A0001_West Muddy Creek Bridges 4 and 5 Replacement.pdf
PDF 435 KB Posted
- Attached to
- WEST MUDDY CREEK #5 BRIDGE REPLACEMENT Federal contract opportunity
- Solicitation number
- 1240LT25R0046
- Issued by
- Department of Agriculture Forest Service
About this file
This document is an Amendment to a Solicitation for the West Muddy Creek Bridge #4 and Bridge #5 Replacement project located in Gunnison, Colorado on National Forest Road 261. The amendment, issued by the USDA Forest Service Intermountain Region, provides a site visit attendees list from September 3, 2025, and answers to contractor questions. Proposals are due by 11:00 a.m. Central Time on September 26, 2025, to be submitted via email to Janice King and Lucas Dahlman.
The project involves bridge replacement with a performance period from October 1, 2025, to October 31, 2026. Key details from the questions and answers include: no weight limitations exist between bridge sites and Highway 133, both bridges can be worked simultaneously, no field work is expected during winter months, and contractors should prepare submittals and equipment during winter for spring groundwork. The site conditions are noted to have water running year-round, with higher flows during spring runoff, and temporary bridge parts will be staged at the Muddy Creek Guard Station approximately 3.7 miles from bridge #5.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240LT25R0046_West Muddy Creek Bridges 4 and 5.pdf | ||
| Attachment 3_Muddy Creek Bridge 4 Plans.pdf | ||
| Attachment 1_SOW_west_muddy_bridges 5 and 4.pdf | ||
| Attachment 2_SOI_Muddy Creek Bridges 4 and 5 replacement.xlsx | XLSX spreadsheet | |
| Attachment 4_Muddy Creek Bridge 4 Specs.pdf | ||
| Attachment 5_Muddy Creek Bridge 5 Plans.pdf | ||
| Attachment 7_WD_CO20250012_01.03.2025.pdf | ||
| Attachment 6_Muddy Creek Bridge 5 Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
2. AMENDMENT/MODIFICATION NO.
6. ISSUED BY
3. EFFECTIVE DATE
09/10/2025
CODE 40LT
USDA-FS CSA INTERMOUNTAIN 8
324 25TH ST
OGDEN UT 84401-2310
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, state and ZIP Code)
1. CONTRACT ID CODE
4. REQUISITION/PURCHASE REQ. NO.
7. ADMINISTERED BY (If other than Item 6)
9A. AMENDMENT OF SOLICITATION NO.
1240LT25R0046
X
98. DATED (SEE ITEM 11)
08/26/2025
I
PAGE OF PAGES
1 I 4
5. PROJECT NO. (ff applicable)
CODE I
10A. MODIFICATION OF CONTRACT/ORDER NO.
108. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
l&IThe above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers Dis extended. mis not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment. and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
E. IMPORTANT:
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Contractor Dis not Dis required to sign this document and return ______ _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WEST MUDDY CREEK BRIDGE #4 and BRIDGE #5 REPLACEMENT in GUNNISON, COLORADO on NATIONAL
FOREST ROAD 261
POC's: Janice King, Contract Specialist, at: janice.king@usda.gov and Lucas Dahlman, Contracting Officer, at Lucas.dahlman@usda.gov
The purpose of Amendment One is as follows:
1) To provide the Site Visit Attendees List from the site visit held Sept. 3, 2025, and
2) To provide answers to contractor's questions. See the Summary of Changes attached to this Amendment.
3) All other terms and conditions remain the same.
Continued ...
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 1 0A, as heretofore changed, remains unchanged and in full force and effect .
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
158. CONTRACTOR/OFFEROR 15C. DATE SIGNED
(Signature of person authorized lo sign)
Previous edition unusable
LUCAS J. DAHLMAN
168. UNITED STATES OF AMERICA
(Signature of Contracting Offlcer)
16C. DATE SIGNED
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
MUDDY CREEK BRIDGE #4 and #5 Bridge Replacement
Summary of Changes
Solicitation#: 1240LT25R0046
AMENDMENT ONE (A0001)
Site Visit Attendees List and Questions and Answers
The purpose of Amendment One is as follows:
1) To provide the Site Visit Attendees List from the site visit held Sept. 3, 2025, and
2) To provide answers to contractor’s questions.
3) All other terms and conditions remain the same.
Proposals are due by 11:00 a.m. Central Time on September 26, 2025, and shall be submitted via email to the following: Janice King at janice.king@usda.gov and to Lucas Dahlman at lucas.dahlman@usda.gov by the due date and time.
Period of Performance: 10/01/2025 – 10/31/2026
Site Visit Attendees List – Sept. 3, 2025
QUESTIONS and ANSWERS
1. How much clearance will be allowed? As needed to accommodate the new bridge
2. What do we do with the trees?
4.
The contract award should be th st s the area is accessible by mid-April.
7. Reattach
8. Where will the temporary bridge parts be staged?
9.