1240LS26Q0056 UWC SO and SLRD Snow Removal_Attachment 3_Schedule of Items.pdf
PDF 159 KB Posted
- Attached to
- Uinta-Wasatch-Cache National Forest Supervisor's Office and Salt Lake Ranger District Snow Removal
- Solicitation number
- 1240LS26Q0056
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a pricing schedule (Attachment 3) for federal contract 1240LS26Q0056 for snow removal services at the Uinta-Wasatch-Cache National Forest (UWC NF) Supervisor's Office and Salt Lake Ranger District. The schedule requires quoters to provide unit prices and total prices for snow removal services across a five-year contract period consisting of one base year (September 1, 2026 – August 31, 2027) and four option years.
The contract encompasses two service locations with identical service types: the Supervisor's Office and Salt Lake Ranger District. For each location and period, quoters must provide pricing for four service line items: parking lot plowing, walkway shoveling, salting/sanding for parking lots, and salting/sanding for walkways. All pricing is requested on an "each" (Ea.) unit basis. The document requires quoters to complete company information at the conclusion, including company name, UEI number from SAM.gov, company representative details, phone number, email address, and signature with date. Quoters must calculate and provide both unit prices and total prices for each line item, with subtotals for each contract year and grand totals for the entire base year through option year 4 period for each location.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1240LS26Q0056– UWC NF Supervisor’s Office and Salt Lake Ranger District Snow Removal Attachment 3 – Schedule of Items.
Item Services Unit Unit Price Total Price
0001a Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Supervisor’s Office – Parking Lot Plowing
Ea. $ $
0001b Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Supervisor’s Office – Walkway Shoveling
Ea. $ $
0001c Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Supervisor’s Office – Salting/Sanding–Parking Lot
Ea. $ $
0001d Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Supervisor’s Office –Salting/Sanding - Walkway
Ea. $ $
Total Quote: $
1001a Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Supervisor’s Office – Parking Lot Plowing
Ea. $ $
1001b Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Supervisor’s Office – Walkway Shoveling
Ea. $ $
1001c Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Supervisor’s Office – Salting/Sanding–Parking Lot
Ea. $ $
1001d Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Supervisor’s Office – Salting /Sanding - Walkway
2001a Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Supervisor’s Office – Parking Lot Plowing
Ea. $ $
2001b Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Supervisor’s Office – Walkway Shoveling
Ea. $ $
2001c Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Supervisor’s Office – Salting/Sanding–Parking Lot
Ea. $ $
2001d Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Supervisor’s Office – Salting/Sanding - Walkway
3001a Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Supervisor’s Office - Parking Lot Plowing
Ea. $ $
3001b Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Supervisor’s Office – Walkway Shoveling
Ea. $ $
3001c Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Supervisor’s Office – Salting/Sanding–Parking Lot
Ea. $ $
3001d Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Supervisor’s Office – Salting/Sanding - Walkway
Parking Lot Plowing
Item Services Unit of
Issue
Unit Price Total Price
4001a Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Supervisor’s Office – Snow Plowing
Ea. $ $
4001b Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Supervisor’s Office – Walkway Shoveling
Ea. $ $
4001c Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Supervisor’s Office – Salting/Sanding – Parking Lot
Ea. $ $
4001d Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Supervisor’s Office – Salting/Sanding - Walkway
Total Quote, Supervisor’s Office BASE YEAR – OPTION YEAR 4 $
Unit Price Total Price
0002a Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Salt Lake RD – Parking Lot Plowing
Ea. $ $
0002b Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Salt Lake RD – Walkway Shoveling
Ea. $ $
0002c Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Salt Lake RD – Salting/Sanding - Parking Lot
Ea. $ $
0002d Base Year – September 1, 2026 – August 31, 2027 Snow
Removal Salt Lake RD – Salting/Sanding - Walkway
Item Services Unit of
Issue
Unit Price Total Price
1002a. Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Salt Lake RD – Parking Lot Plowing
Ea. $ $
1002b. Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Salt Lake RD – Walkway Shoveling
Ea. $ $
1002c. Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Salt Lake RD – Salting/Sanding – Parking Lot
Ea. $ $
1002d Option Year 1 – September 1, 2027 – August 31, 2028 Snow
Removal Salt Lake RD – Salting/Sanding - Walkway
2002a. Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Salt Lake RD – Parking Lot Plowing
Ea. $ $
2002b. Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Salt Lake RD – Walkway Shoveling
Ea. $ $
2002c. Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Salt Lake RD – Salting/Sanding – Parking Lot
Ea. $ $
2002d. Option Year 2 – September 1, 2028 – August 31, 2029 Snow
Removal Salt Lake RD – Salting/Sanding - Walkway
3002a. Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Salt Lake RD – Parking Lot Plowing
Ea. $ $
3002b. Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Salt Lake RD – Walkway Shoveling
Ea. $ $
3002c. Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Salt Lake RD – Salting/Sanding – Parking Lot
Ea. $ $
3002d. Option Year 3 – September 1, 2029 – August 31, 2030 Snow
Removal Salt Lake RD – Salting/Sanding - Walkway
Total Quote:
Unit Price Total Price
4002a. Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Salt Lake RD – Parking Lot Plowing
Ea. $ $
4002b. Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Salt Lake RD – Walkway Shoveling
Ea. $ $
4002c. Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Salt Lake RD –Salting/Sanding – Parking Lot
Ea. $ $
4002d. Option Year 4 – September 1, 2030 – August 31, 2031 Snow
Removal Salt Lake RD –Salting/Sanding - Walkway
Total Quote, Salt Lake RD BASE YEAR – OPTION YEAR 4 $
Quoter’s Company Information
Company Name (Please Print):
UEI NUMBER from SAM.gov
Printed Name of Company Representative:
Signature of Company Representative:
Phone Number:
Email Address:
Date:
File details come from the government source that posted it. Updated .