1240LT22R0083_Amend 02.pdf

PDF 271 KB Posted

Attached to
Fish Lake Complex-Phase 1-Doctor Creek Project Federal contract opportunity
Solicitation number
1240LT22R0083
Issued by
Department of Agriculture Forest Service

About this file

This document contains an amendment to a federal solicitation for the Fish Lake Complex-Phase 1-Doctor Creek Project. The amendment provides additional questions and answers regarding project requirements and extends the proposal due date to August 19, 2022 at 1:00 PM MDT. Key details include specifications for a precast concrete six-unit flush restroom building to match characteristics of an existing building by CXT Incorporated. Electrical specifications are also clarified regarding connecting power inside the new bathroom and reusing or extending existing conduit and feeders. Manhole rim elevations are specified to be flush with final grade. The solicitation is issued by the USDA Forest Service for construction services.

View the file

Other files for this federal contract opportunity

Other files attached to Fish Lake Complex-Phase 1-Doctor Creek Project, newest first.
File Type Posted
1240LT22R0083_Amend01.pdf PDF
Attachment 3 - Wage_Determination_Sevier_County.pdf PDF
Attachment 1 - Specifications.pdf PDF
RFP 1240LT22R0083 GAOA Fish Lake Complex.pdf PDF
Attachment 2 - Drawings and Maps.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT22R0083

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

IDAHO FALLS ID 83401

1405 HOLLIPARK DRIVE

USDA-FS CSA INTERMOUNTAIN 8

40LT

IDAHO FALLS ID 83401

1405 HOLLIPARK DRIVE

ATTN KELLIE SHAW

USDA-FS CSA INTERMOUNTAIN 8

GAOA08/10/20220002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/05/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to provide additional questions and answers that have been submitted in response to the solicitation.

The due date and time for receipt of proposals IS EXTENDED. All proposals in response to the solicitation shall be emailed to kellie.shaw@usda.gov no later than 1300 MDT, Friday, August 19, 2022. Proposals received after the stated due date and time will not be considered.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KELLIE SHAW

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation Number 1240LT22R0083 GAOA – Fish Lake Complex Phase 1 – Doctor Creek Amendment 02

Q. Is the requirement for Fluid Applied Elastomeric Roofing really required?

A. No, it is not required. Please delete Section B. of Part 2.10 and Section L. of Part 3.1 in SECTION 133401 - PRECAST CONCRETE FLUSH RESTROOM BUILDING

Q. Discrepancies exist regarding the specified outside textures and colors of the 6-Unit Flush Restroom Building. What are they supposed to be?

A.

Location Color Texture Roof: Java Brown Cedar Shake Upper Walls: Sand Beige Board and Batt Lower Walls Wainscot: Mountain Blend Napa Valley

Q. Is there a diagram for the 6-Unit Flush Restroom Building?

A. There are no detail drawings for the six-unit flush toilet. The toilet specified is a product.

Floor plan, layout, and other details are available from the manufacture.

Q. Can the same meter base be reused on the new toilet building?

A. No, nothing is to be reused that is existing.

Q. Can the RV pedestals be reused at the host units?

A. The existing pedestal equipment may be reused and shall be relocated, the contractor may also choose to replace at no additional cost to the government. However, the buck transformer 120/208 to 120/240 is to be removed as NEC has been clarified that RV pedestals are now allowed to be served with 120/208 three phase. See sheet E1, page 66.

Q. Are you aware of how the electrical connects to the bathroom, i.e., is there anything to connect inside the new bathroom?

A. A way to connect the electrical inside the bathroom shall be provided. How this is to be done will be determined by the building unit that is supplied.

(see next page)

Amendment 02

Q. SECTION 133401 - PRECAST CONCRETE FLUSH RESTROOM BUILDING, PART

2.1, Section C., Part 1, Subpart a. indicates “MATCH EXISTING FLUSH RESTROOM BUILDINGS ON SITE.” What are the specific characteristics of the existing flush restroom building on site that will need to matched?

A. The existing flush restroom building was provided by CXT Incorporated. The unique characteristics of this building, as provided by CXT, follow:

Each of the specific characteristics associated with list above, in a building provided by CXT, will need to be matched in the new Pre-cast 6-Unit Flush Concrete Restroom Building

Amendment 02

Q. Regarding the Host 2 Power Connection that is to be relocated: Can the existing wire and conduit feeding it be reused?

A. Reworking of the existing feeders to the host pedestal’s new location is intended as stated on sheet E1. If splicing is needed, or desired by the contractor to extend the feeders in lieu of rerouting, grade level handholes per NEC and specification 260533 are required at no additional cost to the government. Existing feeders are installed in conduit. Extensions and reworked portions shall be installed in conduit, see 260533.

Q. Do you have specific design manhole rim elevations associated with the Fish Lake Complex-Phase 1-Doctor Creek Project Plans?

A. The plans do not specifically call out a final rim elevation The manhole rim elevations (relative to finished grade) are called out on sheet W9. This detail calls for the rim top to be flush with finished grade whether it is outside of the roadway or in asphalt.

See also Section 221300-3.4 which states:

For the manholes that are installed outside of the roadway, either height is acceptable (flush or 3” above final grade).