This document is an amendment to Solicitation 1240LR24Q0050 for the Trail Maintenance French Creek and Bear Pete Ridge project near McCall, Idaho on the Payette National Forest, McCall Ranger District. The amendment provides answers to questions received and extends the due date for quotes to June 14, 2024 at 5:00 PM EST. The contract is a Total Small Business Set-Aside. Key details include:
The purpose is to provide trail maintenance including clearing logs, brushing, and tread restoration on approximately 32 miles of trail. A mini excavator may be used, but hand work is expected to be feasible. There are no bridges or structures to be built. Camping is allowed at the trailheads. The Contracting Officer is Elida C. Monroe. Quotes must be submitted via email to Brenda Simmons by the due date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LR24Q0050
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LR
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 6
GAOA05/20/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/20/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of amendment 0001 to solicitation 1240LR24Q0050, is to provide answers to questions received.
The due date has been extended to June 14, 2024, @ 5:00 PM EST.
All quotes are to be sent via email to Brenda Simmons at brenda.simmons@usda.gov by the due date and time. Late quotes may not be accepted.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
ELIDA C. MONROE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
QUESTIONS AND ANSWERS
1. Could you provide a name and number of a McCall district employee who is familiar with the area to answer questions?
Answer: Savannah Steele, 208-634-0415 is the recreation specialist for the McCall District and most familiar with the trail conditions. Paul McCloskey 928-814-2771 will be the COR for the project
2. What are current trail conditions?
Answer: Trail has been logged out each summer for the past several years. There is minor tread restoration work needed but no major slumps or slides are expected.
3. Can we camp in the trailheads?
Answer: Camping is allowed at the trailheads. If contractor is staying more than 14 consecutive days a camping permit will be issued.
4. Is it reasonable to expect trail maintenance to be performed to spec - slough and berm removal, ditch cleaning, waterbar reconstruction- to be done on all 32 miles in one season?
Answer: Yes, with a proper crew size all of the work could be completed in one season.
5. Is it reasonable to take a mini excavator all the way through?
Answer: There are a few rocky sections on the Bear Pete Trail that will be difficult to get a mini excavator through. It is anticipated that the tread restoration could be completed by hand.
6. Can a moderately skilled rider take a motorcycle all the way through both trails?
Answer: Yes
7. How likely would a proposal be entertained that called for some portion of the work to be done next summer?
Answer: With the delayed advertisement we would consider some work occurring in 2025
8. Can a mini excavator safely ford the creek on the northern access of trail 116?
Answer: See general notes on Sheet 3, Trail 116 does not tie into the road system. It was put on the forest map but work the section of trail in the state and private land was never completed.
9. Does the Payette National Forest - Trail Maintenance French Creek and Bear Pete Ridge have any pedestrian trail bridges?
Answer: There are no trail bridges on those routes. This is just a trail maintenance project.
10. What type of equipment is required for this project?
Answer: It is up to the contractor to determine what equipment they will use. Work is expected to be feasible with hand tools. Is it all hand work or mini excavator or both?
If a mini excavator is used it should fit within the trail tread to prevent damage to other resources.
11. Is there a reroute planned and building new trail?
Answer: This is just a trail maintenance project. The reroute portion of this project was completed in an earlier phase of work.
12. Any type of structure to build like bridges?
Answer: There are no structures to be built. Only clearing logs, brushing, and tread restoration.