RaineySOW updated.pdf

PDF 232 KB Posted

Attached to
Laminated Wood Bridge Kits Federal contract opportunity
Solicitation number
1240LS24Q0010
Issued by
Department of Agriculture Forest Service

About this file

This statement of work details requirements for a federal contract to purchase prefabricated glulam timber trail bridges. The USDA Forest Service seeks to procure five bridges for the Rainey Creek Trail Bridge project, including a 50-foot bridge with an 82-inch clear width and three bridges between 40-45 feet with an 81 1/8-inch clear width. The bridges must be delivered unassembled with all specified materials by June 14, 2024 to the Rainey Creek Trailhead in Idaho to allow installation during the 2024 field season. Bridges will be used by stock and must meet design specifications provided in the standard trail plans. Delivery of prefabricated and labeled bridge components packaged for assembly is required along with hardware, timber cut to length with bored holes, and structural materials according to the drawings.

View the file

Other files for this federal contract opportunity

Other files attached to Laminated Wood Bridge Kits, newest first.
File Type Posted
RaineyGLULAM_FINAL_REV1.pdf PDF
Sol_1240LS24Q0010_Amd_0001.pdf PDF
Sol_1240LS24Q0010.pdf PDF
RaineyCreekSOI.pdf PDF
RaineyGLULAM_drw_spec.pdf PDF
RaineySOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Rainey Creek Trail Bridges

Caribou-Targhee National Forest

General Informa�on This requisition seeks the purchase of five prefabricated glulam timber trail bridges for the Rainey Creek Trail Bridge project, to be delivered in time for Forest crews to install them during the 2024 field season.

Specifica�ons Details of the bridges are found on the Rainey Creek Trail bridge Standard Trail Plans included with this requisition. As indicated on the plans, these bridges will be used by stock (horses and pack animals).

The 50-foot bridge shall have a clear width of 82 ¾ inches. The 40-foot and 45-foot bridges shall have a clear width of 81 1/8 inches. All bridge shall have 4 stringers (main support beams). Each prefabricated bridge shall be delivered unassembled with all materials required for assembly as specified on the plans. This includes the bridge deck, rails, superstructure (stringers, diaphragms, etc.), substructure (sills, gabion baskets, backwall, etc.), and hardware. These materials shall be packaged and clearly labeled for each bridge. All timber shall be cut to length, holes bored, and treated. All hardware and structural steel shall be supplied in accordance with the plans.

Drawing sheet 2 depicts the standard glue-laminated diaphragm. Drawing sheet 3 provides an alternate steel diaphragm. Either diaphragm is acceptable.

Schedule To ensure delivery before the funding expires and to allow sufficient time to install the bridges during the 2024 field season the Forest requests delivery by June 14th, 2024.

Delivery Delivery location is the Rainey Creek Trailhead (43.4727, -111.2408) located near Swann Valley Idaho.

The Forest can perform the off-load if the supplier provides at least a 7-day notice prior to delivery. The gravel road and parking lot are accessible to semi-trucks.

Funding The Forest has funds committed to the purchase of these glue-laminated timber trail bridges.

General Information
Specifications
Schedule
Delivery
Funding