofing have been installed and are securely fastened against movement.
3.2 INSTALLATION
3.2.1 General: Installation shall include all standard fasteners, flashings, sealants, gaskets, closure strips, trim, and insulation associated with roofing. Provide expansion joints where required.
END OF SECTION
SECTION 07311
ASPHALT SHINGLES
1.0 DESCRIPTION OF WORK: This specification covers the furnishing and installation of asphalt shingles. It is the Contractors responsibility to verify all field dimensions. Products shall match existing materials and/or shall be as directed by the Contracting Officer. Installation procedures shall be in accordance with the product manufacturer's recommendations. Demolition and removal of materials shall be as required to support the work.
1.1 Wind Uplift Resistance: Asphalt shingles will resist blow-off or damage caused by wind speeds up to 80 mph..
1.2 Submittals: Provide complete product submittal with shop drawings.
1.3 Roof system shall have a minimum of a 30-year labor and material warranty.
2.0 PRODUCTS:
2.1 Glass-Fiber-Reinforced Asphalt Shingles:
2.1.1 General: Impact-Resistant, Laminated-Strip Asphalt Shingles (ie., dimensional and architectural shingles): ASTM D3462/D3462M, laminated, multi-ply overlay construction; glass fiber reinforced, mineral-granule surfaced, and self-sealing; with impact resistance complying with UL 2218, Class 4..
2.1.1.2 Color: Color should match current color. Submit color samples to CO for approval.
2.1.2 ACCESSORIES
Leak Barrier: mineral surfaced, 36”- wide, complying with ASTMD1970, UL Listed ANSI/UL 790 Class A system.
Roof Deck Protection: Synthetic Roofing Felt, 36” or 48”-wide, Type II, complying with ASTM D226 Type II, ASTM D8257, and ASTM D4869.
Starter Strip: ASTM D3462/D3462M, D3018, D3161 Class F; glass-fiber reinforced, mineral-granule surfaced, and self-sealing
2.1.3 Accessories shall include flashing, trim, caps, and similar accessories.
3.0 EXECUTION
3.1 PREPARATION OF SUBSTRATE
A. Remove existing metal roofing and any underlayment covering the roof sheeting.
B. Cover knotholes or other minor voids in substrate with sheet metal flashing secured with roofing nails.
C. Do not install asphalt shingles until all vent stacks and other penetrations thorugh roofing have been installed and are securely fastened against movement.
3.2 INSTALLATION
3.2.1 General: Installation shall include all standard fasteners, flashings, sealants, gaskets, closure strips, trim, and insulation associated with roofing. Install per manufacturer’s recommendations
END OF SECTION
SECTION 07312
CEDAR SHINGLES
1.1 DESCRIPTION OF WORK
A. Provide labor, equipment, and materials to reroof the Darby Visitor Center. Work shall consist of stripping off the old shingles and underlayment (if existing) and disposing of the material in an approved dump site, repairing or replacing sheathing if needed, installing new cedar shingles with underlayment, installing roof anchors, and all other necessary work to deliver a complete, sound, professional, weathertight roofing system.
B. Buildings are Forest Service owned and are listed on or considered eligible for listing on the National Register of Historic Places. Therefore, all work shall adhere to guidance from the Secretary of Interior’s Standards for Rehabilitation of Historic Buildings.
1.2 SUBMITTALS
A. Submit technical product data, installation instructions, and recommendations from shingle manufacturer, the Cedar Shake and Shingle Bureau, and any other relevant installation information, including data that materials comply with requirements.
1.3 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials in manufacturer’s unopened bundles, rolls, or containers with labels intact. All materials must be new, unexpired, and in good condition.
B. Store materials to avoid water damage and store rolled goods on end. Comply with manufacturer’s recommendations for job-site storage and protection.
1.4 UNKNOWN FINDS
A. As with all historic buildings, some construction elements, conditions, material types, artifacts, and archaeological materials, features, and/or artifacts may be hidden upon initial inspection. If previously hidden elements, conditions, material types, artifacts, and/or archaeological materials, features, and/or artifacts are revealed, cease work in the immediate and/or affected area(s) and contact the Forest Service COR and/or Inspector immediately. No work is to be performed outside the scope of this contract.
1.5 JOB CONDITIONS
A. All other areas of the structure, vegetation, and grounds are to be fully protected from the impacts of this work. Do not damage surrounding building fabric, elements, or structure in any way. Do not attach, nail, or staple any item(s) to the structure unless it is directly related to the roof work and approved by the COR.
B. If vegetation or trees are in the way of scaffolding, ladders, and/or equipment, consult with the COR regarding the vegetation or trees before cutting and pruning.
C. Be aware of constantly changing weather conditions and the potential impact to the structure and ongoing work. If work should be rescheduled or redirected due to weather conditions, consult with the COR. Keep all work areas dry and free of construction debris and snow, ice, and water. Protect all work and all areas of the structure from the effects of precipitation and weather. The contractor is responsible for any and all damage that may occur due to their negligence or failure to protect the structure. If removing structural elements of the facility (e.g. sheathing), consider the effects of worker loading, wind loading, etc. and sequence work appropriately.
D. Complete daily cleanup of the job site. Where demolition work creates debris, including in the interior of the building, clean this debris up promptly. Where the opening of previously closed spaces uncovers objectionable material, provide cleanup of up to 1 five gallon bucket per square of roofing. Follow all related CDC and OSHA guidelines.
E. Proceed with installation work only after substrate construction and penetrating work have been completed.
F. Proceed with installation work only when weather conditions are in compliance with manufacturer’s recommendations and when substrate is completely dry.
G. Provide temporary barriers to keep the public at a safe distance away from the project.
PART 2 – PRODUCTS
2.1 WOOD SHINGLES
A. Shingles must be Western Red Cedar, Number One Grade, edge grain, heartwood, and certified by the Cedar Shake and Shingle Bureau. Shingles shall conform with CSSB-97. The Bureau’s website can be found at: http://www.cedarbureau.org/.
B. Upon delivery, shingles will be inspected for the CSSB label.
a. Blue Label American Certified shingles are not acceptable C. Shingle type
a. 16 inch, also called FiveX
b. 18 inch, also called Perfection
c. 24 inch, also called Royals D. Shingle weather exposure: Use the existing exposure found on the historic building. Shingle exposure is usually:
a. 4 ½ or 5 inches for 16 inch shingles
b. 5 ½ inches for 18 inch shingles
c. 7 1/2 inches for 24 inch shingles
2.2 NAILS
A. For roof: hot-dipped zinc-coated box nails which shall be long enough to penetrate into sheathing half to three-quarters of the way. Do not fully penetrate the sheathing. Use 3d nails for 16 inch (FiveX) shingles. Nails for 18 and 24 inches shingles may range from 3d to 8d, depending on the size and thickness of the shingles. Follow shingle manufacturers guidelines when selecting nail weight.
B. For hips and ridges: hot-dipped zinc-coated box nails which shall be long enough to penetrate into sheathing half to three-quarters of the way. Do not penetrate the sheathing. Nails may range from 4d to 8d.
2.3 ICE BARRIER
A. Self-adhering rubberized roofing membrane, Grace Ice and Water Shield for non-metal roofs, or equal.
2.4 SHEATHING
A. Match existing – use one of the following
a. ¾ inch rough sawn or dimensional lumber. Use select grade kiln-dried fir or larch lumber.
b. 1 x 6 shiplap lumber. Use select grade kiln-dried fir or larch lumber.
c. 1 x 8 shiplap lumber. Use select grade kiln-dried fir or larch lumber.
2.5 FLASHING
A. Galvanized steel flashing
a. 32 gauge for sheet or rolled flashing used as step, apron, cap, and counterflashing.
b. 26, 28, or 30 gauge valley flashing, either V or W shaped to match existing.
B. Rubber boot flashing
a. Only to be used on vent pipes. May be supplemented with galvanized steel flashing.
C. Lead flashing
a. If lead flashing is found, consult with the COR regarding its reuse.
i. If the flashing is in good condition, reuse if practicable in place of galvanized or rubber boot flashing.
ii. Follow all appropriate OSHA and CDC guidelines when working with lead.
2.6 RIDGECAP
A. The ridge cap should either match existing or match historic photos.
B. Ridge cap
a. Board – 1 x 6 or 1x8 cedar boards, smooth side up, kiln dried, select grade. Choose a board sized ½ to 1 inch wider than the exposure
b. Shingle – Shingle ridge caps are to be constructed on site or with pre-manufactured units that match the new roof.
a. Metal – If the existing ridge cap is in good condition, reuse the existing. Otherwise, match the new ridge cap to the existing with 26, 28, or 30 gauge galvanized steel metal.
i. Metal ridge caps may or may not have end caps. If the existing ridge cap has end caps or the historic photos show end caps, replace in kind. If the existing end caps are in good condition, reuse the existing. Otherwise, match the new end caps to the existing with 26, 28, 30, or 32 gauge galvanized steel metal.
2.7 ROOF ANCHORS
A. Permanent single D-ring roof anchors, stainless steel or powder-coated steel.
a. Must meet OSHA and ANSI Z359.1-07 requirements.
b. Acceptable Manufacturers
i. Miller by Honeywell RA41
ii. Guardian Fall Protection 00500 Single D
iii. Guardian Pitch Pro 10540 in Black
c. May be used by roof installer as part of a Fall Protection Plan
2.8 DRIP EDGE
A. No metal or other drip edge is to be installed.
2.9 GUTTERS
A. If gutters and/or downspouts are existing on the building, remove, inspect, and replace as needed. Use only galvanized half round gutter and matching downspouts, 24 or 26 gauge in 5 or 6 diameter or match existing diameter. Install according to manufacturer’s direction.
B. Do not install modern or “K” gutters.
3.0 DECORATIVE ELEMENTS
A. If decorative elements occur, replace in-kind. Decorative elements can include:
a. Double coursing. If this is present, it is usually a double course of shingles every fourth course. Replace in-kind to match the original.
b. Stained shingles. Some Forest Service roofs were stained dark green. For these roofs, once the roof has been completed, stain all shingles, including the faces and edges, with Amteco TWP 318.
c. Decorative letters. Some Forest Service roofs had metal letters attached to the roof for aircraft identification. Other roofs had letters painted or stained on. If letters are located, replace in kind or reattach the existing.
PART 3 – EXECUTION
3.1 GENERAL
A. Clean substrate of any projections and substances detrimental to roofing work.
B. Remove all nails, screws, staples, etc. Do not pound nails, staples, etc. into the sheathing or pound flat. All nails, screws, staples, etc., must be removed. Use a magnet to pick up all nails, screws, staples, flashing, etc. from the ground.
C. Coordinate installation of shingles with flashing and other adjoining work to ensure proper sequencing.
D. Do not install shingle roofing until all vent stacks and other penetrations through roofing have been installed and are securely fastened against movement.
E. Hand-nailing the shingles is preferred; however, pneumatic and/or battery tools are acceptable provided the air pressure and/or tool pressure is checked hourly to ensure the nails are driven flush with the surface of the shingle. Nails must not be left proud, nor must they be driven below the surface of the shingle.
F. Personnel working on the roof are not allowed to wear spiked or cleated shoes in order to prevent damage to the shingles. Soft-soled shoes only.
G. If the contractor uses a harness and/or safety rigging to conduct roof work, the contractor must supply a Fall Protection Plan that complies with applicable OSHA standards. The Forest Service COR and/or the Inspector may provide their own harness and/or safety rigging that also complies to these standards.
H. Adjust exposure if necessary when about midway between eave and ridge so that coursing will appear uniform. Ensure that the coursing is even within the last 3 courses of the ridge cap.
I. Do not use broken shingles. Do not use shingles less than 4 inches in width. Do not use shingles over 10 inches in width. Shingles over 10 inches may be cut or cleanly split down to the appropriate width.
J. Install flashing around projections through roof as required to make a watertight structure.
3.2 ROOF APPLICATION
A. Replace sheathing that has experienced excessive rot/decay. Any sheathing boards that have rot pockets that penetrate through the board, are more than 3 inches in size, or affect more than 25 percent of the board must be replaced in kind. Boards may be fully replaced, replaced between joists, or several roof joists depending on the severity of rot.
1. Mark sheathing to be replaced with a grease pencil, chalk, or other non-permanent method.
2. Allow COR to observe sheathing marked for replacement prior to any removal
3. Boards marked for removal can be plunge cut and/or removed by pulling the nails. Do not damage adjacent boards.
4. The maximum amount of sheathing to be removed at a time is limited to 25% of the roof deck or as specified by the COR.
B. In addition to details indicated, comply with installation details and recommendations of the Reroofing with Wood Shakes and Reroofing with Wood Shingles sections from “Dovetails and Broadaxes: Hands-on Log Cabin Preservation, found at http://fsweb.mtdc.wo.fs.fed.us/pubs/pdfpubs/pdf15232802/Part08-Pages-165-196.pdf. Shake information starts on page 187, shingle information starts on page 181.
1. Install ice and water shield over the entire roof in lieu of felt underlayment. Install according to manufacturer’s recommendations. If installing on a warm or hot day, ensure that the underlayment is not damaged by workers during the install.
2. Use hot-dipped zinc-coated box nails which shall be long enough to penetrate into sheathing half to three-quarters of the way. Do not fully penetrate the sheathing. Nails may range from 3d to 8d. Note that nail penetration only acceptable on the starter courses, other sheathing nail penetration is not acceptable.
3. Use triple coverage roof construction, with a triple starter course. Please see the Reroofing with Wood Shakes and Reroofing with Wood Shingles sections from “Dovetails and Broadaxes: Hands-on Log Cabin Preservation, found at http://fsweb.mtdc.wo.fs.fed.us/pubs/pdfpubs/pdf15232802/Part08-Pages-165-196.pdf. Shingle information starts on page 181.
4. Install roof with 1 inch overhang on rake edge and 1 ½ inches on eave edge unless specified otherwise.
5. Install shingles, beginning at lower end with a triple layer starter course, projecting shingles 1 ½ inches beyond sheathing. Space adjoining shingles ¼ inch to 3/8 inch apart, nailing each shingle with two nails spaced ¾ to 1 inch from edge of shingle and 1 ¼ to 2 inches above exposure line of subsequent courses. Stagger edge joints a minimum of 1 ½ inches in succeeding courses. Do not stack joints. Ensure no stacked joints in the course being laid and the two courses below (triple coverage roof). Install shingles to provide weather exposure as indicated. Cut and fit shingles at ridges and edges to provide maximum weather protection.
6. Lay with butts as straight as practicable considering the texture of the shingles.
7. Use two nails per shingle at least 1 inch from edge and about 1 inch or 2 inches above the butt line of the following course. Ensure that the heads of each nail remain on the surface of the shingle - do not pound the nail head into the shingle. Do not use waffle-head hammers, only smooth head hammers.
8. Do not use broken shingles. Do not use shingles less than 4 inches in width. Do not use shingles over 10 inches in width. Shingles over 10 inches may be cut or cleanly split down to the appropriate width.
9. Ensure that nails are set flush with the surface of the shingle. Do not over or under drive nails.
a. Hand-nailing the shingles is preferred; however, pneumatic and/or battery tools are acceptable provided the air pressure and/or tool pressure is checked hourly to ensure the nails are driven flush with the surface of the shingles. Nails must not be left proud, nor must they be driven below the surface of the shingle.
b. Nails must penetrate at least halfway through the thickness of the sheathing but must not penetrate completely through the sheathing except for the starter courses.
c. Ensure that nail heads are not exposed (no “shiners” are allowed).
d. Use only smooth-faced hammers.
C. Flashing
1. If applicable, remove and re-install the existing metal ridge or hip caps. Metal hip caps damaged from removal shall be replaced at contractor’s expense.
2. Install metal flashing and vent flashing as needed and in accordance with details and recommendations of the Reroofing with Wood Shingles section from “Dovetails and Broadaxes: Hands-on Log Cabin Preservation, found at http://fsweb.mtdc.wo.fs.fed.us/pubs/pdfpubs/pdf15232802/Part08-Pages-165-196.pdf, starting on page 169.
3. Install step flashing as needed along dormers, chimneys, etc. as needed and in accordance with details and recommendations of the Reroofing with Wood Shingles section from “Dovetails and Broadaxes: Hands-on Log Cabin Preservation, found at http://fsweb.mtdc.wo.fs.fed.us/pubs/pdfpubs/pdf15232802/Part08-Pages-165-196.pdf, starting on page 169.
4. Replace valley flashing in accordance with details and recommendations of the Reroofing with Wood Shingles section from “Dovetails and Broadaxes: Hands-on Log Cabin Preservation, found at http://fsweb.mtdc.wo.fs.fed.us/pubs/pdfpubs/pdf15232802/Part08-Pages-165-196.pdf, starting on page 175. Valleys should have 4 to 8 inches of exposed metal in the middle and extend 8 to 12 inches beyond the centerline of the valley.
D. Roof Anchors
1. Permanent roof anchors are to be installed in several locations in the roof face. The contractor is to create a permanent roof anchorage plan prior to commencing roof work and coordinate the plan with the COR.
a. Roof anchors are to be set into a joist or purlin according to the manufacturer’s directions, using appropriate fasteners.
b. For an L-4 lookout roof, 8 roof anchors are to be set in the roof. Four anchors are to be set 6 to 12 inches from the eave edge, in the center of each hip roof. An additional four anchors are to be set 6 to 12 inches below the peak in the center of each hip roof.
c. For a gable roof, set anchors so that a person can climb to the peak of the roof, move along the peak, and reach all eaves. For example, anchors may be set in a line up the roof face and along the peak: Set the first anchor 6 to 12 inches from the eave edge and continue up the roof face with anchors set 6 to 8 feet apart until reaching the peak; then set anchors 6 to 8 feet apart 6 to 12 inches below the ridge cap for the length of the ridge cap. If the roof face is large enough, repeat the roof face anchor line in two or three places.
E. Ridge caps
1. Shingle ridge caps are to be constructed on site or with pre-manufactured units that match the new roof. The ridge cap shingles must be 1 inch wider than the exposure. Create or purchase ridge cap shingles and install them in accordance with details and recommendations of the Reroofing with Wood Shingles section from “Dovetails and Broadaxes: Hands-on Log Cabin Preservation, found at http://fsweb.mtdc.wo.fs.fed.us/pubs/pdfpubs/pdf15232802/Part08-Pages-165-196.pdf, starting on page 192.
2. Board ridge caps are to be constructed from cedar 1 x 6 or appropriate width cedar boards. Overlap the boards on the ridge and at joints.
3. Metal ridge caps may be reused if they are in good condition. If the ridge caps must be replaced, replace in kind. If end caps are or were present, re-install to match original.
F. Extra Stock
1. Provide one unopened clearly labeled bundle of shingles for future maintenance use by the Government.
image1.jpeg