C04a RFI QA 1240LT27Q00003.docx

DOCX document 49 KB Posted

Download DOCX, 49 KB

Attached to
GAOA Mesa Falls VC Roof Repairs in Caribou-Targhee National Forest, Idaho
Solicitation number
1240LT27Q0003
Issued by

About this file

This is a Request for Information (RFI) Question and Answer document for solicitation 1240LT27Q0003, a Total Small Business Set-Aside project for roof and exterior maintenance work at the Mesa Falls Visitor Center on the Caribou-Targhee National Forest in Fremont County, Idaho. The project scope includes removal and replacement of corrugated metal roof panels, removal of existing metal trim and flashing with replacement, preparation and staining/painting of all exterior log walls and wood shingle walls, repair of exterior woodpecker damage, repair of damaged overhang framing at the southwest corner, and proper disposal of all demolished materials. Base bid work consists of mandatory corner overhang repairs (realignment/jacking of sagging framing and replacement of one damaged round rafter tail with a matching peeled round log member), with two optional bid items: Optional Item #1 for perimeter overhang framing and decking repairs and Optional Item #2 for snow guards. The anticipated start date is June 2027, with a 90-calendar-day performance period after Notice to Proceed, work to commence within 10 days of NTP, and all work including final cleanup to be completed within the performance window.

Key technical requirements address roofing material specifications, confirming that 20-gauge, 7/8-inch corrugated metal panels with 32-inch net coverage (per Drawing A4.02 Detail 3) govern over conflicting specification references; panels must have a factory coil-coated PVDF/Kynar 500 paint system in weathering steel/Corten appearance (such as Western States Metal Roofing or Bridger Steel products) with metallic-coated substrate (ASTM A653 G90 or ASTM A792 AZ50); high-temperature self-adhering underlayment rated 240°F or higher with a separate slip sheet is required; approximately 142 linear feet of continuous pre-finished metal ridge ventilation is required (115-120 linear feet active ventilation, 25-30 linear feet solid closures); the roof quantity is 49 squares (Design Quantity) for payment purposes; all subcontractor substitution requests will be evaluated during the submittal process with the awardee. Wage determination General Decision ID20260021 for Fremont County (posted with Amendment 0001) applies, with CARP0808 Zone 3 pay rates for locations more than 60 miles from Idaho Falls post office. The solicitation is a simplified acquisition using FAR Part 12 (Commercial Items), evaluated on lowest price technically acceptable, with sealed quotes submitted by email to PPS.proposals@usda.gov (later amended to Blaine.Greenwalt@usda.gov) in four separate Adobe PDF documents (signed SF1442, Schedule of Items, Technical Proposal, and scanned Bid Guarantee SF24 with Power of Attorney). The original quote due date of December 1, 2026, was extended to December 4, 2026, by Amendment 0001. A bid guarantee of 20 percent of the base bid plus options is required; performance and payment bonds at 100 percent of the contract price must be furnished within 10 days after award. The site visit held October 27, 2026, was not mandatory; the attendance roster was posted with Amendment 0001. The prime contractor must be a small business registered in SAM.gov under NAICS 238160 (Structural Steel and Precast Concrete Contractors); past performance references may be satisfied by the proposed subcontractor's experience, and subcontractors may attend the site visit on behalf of the prime. The Federal Acquisition Regulation clause 52.219-14 (Limitations on Subcontracting) does not apply as the anticipated contract value is below the simplified acquisition threshold. No hazardous materials (lead-based paint or asbestos) are anticipated, and all permits and licenses remain the contractor's responsibility per FAR 52.236-7.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

REQUEST FOR INFORMATION (RFI) FORM

Request For Information (RFI) Form

1240LT27Q0003

GAOA Mesa Falls VC Roof Repairs, Idaho Caribou-Targhee National Forest All RFI answers are for clarification purposes only.

RFI #1 – Should cracks in logs be filled?

Reference keyed notes in drawings. “Prep and stain all log walls….Inspect log surfaces for holes, cracks, or imperfections and fill them with wood fillers.”

RFI #2 – Does stain on log walls need stripped before re-staining?

Reference specification 099300-Staining and Transparent Finishing- “Comply with manufacturer's written instructions. “ RFI #3 – Attachment 4 is General Decision ID20260100, which lists Bonneville County only. Attachment 3, sheet G-01, places the Mesa Falls Visitor Center in Fremont County, which General Decision ID20260021 covers for Building construction. Please confirm which wage determination will be incorporated in the resulting order. If ID20260021, please confirm whether the CARP0808 Zone 3 pay (more than 60 miles from the Idaho Falls post office) applies to this site.

Amendment 0001 updates the Davis Bacon Act (DBA) determination to reflect the location of Fremont County. Please see file labeled “C04c General Decision ID20260021 05182026.”

RFI #4 – Attachment 4 wage decision ID20260100 names Bonneville County, while the drawing cover names Fremont County. Which county, wage decision and labor classifications govern this work? Please issue a correction if needed.

Please see RFI #3.

RFI #5 – Drawing A1.01 shows approximately 4,490 square feet of roof. The schedule lists 49 SQ each for metal roofing and ice-and-water shield. Which quantity controls pricing and payment, and is the difference an allowance or intended field adjustment?

The “DQ” in the method of measurement in the Schedule of Items stands for “Design Quantity” or estimated quantity. Line items with this designation will be paid for the full estimated design quantity rather than the actual quantity unless the actual quantity varies by more than 15% from the design quantity. In fixed-price construction contracts with unit-priced items, if the actual quantity of work varies by more than 15% above or below the estimated quantity in the design, either party can demand an equitable price adjustment RFI #6 – The general scope calls snow guards an option and Section 077253 specifies them, but the schedule has only Option 1 for round overhang framing. Please identify the snow-guard line, required quantity and layout, or provide an amended price schedule.

Snow guards were removed from the final design. Ignore relic references.

RFI #7 – Section 074113 describes G90 galvanized or AZ50 coated pre-painted sheet and also an exterior Weathering Steel finish. It lists 29.3-inch panel coverage, while drawing A4.02 detail 3 shows 32-inch roof coverage. Please identify the required compliant material, finish, panel profile and effective coverage for pricing.

Governing Requirement: The contract drawings govern panel gauge, profile, and installation layout.

Panel Profile & Thickness: Panels shall be heavy-duty 20-gauge steel, 7/8-inch corrugated profile (2.67" corrugation pitch ×7/8" rib height), complying with Drawing A1.01 (Keynote 01), Sheet A4.01 (Details 1, 2, and 3), and Sheet A4.02.

Panel Coverage: For all roof applications, panels shall be installed with a 2-corrugation side lap providing 32 inches net coverage as detailed on Sheet A4.02 (Detail 3). (The 29.3-inch mention in Section 074113 is superseded by Detail 3/A4.02 for steep-slope/snow performance).

Material & Finish: Substrate shall be metallic-coated structural steel sheet (ASTM A653 G90 or ASTM A792 AZ50). Finish shall be a factory coil-coated PVDF/Kynar 500 paint system in a 'Weathering Steel / Corten' color/appearance (as offered by Western States Metal Roofing, Bridger Steel, or approved equal). Bare/unpainted rusting Corten is not permitted to prevent rust-runoff staining on historic logs and wood shingle siding.

(Contractor Note: Coordinate fastener schedule and mastic placement per Detail 3 on Sheet A4.02).

RFI #8 – The roofing section includes ice-and-water shield, planking and flashing in roofing measurement and payment, while the schedule separately lists underlayment and framing. Please clarify each line item boundary to avoid omitted or duplicated pricing.

Refer to Measurement and Payment section of specification 61600. Snow and Water Shield is a separate payment item under 61600, the rest falls under the roofing line item of 61600.

RFI #9 – Bid guarantee Block 13b requires one. This is a Part 12 RFQ evaluated on lowest price technically acceptable, with quotes by email and no public opening.

Will the Government consider waiving it under FAR 28.101-1(c)?

No RFI #10 – Wage determination Attachment 4 is the Bonneville County decision (ID20260100). Drawing G-1 puts the project in Fremont County. Which wage determination applies?

Please see RFI #3.

RFI #11 – Snow guards The scope lists snow guards as an optional item, but the Schedule of Items has no line for them.

Please see RFI #6.

RFI #12– Roof panels Section 074113 calls for 0.034 in. weathering steel at 29.3 in. coverage. The drawings call for 20 gauge pre-finished panels, and Detail A4.02 shows 32 in. coverage. Which gauge, finish and coverage controls?

Refer to RFI #7 RFI #13 – Based on the Period of Performance and time if year, is there a winter suspension time frame?

The anticipated start date is in June of 2027 with work being completed 90 days after the NTP.

RFI #14 – There is not a clin line for the optional snow guards. How should we incorporate our price?

Refer to RFI #6 RFI #15 – Roof quantity and measurement. Attachment 1 SOI lists 49 SQ of metal roofing and 49 SQ of ice-and-water shield, while drawing A1.01 notes approximately 4,490 SF of roof area. Please confirm the controlling bidding/payment quantity, whether the 49 SQ includes waste, and whether the drawing area is the actual sloped roof surface area.

Refer to RFI #5 RFI #16 – Roof panel material and finish. The SOI/drawings call for 20-gauge, 7/8-inch corrugated roofing. Section 074113 specifies nominal thickness 0.034 inch and describes metallic-coated/pre-painted steel but also lists exterior finish as Weathering Steel. Please confirm the required base metal, thickness/gauge, coating, finish and color, and whether weathering steel or a factory prefinished coated panel is intended.

Refer to RFI #7 RFI #17 – Snow guards and option pricing. The general scope and Section 077253 describe snow guards, but Attachment 1 SOI provides only Option 1 for overhang framing repairs and no separate snow-guard pay item. Are snow guards required in the base, included in Option 1, a separate option, or excluded? If required, please provide the quantity/layout/design criteria, compatible attachment requirements for the corrugated roof, and a revised pricing schedule.

Refer to RFI #6 RFI #18 – Base framing repair and Option 1. Please distinguish the mandatory corner-overhang repair from Option 1. For the base repair, please identify the round members, connections and decking to repair/replace and any required dimensions, timber species/grade and support details. For the lump-sum option, please provide an estimated extent or defined allowance and explain how concealed damage beyond that extent will be authorized and paid.

1. Base Bid (Mandatory Work):

· Location: Restricted strictly to the Southwest (SW) corner overhang as delineated on Sheet A1.02 (Keynotes 01, 02, and Photos 01, 02, and 04) and Section 061323 Paragraph 1.5.A.

· Scope: Realign/jack sagging outrigger and roof framing back to level/plumb alignment to eliminate gaps. Replace the one (1) dislocated/damaged round rafter tail shown in Photo 02 with a matching peeled round log member (Douglas Fir or Western Larch, No. 1 or select rustic grade, treated per Section 061323, diameter to match existing adjacent tail, approx. 6"–8" dia.). Secure connections using concealed structural timber screws/ties per Section 061323. Inspect and repair/refasten adjacent 2x tongue-and-groove plank roof decking at this isolated corner only.

2. Optional Bid Item #1 (Perimeter Overhang Framing & Decking):

· Scope: Per Sheet A1.02 Keynote 03 and Section 000501 Paragraph 1.3.B, Option 1 encompasses potential localized repairs to round log tails, outriggers, and plank decking around the remaining roof perimeter overhangs discovered upon full tear-off of existing roofing.

· Bidding Basis: Bidders shall price Optional Bid Item #1 as a Lump Sum allowance based on repairing up to twenty (20) linear feet of deteriorated 2x plank roof decking and replacing up to two (2) additional round rafter tails matching existing dimensions.

3. Concealed / Unforeseen Damage Beyond Specified Extent:

· Any structural rot, compromised timber framing, or broken decking discovered after roof tear-off that exceeds the base bid scope and Option 1 defined allowance shall be immediately documented and reported to the Contracting Officer (CO) and COR.

· Work beyond this baseline will be negotiated and authorized via formal contract modification under FAR 52.243-4 (Changes) and paid per the established contract change order procedures. Contractors shall not perform unauthorized structural removals without prior written direction from the CO.

RFI #19 – Roof decking and underlayment payment. Section 074113 measurement/payment includes ice-and-water shield and planking/decking in the roofing price, while the SOI prices the membrane separately and has no separate deck-repair allowance. Please confirm the scope allocated to each item, the estimated decking repair/replacement quantity and material, and how additional concealed deck damage will be measured, approved and paid without duplicate pricing.

Deck repair of damaged sections discovered during tear off will be considered a change condition and paid for through a contract modification.

RFI #20 – Applicable wage determination. The drawings locate the project in Fremont County near Ashton/Upper Mesa Falls, but Attachment 4, ID20260100 dated May 18, 2026, identifies Bonneville County. Please confirm the correct project county and applicable wage determination, including any correction required before quotations are due.

Please see RFI #3.

RFI #21 – Hazardous materials and surface preparation. Please confirm whether lead-based paint, asbestos or other hazardous-material surveys are available for the roofing, coatings, window/door trim and wood surfaces disturbed by this project. If present, please identify required testing, containment, removal/disposal and payment responsibilities and provide available survey reports.

No LBP or asbestos anticipated on this project.

RFI #22 – Construction period and public access. The specifications anticipate a June 2027 start and the solicitation allows 90 calendar days after NTP, with commencement within 10 days. Please confirm the anticipated NTP/construction window, whether the visitor center remains occupied/open, and any seasonal closures or access restrictions affecting scaffolding, roof work, timber repair and exterior painting/staining.

The anticipated start date is in June of 2027 with work being completed 90 days after the NTP.

RFI #23 – Site visit confirmation. Please confirm that the organized site visit remains Tuesday, October 27, 2026, at 10:00 a.m. Mountain Time at the Mesa Falls Visitor Center at Upper Mesa Falls. Is advance RSVP required, is attendance mandatory, and are there any special entry or PPE requirements?

A site visit was conducted on October 27, 2026, and was NOT mandatory.

RFI #24 – Would the government consider a standing seam, concealed fastener roof rather than corrugated metal? The corrugated metal will require maintenance when the rubber screw gaskets wear out. Since it's a 12:12 pitch, that maintenance will be expensive.

All substitution requests will be handled during the submittal process with the awardee.

RFI #25 – May J&D rely on the experience and past performance of its proposed subcontractor to satisfy the technical qualification requirements?

Please see Non-Price Factor 2 – Past Performance for the complete details required for the Request for Quote. Offeror must furnish a list of three (3) projects of similar magnitude completed by the firm within the last three (3) years.

RFI #26 – May an authorized representative of our proposed subcontractor attend the October 27 mandatory site visit on behalf of J&D?

A site visit was conducted on October 27, 2026, and was NOT mandatory. Any contractors prime/sub were welcome to attend.

RFI #27 – Are there any specific prime-contractor licensing, experience or self-performance requirements that would prevent this arrangement?

All necessary licenses/permits are the responsibility of the prime contractor.

RFI #28 – Can the required bid, performance and payment bonds be obtained through a qualified subcontractor, or must they be issued directly on behalf of J&D as the prime contractor?

The bid guarantee and performance and payment bonds shall be provided by the prime contractor.

RFI #29 – Does the Forest Service permit multiple subcontractors for the roofing, exterior painting/staining and carpentry portions of the project?

The offeror shall determine the makeup of their sub-contractors.

RFI #30 - Please clarify which metal roof panel requirement governs: the 20-gauge panels identified on Drawings A1.01 and A2.01-A2.04 or the nominal 0.034-inch thickness specified in Section 074113, Paragraph 2.1. Please identify the minimum required base-metal thickness.

Refer to RFI #7 RFI #31 - Please confirm the required roofing panel and trim finish. Section 074113 references a weathering steel finish while also specifying metallic-coated, coil-prepainted steel; drawings refer to prefinished metal. Is natural weathering steel, a factory-painted weathered-steel look, or a specific PVDF-coated finish required? Please identify the approved color/finish.

Refer to RFI #7 RFI #32 - Section 074113 specifies a 0.875-inch-high corrugated profile with 2.67-inch rib spacing and 29.3-inch panel coverage. May an equivalent 7/8-inch corrugated metal panel with a slightly different coverage width be proposed, subject to technical submittal and approval?

All substitution requests will be handled during the submittal process with the awardee.

RFI #33 - Drawing A1.01 identifies approximately 4,490 SF of roof area while the Schedule of Items indicates 49 squares. Please confirm the quantity to use for pricing/payment, and whether the bid quantity includes slopes, laps and waste.

Please see RFI #5.

RFI #34 - Please confirm the existing roof deck construction (plank decking versus plywood), including known deterioration and estimated quantity/location of damaged decking, if available.

Believed to all be plank decking. Please see RFI #3.

RFI #35 - Please clarify what quantity and type of damaged decking/sheathing replacement is included in the base bid, and how concealed deterioration discovered after tear-off beyond the identified scope will be authorized and compensated. Sections 000501, 070150, and 074113 appear to overlap.

Please see RFI #3 RFI #36 - Please clarify the scope division for overhang framing and structural repair. Section 000501 identifies Optional Bid Item #1 for overhang framing, round framing, and plank decking, while drawing A1.02 shows localized damage. Which repairs are included in the base bid and which are part of the option? Will any be performed under a separate contract?

Please see RFI #18 RFI #37 - Please confirm snow guards are to be priced as an optional bid item and identify the intended roof areas. Is there an approved arrangement, design snow load, or required quantity, or is the contractor to design the layout under Section 077253? Please also confirm an approved attachment method for exposed-fastener corrugated panels.

Please see RFI #6. Fasteners should be installed per manufacturers recommendation. Refer to specification 074113.

RFI #38 - Please identify the exact ridge sections and approximate linear footage requiring ventilation versus solid ridge cap. The general scope requires ridge vents, but the roof drawings do not clearly designate all ventilated locations.

1. Ventilated Ridge Scope:

· Continuous pre-finished metal ridge ventilation is required on all primary horizontal roof ridges over unconditioned attic space, in accordance with Section C (1.1.B.2.d) and Sheet A1.02/A2.01–A2.04 Keynotes.

· Approximate Linear Footage: Total ridge length is approximately 142 linear feet (approx. 70 LF along the main North–South ridge and approx. 72 LF total along the East and West cross-gable ridges).

2. Solid Ridge Cap & Termination Details:

· Ridge vents shall stop two (2) feet short of all exterior gable eaves/rakes, hips, and chimney intersections.

· At chimneys, hips, and within 24 inches of gable rakes, install a solid (non-vented) pre-finished ridge cap with closed-cell profile foam closures set in sealant per Sheet A4.01 (Detail 1) and Sheet A4.02 (Detail 1/2) to prevent wind-driven snow infiltration.

· Bidders shall calculate approximately 115 to 120 linear feet of active ventilated ridge and approximately 25 to 30 linear feet of solid flashing/closures.

RFI #39 - Section 076200 includes gutters and downspouts, but the drawings do not clearly define a replacement quantity. Please confirm whether existing gutters/downspouts are to remain, be removed and reinstalled, or be replaced, and identify locations/quantities.

No gutters or downspouts on this project RFI #40 - Section 074113, Paragraph 2.2, calls for high-temperature self-adhering underlayment tested at 220 degrees F and separately calls for a slip sheet; Paragraph 3.2 directs slip-sheet installation. Please confirm that 220 degrees F is the required test temperature rather than 240 degrees F and that a separate slip sheet is required over the full roof.

1. Underlayment Temperature Rating:

· In consideration of high solar heat absorption beneath dark metal roofing, self-adhering underlayment over the entire roof deck shall be High-Temperature (HT) rated, stable after testing at 240°F or higher per ASTM D1970 (meeting Section 076200 Paragraph 2.3.A.2 and Sheet A4.01 notes). Products such as Carlisle WIP 300HT, Grace Ice & Water Shield HT, or approved equal are compliant.

2. Slip Sheet Requirement:

· Yes, a separate slip sheet is mandatory over the entire roof surface.

· Install one layer of minimum 3-lb rosin-sized building paper (or manufacturer-approved synthetic slip sheet) directly over the self-adhering membrane prior to installing the 20-gauge corrugated metal panels, per Section 074113 Paragraph 3.2.B and Section 076200 Paragraph 2.3.B.

· Purpose: The slip sheet prevents the hot asphaltic underlayment from adhering to the underside of the metal panels, allowing free thermal movement and preventing panel friction from tearing the waterproof membrane under heavy snow loads.

RFI #41 - The site drawings identify Fremont County, Idaho, but Attachment 4 is Davis-Bacon General Decision ID20260100 covering Bonneville County. Please provide the correct applicable wage determination for Fremont County by solicitation amendment.

Please see RFI #3.

RFI #42 - Please confirm whether a roofing manufacturer material, finish, or weathertightness warranty of a specified duration is required in addition to the FAR 52.246-21 construction warranty and identify the required duration and coverage.

No warranty beyond what is listed in the FAR RFI #43 - Are existing asbestos, lead-based paint, or other hazardous-material surveys/reports available for the roof and exterior surfaces affected by the project? If not, please clarify the procedure for discovery, testing, and authorization of regulated-material abatement.

Please see RFI #21.

RFI #44 - Beyond the bid guarantee, performance/payment bonds and FAR 52.228-5 insurance provisions, please confirm any project-specific minimum insurance limits, special bond requirements, or subcontractor qualification/approval requirements that bidders should include.

Any required permits/licenses and insurance to perform the work as stated in the FAR.

RFI #45 - Taylor Metal Products is interested in submitting the attached substitution request to be an approved-equal manufacturer of the formed metal roof panels on the following project.

All substitution requests will be handled during the submittal process with the awardee.

RFI #46 – Are public works license required for prime and subcontractors?

Refer to the FAR for applicable requirements RFI #47 - Is there any historical preservation that we need to pay special attention to?

Big Falls Inn is listed on the National Register of Historic Places. Repairs should match the existing profiles.

RFI #48 - Will there be any restrictions on lifts, and what protective measures for the property will need to be implemented if they are allowed?

Refer to specifications section C. Lifts are allowed, but will need to protect the landscaping around the building (specification 070150).

RFI #49 - The Specifications (Section 074623, Part 2) call out 22 Gauge steel, but the Final Drawings (Keynotes 01) calls out 20 Gauge. Are the Drawings or the Specifications going to take precedence here?

Please see RFI #7.

RFI #50 - Specifications Section 076200, Part 2.6 is for hanging gutters, downspouts and splash pans, but I'm not seeing those in the drawings. Are those items included in the project?

Please see RFI #39.

RFI #51 - I'm not seeing any measurements for the chimney flashing in the drawings or specs. Can I get the measurements on that?

Plan and profile drawings are to scale RFI #52 - In Specification Section 074113, Part 2.1 shows MBCI as an approved manufacturer for the nominal thickness, panel coverage, and height requirements. MBCI does not make a 20ga panel. They do make a 24 ga and a special-order 22 ga panel. Would a 24- or 22 ga panel work for the roofing material?

All substitution requests will be handled during the submittal process with the awardee.

RFI #53 – Applicable Wage Determination Attachment 4 provides Davis-Bacon Wage Determination ID20260100 for Bonneville County, Idaho. However, Drawing G-01 identifies the project location as Fremont County, Idaho.

Please confirm whether the correct wage determination has been provided. If not, please issue the applicable determination.

Please see RFI #3.

RFI #54 – Roofing Quantities Attachment 1, Schedule of Items, identifies 49 roofing squares (4,900 square feet), while Drawing A1.01 identifies approximately 4,490 square feet.

Please confirm which quantity governs pricing and payment.

Please see RFI #5.

RFI #55 – Snow Guards Attachment 2, Specifications, identifies snow guards as optional work. However, Attachment 1 does not provide a separate pricing line for snow guards.

Please confirm whether snow guards are required and identify the appropriate bid item for pricing this work.

Please see RFI #6.

RFI #56 – Roofing Material Requirements Please confirm the required metal roofing panel gauge, thickness, coating, finish, and profile, including which specification governs if the roofing material descriptions differ.

Please see RFI #7.

RFI #57 – Concealed Wood and Structural Damage Please clarify how additional deteriorated roof decking, sheathing, or structural framing discovered after removal of the existing roofing will be authorized, measured, and compensated if the repairs exceed the work identified in the drawings and specifications.

Please see RFI #3 and #18 RFI #58– Mobilization Pricing Section 011900 addresses mobilization payments; however, Attachment 1 does not identify a separate mobilization pricing item.

Please confirm whether mobilization costs should be included in the base bid items and how mobilization payments will be administered.

Mobilization should be included in the existing line items shown in the specifications RFI #59 – Evaluation of Optional Work Please confirm whether the government will evaluate pricing based on the base bid alone or the combined total of the base bid and optional bid items.

Base and optional line items will be evaluated.

RFI #60 – Subcontractor Past Performance The solicitation requests three similar projects completed by the offering firm.

Please clarify whether relevant past-performance projects completed by a proposed major subcontractor may be submitted and considered under the Past Performance evaluation factor.

Yes RFI #61 – Roofing Removal Specification Section 070150 references an existing built-up asphalt roofing system, while the project scope and drawings describe removal and replacement of corrugated metal roofing.

Please confirm that the corrugated metal roofing system shown in the drawings governs the required removal and replacement work.

Confirmed drawings are correct RFI #62 – Limitations on Subcontracting The solicitation identifies this project as a Total Small Business Set-Aside, but Federal Acquisition Regulation clause 52.219-14 appears unchecked.

Please confirm the applicable limitations on subcontracting and whether a solicitation amendment will be issued to clarify this requirement.

FAR 52,29-14 does not apply to requirements anticipated not to exceed the simplified acquisition threshold. The prime must be a small business in Sam.gov under NAICS 238160.

RFI #63 – Roof Area / Design Quantity: Sheet A1.01 keynote states "TOTAL ROOF AREA = 4,490 SF +/-" and the SOI lists 49 SQ (DQ) for metal roofing and ice & water shield. The dimensioned roof plan (37'-10" x 69'-8" main roof, 34'-4" x 29'-10" east wing, 3'-6" x 29'-6" west wing) at the noted +/-12:12 pitch yields approximately 5,300 SF (53 SQ). Please confirm the design quantity for SOI items 061600.

Please see RFI #5.

RFI #64 – Metal Roof Panels and Ridge: (a) Section 074113 requires a "Weathering Steel" finish, while the drawing keynotes call for "pre-finished ... color to match" and Section 076200 requires PVDF trim with color selected by the COR. Please confirm the required finish for panels and trim. (b) Section 074113 lists 29.3" panel coverage; Sheet A4.02 Detail 3 shows 32". Please confirm the acceptable profile. (c) SOI 070150 removes existing ridge vents, but A4.01 Detail 1 shows a non-vented ridge. Please confirm no vented ridge is required.

Please see RFI #7 and #38.

RFI #65 – Snow Guards and Gutters: (a) The Scope of Contract lists snow guards as an Optional Bid Item and Section 077253 is included, but the SOI has no snow guard line. Are snow guards in this contract? (b) Section 076200 specifies gutters and downspouts "to match existing," but none are shown on the drawings. Are gutters and downspouts required?

Please see RFI #6 RFI #66 – Existing Roof System / Hazardous Materials: Section 070150, 1.5 describes an existing built-up asphalt roof with ballast and spray foam. Please confirm the existing Visitor Center roof is corrugated metal over felt and provide any hazardous material test results for the existing felts, mastics, or sealants.

Please see RFI #61 RFI #67 – Sheathing / Plank Decking Replacement: Sheathing is to be replaced "as necessary" and decking is included in the per-square price, but no quantity is stated. Please provide the existing plywood thickness and an estimated replacement quantity or establish a unit price for sheathing/decking replacement.

Please see RFI #18 RFI #68 – Overhang Scope: (a) SOI base item 061323 repairs sagging framing at the corner overhang (A1.02), but Sheet A2.04 keynote 07 states "FUTURE PROJECT / NOT IN CONTRACT – address sagging framing at balcony and corner overhang." Please confirm whether the corner overhang repair is in the base bid. (b) Section 000501 and keynote 07 require staining roof overhang surfaces and round framing, but the SOI lists only log walls (2,350 SF) and shake walls (557 SF). Please confirm which SOI item covers the overhang soffits and round framing.

a. The “future project” note is referring to the sagging porch. The corner repair is in contract.

b. Refer to specification 099300. Finishes for exposed framing are included in the price for the log walls RFI #69 – Wage Determination and Bid Guarantee: (a) General Decision ID20260100 lists Bonneville County; the project is in Fremont County. Please confirm the applicable wage determination. (b) The SF 1442 requires a bid guarantee but states no amount. Please confirm it is 20% of the bid price per FAR 28.101-2.

Please see RFI #3 for the answer to your wage determination question. The bid guarantee is 20% of the bid price.

RFI #70 - Site visit attendance and eligibility (Solicitation / Evaluation Factors) The Pre-Bid Site Visit Plan (Attachment 5) states the site visit was Tuesday, October 27, 2026, at 10:00 AM Mountain Time, meeting at the project site at Upper Mesa Falls. Tess Luck Inc. did not attend that site visit, and no subcontractor attended on our behalf. Attachment 5 does not state that attendance was mandatory, does not give registration instructions, and does not state a consequence for non-attendance. Please confirm in writing: (a) Was attendance at the October 27, 2026 site visit required to submit a quotation? (b) Is a bidder who did not attend still eligible to submit a quotation by December 1, 2026? (c) Is a second site visit planned, or will the attendance list or site visit notes be posted to SAM.gov? (d) Would attendance by a proposed subcontractor satisfy any attendance requirement?

Please see RFI #23. The site visit sign in sheet will be posted with amendment 0001.

RFI #71 - Quote submission method (Solicitation) Standard Form (SF) 1442, Box 13a, states sealed offers in original and 1 copy are due at the place in Item 8 by 1500 local time on December 1, 2026, and that sealed bids will be publicly opened at that time. The solicitation text, Quote Due Date section, states all quotes shall be emailed to PPS.proposals@usda.gov no later than December 1, 2026, 3:00 PM Mountain Time, as four separate Adobe PDF documents (signed SF1442, Schedule of Items, Technical Proposal, and scanned Bid Guarantee, Standard Form 24 with Power of Attorney). Please confirm: (a) Is email submission to PPS.proposals@usda.gov the correct and complete submission method, with no paper sealed bid required? (b) What is the exact subject line required? (c) How will receipt be confirmed?

Email submission of your quote to PPS.proposals@usda.gov is the only submission method allowed. No paper sealed bid is required. Please see Quote Due Date and page 16 of the SF1442 for the email subject line requirements.

RFI #72 - Period of performance and anticipated start date (Solicitation / Technical Data) The SAM.gov listing summary states an estimated period of performance of 120 calendar days after issuance of the Notice to Proceed (NTP), the written order to start work. SF1442, Box 11, the solicitation text, Period of Performance section, and the Specifications, Contract Time, all state 90 calendar days after the NTP, with work to commence within 10 calendar days after the NTP, including final cleanup, and an Anticipated Start Date of June 2027. Please confirm: (a) 90 calendar days is the correct period of performance. (b) June 2027 is the anticipated start date, and is there a firm NTP date or work window? (c) Are there any seasonal access, road closure, or blackout dates at Upper Mesa Falls that affect the June 2027 start or the 90-day schedule?

Please see RFI #22.

RFI #73 - Bid guarantee and performance and payment bonds (Solicitation) Please confirm: (a) The bid guarantee amount is 20 percent of the bid price, under Federal Acquisition Regulation (FAR) 52.228-1, submitted as a scanned copy of Standard Form 24 with Power of Attorney with the quotation. (b) Performance and payment bonds are required, to be furnished within 10 calendar days after award, under SF1442, Box 12a–12b, and FAR 52.228-15. What are the required bond amounts as a percent of the contract price? (c) Are bond premiums reimbursed as stated in Section 011900, Mobilization, after evidence of payment?

The performance and payment bond premium shall be 100% bid price.

RFI #74 - Insurance, permits, and hazardous materials (Technical Data) FAR 52.228-5, Insurance — Work on a Government Installation, is checked, and FAR 52.236-7, Permits and Responsibilities, is checked, but no insurance limits are stated in the documents provided. Section 017320 states hazardous materials may be present in the building to be demolished, and not to disturb them except under procedures in the contract documents. Please confirm: (a) What minimum insurance types and limits are required, and where are they stated? (b) Which permits must the contractor obtain, and which, if any, will the Forest Service obtain? (c) Is there a hazardous materials survey, asbestos, or lead-based paint report for the Visitor Center, and if so, please provide it; if none exists, please confirm none is known.

a. Please see RFI #44.

b. Please see RFI #21.

RFI #75 -Regarding white is the only 20 gauge corrugated roof panel Western States Metal Roofing produces. In 20 gauge, all other colors are special order and drives up the cost. Which color is being produced for the corrugated roof panel finish?

Natural galvanized steel color.

RFI #76 - What is the thickness and width of the T&G decking?

Unknown RFI #77 - What is the thickness of the plywood decking?

Unknown RFI#78 - A1.02 drawing indicates on Note 1 to repair framing valley support member. What is the valley support member size?

Possibly 3x6. Contractor to field verify RFI#79 - Is there enough attic space and access for shoring existing damaged support beam?

Attic is accessible. Unable to answer without more information on shoring type.

RFI #80 - Is there an address to the Visitor's Center and street name?

Forest Service Road 20295 aka Upper Mesa Falls Road RFI#81 - Please provide site visit sign-in sheet.

Please see RFI #23 RFI #82 – FAR 52.219-14, Limitations on Subcontracting, is not checked, but this is a total small business set-aside. Does the clause apply, and if so, what share of the work must the prime perform?

Please see RFI #62.

RFI #83 – The Schedule of Items has one Price column. Should offerors enter unit prices or extended totals for the DQ and AQ items?

Use updated SOI with unit price and total RFI #84 – Is the 20% bid guarantee based on the base bid alone or the base bid plus Option 1?

Base bid plus Options.

RFI #85 – With Upper Mesa Falls closed for road work into the winter, when is notice to proceed expected, and will the site be reachable for the 90-day performance period?

Anticipated start will be June 2027. NTP will not occur until the site is accessible.

RFI #86 – May past performance include projects completed by the proposed subcontractor?

Yes RFI #87 – Would the USDA consider an alternate color for roofing materials specified in the plan documents, depending on sourcing and availability?

No. Please see RFI #75 RFI #88 – Would USDA consider alternate gauges for roofing materials specified in the plan documents, depending on sourcing and availability?

Please see RFI #24