This document is a Presolicitation Notice for the Dutch Joe Bridge Replacement project in the Bridger-Teton National Forest, Pinedale Ranger District, Sublette County, Wyoming. The project will remove and replace the existing 44-foot timber Dutch Joe Bridge with an 80-foot rolled girder bridge. It will also include the furnish and install of a temporary bridge to allow for road access during construction activities. The project must be completed between July 1st and October 14th due to wildlife migration corridor requirements. The anticipated contract value is between $500,000 and $1,000,000, with a period of performance of 480 days. This procurement is being solicited as a Small Business set-aside, with the intent to award a Firm-Fixed Price contract. The complete solicitation package will be made available through SAM.gov, and all prospective contractors must be registered in the System for Award Management (SAM) before award of contract.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Presolicitation Notice

1240LT24R0037

Dutch Joe Bridge Preplacement Bridger-Teton National Forest Pinedale Ranger District Pinedale, Wyoming Sublette County

DESCRIPTION OF WORK

The Bridger-Teton National Forest (BTNF) Dutch Joe Bridge Replacement project will remove and replace the existing Dutch Joe Bridge (370850-2.011). The existing bridge is 44-foot timber structure and will be replaced with an 80-foot rolled girder bridge. The project will also include furnish and install of a temporary bridge located downstream from existing to allow for temporary road access during construction activities. Project must start and be complete between July 1st and October 14th as it is part of a wildlife migration corridor.

Project Location The Bridger-Teton National Forest (BTNF), Dutch Joe Bridge project is in Sublette County, Wyoming within the Pinedale Ranger District. Map location is approximately 52 miles southeast of Pinedale, Wyoming via U.S Hwy 191 (12.0 miles), WY-353 (15.5 miles), big Sandy Elkhart Road (12 miles), Lander Cutoff Road (7.0 miles) and Big Sandy Opening Road (6.0 miles). The bridge is located on NFSR 370850, Big Sandy Road and crosses Dutch Joe Creek. Approximate Latitude and Longitude of the bridge are: 42.62684588, -109.255316.

Contract Time:

Period of Performance is 480 days.

The magnitude of proposed project is between $500,000 and $1,000,000.

Project drawings will be provided as attachments to the Request for Proposal (RFP).

The complete solicitation package will be attached and made available only through SAM.gov, https://sam.gov/content/home on or within 15 days of this notice. Anyone wishing to participate in this proposed procurement must obtain their copy from SAM.gov. Copies will not be mailed from the Contracting Office. All amendments will be posted on SAM.gov. Contractors will be solely responsible for obtaining amendments from this site to update files.

This requirement is being solicited as a Small Business set-aside, with the intent to award a Firm-Fixed Price contract. A single award will be made from the solicitation.

All prospective contractors must be registered in the System for Award Management (SAM) database at http:www.sam/gov/ before award of contract; failure to register in the SAM database may cause your firm to be ineligible for the award and removed from consideration.

NAICS: 237310, $45.0M