1240LT21Q0025_SF30.pdf
PDF 363 KB Posted
- Attached to
- Dutch John Bunkhouse/Office Remodel project on the Flaming Gorge Ranger District, Ashley National Forest
- Solicitation number
- 1240LT21Q0025
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LT21Q0025
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LT
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 8
05/28/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/03/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The solicitation is amended as follows:
*Amended Schedule of Items
*Change F.2 period of performance from 90 calendar days to 120 calendar days
*Amended project specifications
*Amended project drawings
The attendance Roster, questions and answers submitted in response to the solicitation and project photos are included as an attachment to the amendment.
The amendment extends the due date for receipt of proposals. All proposals received in response to the solicitation shall be submitted no later than 1:00pm MST Thursday, June 10, Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
KELLIE SHAW
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1240LT21Q0025/0001
2021. Instructions for preparing and submitting proposals can be found in L.2 of the solicitation.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation No: 1240LT21Q0025 AMENDMENT 01 Dutch John Bunkhouse/Office Remodel Project
Dutch John Bunkhouse and Office Remodel Project
1240LT21Q0025 – AMENDMENT 01
Changes to the solicitation:
1. F.2 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) is amended as follows:
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after start date identified on the notice to proceed. The time stated for completion shall include final cleanup of the premises.
2. The schedule of items is hereby amended. Offerors shall submit proposals on amended schedule of items. Offers received on initial schedule of items provided in the solicitation will be considered non-responsive to the solicitation. See following page for amended schedule of items.
3. The project drawings and specifications have been amended. See amended project drawings and specifications included as an attachment to this amendment.
4. Project photos are included as an attachment to this amendment.
5. The due date for receipt of proposals has been extended from June 3, 2021 to June 10, 2021.
Pre-proposal Site Visit Information:
• Pre-Bid Site Visit Attendees include:
o Lance Valentine, Ashley Forest, lance.valentine@usda.gov, 435-790-5988 o Kerry Wilson, City Seamless LLC, kerry@cityseamless.com, 435-256-1233 o Dan Holbrook, Cinnamon Creek Construction, dan@cinnamoncreekconstruction.com, 801-837-o Chase Sawyer, Guardian Const, chase@sawyerrestor.com, 307-677-6867 o Benjamin Prieto, Global Star LLC, biogreen04@gmail.com, 208-919-9572 o Cameron Vasil, Global Star LLC, kuconsultingid@gmail.com, 208-919-9572 o Travis Boren, Guardian Const, travis@sawyerrestore.com, 307-677-7278 o Russ Tonks, Guardian Const, russell@guardiangc.net, 801-349-0639
Questions and Answers:
1. Can the tress adjacent to the building be trimmed to provide 6 ft. of clearance between the trees and the building?
a. Trees adjacent to the Building will be trimmed back by the Forest Service a distance of 2-3 feet from the Building prior to Notice to Proceed. Tree trimming is not required of Contractor.
2. Are the window blinds to be removed and disposed of?
a. See revised project and specifications included with this amendment.
3. Will the exterior stairway need to be repaired, replaced, repainted as part of the bid?
a. See revised project and specifications included with this amendment.
mailto:lance.valentine@usda.gov mailto:kerry@cityseamless.com mailto:dan@cinnamoncreekconstruction.com mailto:chase@sawyerrestor.com mailto:biogreen04@gmail.com mailto:kuconsultingid@gmail.com mailto:travis@sawyerrestore.com mailto:russell@guardiangc.net
Solicitation No: 1240LT21Q0025 AMENDMENT 01 Dutch John Bunkhouse/Office Remodel Project
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
BASE ITEMS
Item Supplies/Services Qty Method of Measure
Unit of Issue
Unit Price Total Price
011900 Mobilization 1 LSQ LS $ $ 017320 Selective Demolition 1 LSQ LS $ $ 074646 Fiber, Cement Exterior
Siding, Trim, Soffit and Fascia
1 LSQ LS $ $
085413-1 Fiberglass Windows – 3’ x 4’, Trim and Repair
46 AQ EA $ $
085413-2 Fiberglass Windows – 3’ x 2’-11, Trim and Repair
23 AQ EA $ $
085413-3 Fiberglass Windows – 3’ x 2’-11 Obscure, Trim and Repair
2 AQ EA $ $
085413-4 Fiberglass Windows – 4’ x 1’-10 ½” Obscure, Trim and Repair
4 AQ EA $ $
099000 Exterior Siding Painting 1 LSQ LS $ $ 260000 Reconfigure Exterior
Electrical
1 LSQ LS $ $
BASE ITEMS TOTAL $
OPTIONAL ITEMS
Item Supplies/Services Qty Method of Measure
Unit of Issue
Unit Price Total Price
096816 Move Furniture, Install Sheet Carpeting and Resilient Accessories
1 LSQ LS $ $
OPTIONAL ITEM TOTAL $
BASE ITEMS TOTAL $
OPTIONAL ITEM TOTAL $
BASE AND OPTIONAL ITEMS TOTAL $
| 1240LT21Q0025_SF30.pdf |
| AMENDMENT_01.pdf |
| PART I—THE SCHEDULE |
| SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS |
| B.1 SCHEDULE OF ITEMS |