1240LT22Q0131_Amend 01.pdf

PDF 293 KB Posted

Attached to
Reader/Basset/Highway 191 Boundary Fence Project on the Ashley National Forest
Solicitation number
1240LT22Q0131
Issued by

View the file

Other files

File Type Posted
J3_FENCE SPECS.pdf PDF
J2_DRAWINGS AND MAPS.pdf PDF
1240LT22Q0131_RFQ.pdf PDF
J1_Wage Determination.pdf PDF
J4_Experience Questionnaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT22Q0131

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

IDAHO FALLS ID 83401

1405 HOLLIPARK DRIVE

USDA-FS CSA INTERMOUNTAIN 8

08/17/20220001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/21/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Reader/Basset/Highway 191 Boundary Fence Project

Ashley National Forest

The purpose of this amendment is to provide the attendance roster from the site visit held on August 8, 2022 and questions and answers that have been submitted in response to the solicitation.

The due date and time for receipt of quotes IS EXTENDED. Quotes shall be submitted via email to kellie.shaw@usda.gov no later than 1300 MT, Wednesday, August 24, 2022.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KELLIE SHAW

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation 1240LT22Q0131 – Amendment 01 Reader/Basset/Highway 191 Boundary Fence Ashley National Forest

Attendees:

Steve Summers, Green River Construction Taylor Brochbank, Green River Construction Gary Brown, US Forest Service

Questions and Answers:

Highway 191:

Q. Can our subcontractor use a brush hog as they're clearing along this fence and along the enclosures?

A. Any method is acceptable as long as if follows the contract specs.

Q. Is the end point of this section of fence where it meets up with the next fence (the fence you mentioned in your previous email)?

A. Yes

Wildlife/Cattle Enclosures:

Q. Can an 8ft path be cleared on the outside perimeter of these fences? That way the heavy equipment could maneuver around the enclosure, to avoid driving through the enclosure area.

A. Yes

Solicitation 1240LT22Q0131 – Amendment 01 Reader/Basset/Highway 191 Boundary Fence Ashley National Forest

Q. Did you want a welded top rail on the 4ft cattle fence enclosure?

A. No welded top rail is specified.

Gartrell Spring Enclosure:

Q. Would you prefer that cedar posts/treated posts be used for this enclosure, as opposed to steel posts and wire netting? It's looking like the steel posts would be a cheaper option.

A. Cedar and treated posts are specified and required. Because it is a water source cattle and wildlife will push too much on a wire fence.

Cattail Pond:

Q. Could you send me Susan's contact information?

R. Permittee contact information will be provided to the successful offeror after contract award.

General Questions:

Q. As far as the deadline schedule for each project is concerned, does each project have to be started immediately after the previous project is completed? For example, say that the Highway 191 project is completed in 20 days, would the next project need to be started immediately? Or is it up to the contractor when they start the next project (so long as they didn't pass the 60-day requirement)? Our subcontractors were just wanting to know so they can schedule accordingly.

R. A notice to proceed will be issued prior to the start of work. Per F.2 of the solicitation, all base items must be completed within 60 calendar days from the start date identified on the notice to proceed. Option items, if awarded, must be completed within 30 calendar days from the start date identified on the notice to proceed.

Q. How soon do you anticipate that this contract will be awarded after the August 22nd deadline? Again, we just wanted to know for scheduling purposes.

R. Quotes must be valid for 30 days. The Government has up to the 30 days to make a contract award.