About this file
This performance work statement outlines requirements for extensive stand examination data collection services within the Rio Grande National Forest. The contractor will be required to collect Common Stand Exam and R2 FSVeg Spatial Polygon Vegetation data in 155 stands comprising 713 plots, with optional data collection available for an additional 10 stands and 33 plots. Data collection must be performed using approved electronic software and paper forms, with all data submitted in electronic format. Required data includes plot center identification, tree measurements, vegetation composition, and other stand assessment details. The contractor must accurately locate and survey all plots using GPS and mapping provided by the government. This is a firm-fixed price contract to be awarded based on evaluation of price and other factors.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Signed SF30 Amend 1.pdf | ||
| 1240LQ23Q0095 Amendment 0001 CSE.pdf | ||
| 1240LQ23Q0095 Attachment 4 Exhibit 13_DivideGeneralMap.pdf | ||
| 1240LQ23Q0095 Attachment 5 Exhibit 14 ConejosPeakGeneralMap.pdf | ||
| 1240LQ23Q0095Attachment 8 FS-Schedule of Items.xlsx | XLSX spreadsheet | |
| 1240LQ23Q0095 Attachment 9 - Experience Questionnaire.pdf | ||
| 1240LQ23Q0095 1449.pdf | ||
| 1240LQ23Q0095 CSE NRE_Commercial Services_Combined SS_RFQ_06022023 (1) (002) IW.pdf | ||
| 1240LQ23Q0095 Attachment 3 Exhibit 12 VicinityMap.pdf | ||
| 1240LQ23Q0095 Attachment 6 Exhibit 15 R2SuppFSVegSpatialUserGuide 20201203.docx | DOCX document | |
| 1240LQ23Q0095 Attachment 7 Wage Determination 2015-5433 Rev23.txt | TXT text file | |
| 1240LQ23Q0095 Attachment 2 2023 CSE QASP RGNF.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Performance Work Statement 08/23/2023
Contents
| Project Title | 3 |
| General Information | 3 |
| 1.0 Background and Purpose | 3 |
| 2.0 Definitions | 3 |
| Contractor Requirements | 4 |
| 3.0 Technical Requirements / Tasks | 4 |
| 4.0 Safety | 15 |
| 5.0 Protection Measures | 15 |
| 6.0 Deliverable / Schedule | 17 |
| 7.0 Government Furnished | 18 |
| 8.0 Travel | 20 |
| 9.0 Contractor’s Key Personnel | 20 |
| 10.0 Security Requirements | 20 |
| 11.0 Data Rights | 20 |
| 12.0 Section 508 - Electronic and Information Technology Standards | 20 |
| 13.0 Performance Requirement Measures | 20 |
| Attachments | 22 |
| Exhibit 1 –SAMPLE DESIGN SPECIFICATIONS –Pay Items 3.1 & 3.3) | 22 |
| Exhibit 2- Setting Form | 23 |
| Exhibit 3- Sample Design Form | 24 |
| Exhibit 4- Plot Data Form | 25 |
| Exhibit 5- Tree Data Form | 26 |
| Exhibit 6 -- Downed Woody Material Form: Brown’s Transect or Fixed-Area Piece Count | 28 |
| Exhibit 7--Vegetation Composition Forms 1 & 2, Cover By Lifeform (Live only) | 29 |
| Exhibit 8 -- Vegetation Composition Form 4, Ground Surface Cover | 32 |
| Exhibit 9 -- R2 FSVEG SPATIAL POLYGON VEGETATION ATTRIBUTES FORM | 33 |
| Exhibit 10 -- List of Acceptable Site Tree Species | 34 |
| Exhibit 11 -- List of Species of Concern that need to be recorded | 34 |
| Exhibits 12-14 – Maps | 34 |
| Exhibit 15 – R2 Supplement to the FSVeg Spatial User Guide | 34 |
Project Title 2023 Rio Grande National Forest CSE Contract
General Information
1.0 Background and Purpose
This Contract is for extensive stand examination data collection activities within the Rio Grande National Forest. Information shall be collected as outlined in the Government provided Common Stand Exam Field Guide (Region 2) and Region-specific Appendices, unless specifically modified by the contents of Contract. Region 2 FSVeg Spatial Polygon Vegetation walk-through surveys will also be performed as outlined in the R2 Supplement to the FSVeg Spatial User Guide. Units consist primarily of previously harvested spruce-fir stands on slopes that are generally 0-35%. Average stand size is approximately 33 acres, with a range of 1-262 acres. See the following table for a description of access from national forest system roads (NFSR).
Table 1. Access to stands within the Contract.
| Contract Item |
| Within ¼ mile of NFSR |
| Within ¾ mile of NFSR |
| Total Number |
| Plots (base item) |
| 670 |
| 43 |
| 713 |
| Stands (base item) |
| 161 |
| 5 |
| 156 |
Optional Items
| Plots (optional item) |
| 33 |
| -- |
| 33 |
| Stands (optional item) |
| 10 |
| -- |
| 10 |
2.0 Definitions
Acceptable Quality Level (AQL): The allowable leeway or variance from a standard before the Government will reject the specific service. As long as the percent of defective performance does not exceed the AQL, the service will not be rejected by the Government. The Contractor, however, must re-perform the defective service when possible. See the Quality Assurance Surveillance Plan for AQL’s related to this Contract.
Borderline Tree: A tree that cannot be easily identified as being located inside or outside of a sample variable plot when measured with a wedge prism or angle gauge. When a borderline tree is encountered, the limiting distance of that tree must be calculated to determine the in/out status.
CLIN: Contract Line Item.
Contracting Officer (CO): Individual with authority to bind the Government with their signature on the contract.
Contracting Officer Representative (COR): Individual(s) designated to act on the behalf of the CO within the delegation given them in writing.
CSE – Common Stand Exam.
Diameter at Breast Height (DBH): The outside bark diameter at 4.5 feet above the forest floor on the uphill side of a tree. See the Common Stand Exam Field Guide for special situations where measurement methods may differ.
Federal/National Holiday: New Year’s Day, Martin Luther King Jr. Day, Presidents’ Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
GPS: Global Positioning Satellite.
Limiting Distance: The maximum distance that the center of a tree can be from plot center and still be within the variable plot. Limiting distance is a function of the actual DBH of the tree as measured by a diameter tape and the Plot Radius Factor (PRF).
NFSR: National Forest System Road.
Period of performance (also PoP, Performance Period, or Contract Time): All calendar days allowed for completion of the contract work. Includes all days of the week including weekends and holidays.
Quality Assurance: Those actions taken by the Government to check goods or services to determine that they meet the requirements found in the Contract and all attachments.
Quality Assurance Surveillance Plan (QASP): An organized written document used for quality assurance surveillance. The document contains information about how the Government will assess performance, checklists, and may contain decision tables.
Quality Control: Those actions taken by the Contractor to control the production of goods or services so that they will meet the requirements of the Contract and all attachments. Refer to FAR clause(s) 52.246-4—Inspection of Services—Fixed Price.
Quality Control Plan (QCP): Contractor’s plan for self-monitoring work prior to the Government inspection and acceptance.
Random Sampling: A method of looking at a few individual items in a lot to determine the quality of that lot against a standard.
(Acceptable) Service: A job performed to the standard and within the AQL. The Contractor must do the specific job, and meet the standard, and meet the AQL before one can say that performance has been acceptable and that the Contractor should be paid.
Standard: An acknowledged measure of comparison.
UTM: Universal Transverse Mercator. This is a coordinate system that divides the world into 60 north-south zones.
Weekend: Saturday and Sunday.
Contractor Requirements
3.0 Technical Requirements / Tasks
This Contract is for post-treatment extensive stand examination data collection activities with the Rio Grande National Forest. Work shall be performed in an orderly and workmanlike manner and data submitted only on fully completed stands.
Table 2. Schedule of Items
PAY ITEM
DESCRIPTION
UNIT OF ISSUE
QUANTITY
3.1
| Stand Exam Data Collection Services |
| EA |
| 713 |
(in 155 stands)
| 3.2 |
| R2 FSVeg Spatial Polygon Vegetation Form |
| EA |
| 155 |
(in 155 stands)
Optional Items
| 3.3 |
| Stand Exam Data Collection Services- Optional Plots |
| EA |
| 33 |
(in 10 stands)
| 3.4 |
| R2 FSVeg Spatial Polygon Vegetation Form- Optional Settings |
| EA |
| 10 |
(in 10 stands)
Optional Items: Bid options will be awarded at the discretion of the Government, based on continuing need, price reasonableness, and availability of funding. Proposal Evaluation Criteria: Contract award will include evaluation of factors other than price, plus Contract total value. See the Proposal Evaluation Criteria included with this Contract. Contract total value includes base and optional items combined.
3.1 Locating Plots
a. Plot Location Determination: The Universal Transverse Mercator (UTM) of the plot locations within each stand shall be provided for each setting, as an electronic shapefile or KML/KMZ file. The Contractor shall use a global position system (GPS) to locate the plots on the ground with datum and waypoint information provided by the government. A recreation grade GPS (e.g. Garmin, Magellan, etc.) is sufficient.
b. Sample plot locations to be measured within each stand will be marked on one of the topographical maps provided. Plot numbers have been pre-assigned for each plot in each stand.
c. Locating Plot Center: Upon arrival at the specified coordinates, the Contractor shall check the map to confirm that he/she is at the correct sample plot location. Installing plots in the wrong stand shall result in rejection of data.
d. Non-functioning GPS: The Contractor may elect to use traditional methods of plot location if the GPS is unable to acquire the necessary resolution to execute the traverse from waypoint data. In either case, the Contractor must navigate to the location provided on the topographic map.
3.2 Plot Center Identification/Flagging
The Contractor shall identify sample plot centers with a marker that shall be a wire flag, wooden stake, or other marker as agreed upon at the prework conference. Sample plot center markers shall be firmly driven into the ground.
Upon inspection, the center point of the marker where it intersects the ground shall be used as plot center. If the marker is not a wire flag, flagging shall be tied to the marker so that it is visible above the plot center. The HUC6 watershed alias, stand and plot numbers shall be written legibly on the flagging or wire flag using a waterproof marker. If Brown’s transects are conducted, the azimuth of transect shall be written as well.
3.3 Survey Technique
Plots shall be located using waypoint navigation with a GPS unit. During the initial establishment of the plot, the plot center monument may vary +/- 30 feet of the true plot location listed. Recurring errors in the location of sample plots greater than the acceptable error shall make the stand survey unsatisfactory; relocation of sample plots and remeasurement shall be required.
3.4 Recording Requirements
The data fields to be collected and recorded are enumerated in the Date Collection Specifications paragraphs of this section. The following methods shall be used for electronic data collection:
a. Common Stand Exam using the Government-provided ExamsPDR program. The ExamsPDR program runs on several types of PDR style computers with the Windows-based mobile operating system.
b. Common Stand Exam using the Government-provided ExamsPC program. The ExamsPC data entry program runs on computers with the Windows 7/10 operating systems. This may require data to be recorded on paper forms in the field and then entered into the ExamsPC program at a later time.
c. Government-provided setting level R2 FSVeg Field Data Collection/Verification Form in the VegPy or Survey123 electronic format.
d. Data recorded on paper forms shall NOT be accepted as the final data submission.
e. The Contractor is responsible for providing the computer hardware necessary for running the software programs.
3.5 Data Collection Specifications
This section describes the data collection forms and the fields on each form to be completed. Detailed information and lists of valid codes for each of the following data forms are found in the Common Stand Exam (CSE) Field Guide (Region 2) and Appendices (See Government Furnished Property). If the following Contract specifications differ from the provided Common Stand Exam Field Guide and Appendices listed below, the following Contract specifications shall have precedent.
a. Setting Form (CSE) A setting is normally a stand in which the stand exam is being done. Following is a list of data fields required for each setting. Project name (Field 1) will be supplied by the Government. Contractor shall be responsible for collecting and filling out the Setting Form for all data items that are set to “YES” in the Required column:
Table 3. CSE Setting Form Requirements
| FIELD NUMBER |
| FIELD DESCRIPTION |
| REQUIRED |
| DATA |
SOURCE
COMMENTS
| 1 |
| Project Name |
| Yes |
| Government |
| ‘CSE 2023’ |
| 2 |
| Region |
| Yes |
| Government |
| Always ‘02’ |
| 3 |
| Proclaimed Forest |
| Yes |
| Government |
| Always ‘09’ |
| 4 |
| District |
| Yes |
| Government |
| Conejos Peak RD = ‘03’ |
Divide RD = ‘04’ Saguache RD = ‘07’
| 5 |
| Location/Watershed Alias |
| Yes |
| Survey Stand List |
| Provided at the prework conference. |
| 6 |
| Stand |
| Yes |
| Survey Stand List |
| Provided at the prework conference. |
| 7 |
| Owner |
| Yes |
Always ‘USFS’
| 8 |
| State |
| Yes |
Always ‘CO’
| 9 |
| County |
| Yes |
Conejos County = '21’ Hinsdale = ‘53’ Mineral = ‘79’ Rio Grande = ‘105’
| 10 |
| Admin Forest |
| Yes |
Always ‘09’
| 11 |
| Admin Region |
| Yes |
Always ‘02’
| 12 |
| Date |
| Yes |
| Contractor |
| Format is MM/DD/YYYY |
| 13 |
| Photo ID |
| N/A |
| 14 |
| Exam Level |
| Yes |
| Government |
| Always ‘Extensive,’ Code 2211. Description: Extensive Tree; Extensive Veg; Piece Count, Ground Surface Cover. See Table 6. |
| 15 |
| Exam Purpose |
| Yes |
| Government |
| Always ‘SE’ |
| 16 |
| Stratum |
| N/A |
| 17 |
| Existing Vegetation |
| YES |
| Contractor |
| SAF. See CSE Field Guide Appendix E |
| 18 |
| Potential Veg Ref |
| No |
| 19 |
| Potential Vegetation |
| No |
| 20 |
| Structure |
| Yes |
| Contractor |
| 21 |
| Capable Grow Area |
| Yes |
| Contractor |
| 22 |
| Fuel Model |
| No |
| 23 |
| Elevation |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 24 |
| Aspect |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 25 |
| Slope |
| Yes |
| Contractor |
| 26 |
| Slope Position |
| Yes |
| Contractor |
| 27 |
| Acres |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 28 |
| Radial Growth Interval |
| Yes |
| Contractor |
| Always “10” |
| 29 |
| Radial Growth Interval 2 |
| No |
| 30 |
| Height Growth Interval |
| Yes |
| Contractor |
| Always “5” |
| 32 |
| Precision Protocol |
| Yes |
| Contractor |
| Always “CSE” |
| 33 |
| Examiner |
| Yes |
| Contractor |
| First and Last Name |
| 34 |
| Remarks |
| Yes |
| Contractor |
| 35 |
| Damage Category |
| Yes |
| Contractor |
| 36 |
| Damage Agent |
| Yes |
| Contractor |
| 37 |
| Damage Severity |
| No |
| 38 |
| Species of Management Interest |
| Yes |
| Contractor |
| See Exhibit 11 |
| 39 |
| User Code |
| No |
All Setting Form fields, whether required by Contract or not, are included on the setting form provided in the exhibits, as identified in the Attachments section. Fields not specifically required by Contract are to be skipped on the setting form.
b. Sample Design Form (CSE) Large Tree (live): On each individual setting, the Contractor shall select a BAF resulting in a stand average of 4-8 large standing live trees per plot. If a 10 BAF is used, the minimum average live trees per plot standard is waived.
Small Tree (live): On each individual setting, the Contractor shall select a fixed area plot size resulting in a stand average of 4-8 small standing live trees per plot. If a 1/10th acre plot size is used, the minimum average live trees per plot standard is waived.
Large Tree (dead): On each individual setting, the Contractor shall select a fixed area plot size resulting in a stand average of 2-4 large standing dead trees per plot. If a one (1) acre plot size is used, the minimum average dead trees per plot standard is waived.
Contractor shall be responsible for collecting and filling out the Sample Design Form for all data items that are set to “YES” in the Required column below.
Table 4. CSE Sample Design Form Requirements
| FIELD NUMBER |
| FIELD DESCRIPTION |
| REQUIRED |
| DATA |
SOURCE
COMMENTS
| Region |
| Yes |
| Government |
| Proclaimed Forest |
| Yes |
| Government |
| District |
| Yes |
| Government |
| Location/Watershed Alias |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| Stand Number |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 1 |
| Sample Selection Method |
| Yes |
| Government |
| See Exhibit 1 – Sample Design Specifications. |
| 2 |
| Sample Expansion Factor |
| Yes |
| Contractor |
| See Exhibit 1 – Sample Design Specifications and Section 3.5.b. |
| 3 |
| Starting Azimuth |
| No |
| 4 |
| Subpop Filter |
| Yes |
| Government |
| See Exhibit 1 – Sample Design Specifications. |
| 5 |
| Selection Criteria Number |
| Yes |
| Government |
| See Exhibit 1 – Sample Design Specifications. |
| 6 |
| Subpop Variable |
| Yes |
| Government |
| See Exhibit 1 – Sample Design Specifications. |
| 7 |
| Subpop Minimum Value |
| Yes |
| Government |
| See Exhibit 1 – Sample Design Specifications. |
| 8 |
| Subpop Maximum Value |
| Yes |
| Government |
| See Exhibit 1 – Sample Design Specifications. |
| 9 |
| Remarks |
| No |
| Contractor |
All sample design fields, whether required by Contract or not, are included on the design form provided in the exhibits. Fields not specifically required by Contract are to be skipped on the sample design form.
c. Plot Form (CSE) The following items are required to be recorded at each plot on the Plot form. Detailed information and lists of valid codes for each data item are found in the Common Stand Exam Field Guide (Region 2) and Appendices (see Government Furnished Property). Contractor shall be responsible for collecting and filling out the Plot Data Form for all data items that are set to “YES” in the Required column.
Table 5. CSE Plot Form Requirements
FIELD NUMBER
FIELD DESCRIPTION
REQUIRED
DATA
COMMENTS
| Region |
| Yes |
| Government |
| Proclaimed Forest |
| Yes |
| Government |
| District |
| Yes |
| Government |
| Location/Watershed Alias |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| Stand Number |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 1 |
| Plot Number |
| Yes |
| Contractor |
| 2 |
| Latitude |
| No |
| 3 |
| Longitude |
| No |
| 4 |
| Capable Grow Area |
| Yes |
| Contractor |
| 5 |
| Aspect |
| No |
| 6 |
| Slope |
| No |
| 7 |
| Slope Position |
| No |
| 8 |
| Slope Horizontal Shape |
| No |
| 9 |
| Slope Vertical Shape |
| No |
| 10 |
| Elevation |
| No |
| 11 |
| Existing Vegetation |
| N/A |
| 12 |
| Potential Vegetation |
| No |
| 13 |
| Fuel Model |
| No |
| 14 |
| Residual Description Code |
| No |
| 15 |
| Dist Seed Wall |
| N/A |
| 16 |
| History |
| No |
| 17 |
| History Date |
| No |
| 18 |
| User Code |
| No |
| 19 |
| Plot Remarks |
| Yes |
Please use plot remarks
All plot data fields, whether required by Contract or not, are included on the plot data form provided in the exhibits. Fields not specifically required by Contract are to be skipped on the form.
d. Tree Form (CSE) Begin recording standing tree data on the Tree form at azimuth 360 (North), progressing in a clockwise direction around plot center. Trees shall be recorded in the following order:
| a. | Live Trees located on the variable radius plot, including growth tree data. |
| b. | Live Trees located on the small fixed radius plot, including growth tree data. |
| c. | Standing Dead trees on the large fixed radius plot. |
All tree data fields, whether required by Contract or not, are included on the tree data form provided in the exhibits. Fields not specifically required by Contract are to be skipped on the form.
The following items, except as noted, are required to be collected by Contractor for each tree on the plot, for the specified exam level. Detailed information and lists of valid codes for each data field are found in the Common Stand Exam Field Guide (Region 2) and Appendices (see Government Furnished Property). Contractor shall be responsible for collecting and filling out the Tree Data Form for all data items that are set to “YES” in the required column.
Table 6. CSE Tree Form Requirements
| FIELD NUMBER |
| FIELD DESCRIPTION |
| Extensive Examination Level |
| DATA |
REQUIRED FOR:
| BAF |
| Yes |
| Contractor |
| Fixed Plot Size |
| Yes |
| Contractor |
| Breakpoint DBH |
| Yes |
| Contractor |
| Location/Watershed Alias |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| Stand Number |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 1 |
| Plot Number |
| Yes |
| Contractor |
| All trees |
| 2 |
| Tag ID |
| Yes |
| Contractor |
| All trees |
| 3 |
| Tree Status |
| Yes |
| Contractor |
| All trees |
| 4 |
| Tree Class |
| No |
| 5 |
| Site/GST |
| Yes |
| Contractor |
| For growth trees only |
| 6 |
| Species |
| Yes |
| Contractor |
| All trees |
| 7 |
| Tree Count |
| Yes |
| Contractor |
| All trees |
| 8 |
| DRC Number Stems |
| Yes |
| Contractor |
| DRC species only |
| 9 |
| DBH/DRC |
| Yes |
| Contractor |
| All trees ≥4.5 feet tall |
| 10 |
| Height |
| Yes |
| Contractor |
| All trees |
| 11 |
| Height to Crown |
| No |
All trees
| 12 |
| Radial Growth |
| Yes |
| Contractor |
| Growth trees ≥3 inches DBH or DRC only |
| 13 |
| Height Growth |
| Yes |
| Contractor |
| Growth tree <3 inches DBH or DRC only |
| 14 |
| Age |
| Yes |
| Contractor |
| Growth trees only |
| 15 |
| Crown Ratio |
| Yes |
| Contractor |
| Growth tree only |
| 16 |
| Crown Class |
| No |
| 17 |
| Crown Width |
| No |
| 18 |
| Wildlife Use |
| No |
| 19 |
| Log/Snag Decay |
| Yes |
| Contractor |
| All standing dead trees ≥10 inches DBH or DRC and ≥12 feet in height (≥6 feet for DRC species). |
| 20 |
| Cone Serotiny |
| No |
| 21 |
| Damage Category |
| Yes |
| Contractor |
| All trees with damage. Record up to 3 most severe. |
| 22 |
| Damage Agent |
| Yes |
| Contractor |
| Required if damage category is not blank |
| 23 |
| Tree Part |
| No |
| 24 |
| Damage Severity |
| Yes |
| Contractor |
| Required if damage category is not blank |
| 25 |
| Tree Remarks |
| Yes |
| Contractor |
| Borderline trees |
| 26 |
| User Determined |
| No |
e. Down Woody Form (CSE) The Contractor shall collect data for down woody material, using the Piece Count on a Fixed Area Plot Method. On each individual setting, a fixed area plot size resulting in a stand average of 4-8 pieces per plot will be selected, with a minimum plot size of 1/100th acre. If a 1/10th acre plot size is used, the minimum average pieces per plot standard is waived.
The following items are required to be recorded on the down woody form at each plot. Detailed information and lists of valid codes for each data item are found in the Common Stand Exam Field Guide (Region 2) and Appendices. Minimum diameter and piece length is specified in the Sample Design, Exhibit 1. See the Common Stand Exam Field Guide for details on the method used.
Table 7. Down Woody Material form requirements.
| Field Number |
| Field Description |
| Required |
| Data Source |
| Comments |
| Region |
| Yes |
| Government |
| Proclaimed Forest |
| Yes |
| Government |
| District |
| Yes |
| Government |
| Location/Watershed Alias |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| Stand Number |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| 1 |
| Plot Number |
| Yes |
| Contractor |
| 2 |
| First Duff |
| Yes |
| Contractor |
| 3 |
| Second Duff |
| Yes |
| Contractor |
| 4 |
| Fuel Depth |
| Yes |
| Contractor |
| 5 |
| First Litter |
| No |
| 6 |
| Second Litter |
| No |
| 7 |
| Twig 1 (0-.24) |
| No |
| 8 |
| Twig 2 (.25-.99) |
| No |
| 9 |
| Twig 3 (1.0-2.99) |
| No |
| 10 |
| Piece Count |
| Yes |
| Contractor |
| 11 |
| Decay Class |
| Yes |
| Contractor |
| 12 |
| Diameter |
| Yes |
| Contractor |
| Midpoint diameter between large end and small end. |
| 13 |
| Diameter Large End |
| No |
| 14 |
| Diameter Small End |
| No |
| 15 |
| Piece Length |
| Yes |
| Contractor |
| 16 |
| Volume 1 |
| No |
| 17 |
| Weight 1 |
| No |
| 18 |
| Volume 2 |
| No |
| 19 |
| Weight 2 |
| No |
| 20 |
| Volume 3 |
| No |
| 21 |
| Weight 3 |
| No |
| 22 |
| Volume 4 |
| No |
| 23 |
| Weight 4 |
| No |
All down woody fields, whether required by this Contract or not, are included on the down woody form provided in the exhibits 1 and 6. Fields not specifically required by this Contract are to be skipped on the form.
f. Vegetation Composition Form (CSE) Vegetation composition form 1 (cover by life form) will be recorded on a plot size of 1/10 acre (37.2 foot radius). Record the total cover percent by lifeform. Form 2 (List species) and Form 4 (ground surface cover) will be collected on the same plot area (1/10 acre).
Record the total cover percent by lifeform. Record the presence of any Species of Concern (Noxious Weed species, see list – Exhibit 11), even if that species does not have 1% or more cover.
The following items are required at each plot. Detailed information and lists of valid codes for each data item are found in the Common Stand Exam Field Guide (Region 2) and Appendices.
Table 8. Vegetation Composition Form Requirements
| Field Description |
| Form Type |
| Data Source |
| Remarks |
| Form 1 |
| Form 2 |
| Form 4 |
| Region |
| Yes |
| Yes |
| Yes |
| Government |
| Proclaimed Forest |
| Yes |
| Yes |
| Yes |
| Government |
| District |
| Yes |
| Yes |
| Yes |
| Government |
| Location/Watershed Alias |
| Yes |
| Yes |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| Stand Number |
| Yes |
| Yes |
| Yes |
| Survey Stand List |
| Provided at prework conference. |
| Plot Num |
| Yes |
| Yes |
| Yes |
| Contractor |
| Life Form |
| Yes |
| Yes |
| NA |
| Contractor |
| Layer |
| Yes |
| Yes |
| NA |
| Contractor |
| Layer Code |
| Yes |
| Yes |
| NA |
| Contractor |
| Species |
| NA |
| Yes |
| NA |
| Canopy cover (%) |
| Yes |
| Yes |
| NA |
| Contractor |
| Predominant height |
| Yes |
| Yes |
| NA |
| Contractor |
| For Trees & Shrubs only |
| Predominant dbh/drc |
| Yes |
| No |
| NA |
| Contractor |
| For Trees only |
| Predominant age |
| NA |
| No |
| NA |
| Maturity |
| NA |
| No |
| NA |
| Shrub Form |
| NA |
| Yes |
| NA |
| User defined data |
| No |
| NA |
| No |
| Remarks |
| No |
| Yes |
| No |
| Surface Cover Type |
| NA |
| NA |
| Yes |
| Contractor |
| Cover % |
| No |
| NA |
| Yes |
| Contractor |
All vegetation composition data, whether required by Contract or not, are included on the vegetation composition form provided in the exhibits. Fields not specifically required by Contract are to be skipped on the form. All ground surface cover data, whether required by Contract or not, are included on the Ground Surface Cover Form provided in the exhibits. Fields not specifically required by Contract are to be skipped on the form.
g. R2 FSVeg Spatial Polygon Vegetation Attributes Form.
This form shall be completed for each stand. The field crew shall walk through the entire stand before completing the form. Detailed information and lists of valid codes are in the R2 Supplement to the FSVEG Spatial User Guide.
The Contractor will be responsible for collecting and filling out the ‘R2 FSVEG SPATIAL POLYGON VEGETATION ATTRIBUTES FORM’ for each polygon listed in the Survey Stand List and will complete all data items that are set to “YES” in the required column; data shall be submitted in a VEGPY or Survey123 electronic format:
Table 9. R2 FSVeg Spatial Polygon Vegetation Attributes form requirements.
| Item Description |
| Required |
| Data Source |
| Comments |
POLYGON INFORMATION
| Setting ID (16 digits) |
| Yes |
| Government |
| Survey Stand List |
| Region, Forest, District code |
| Yes |
| Government |
| Survey Stand List |
| Location |
| Yes |
| Government |
| Survey Stand List |
| Polygon ID |
| Yes |
| Government |
| Survey Stand List |
| Species Survey Method |
| Yes |
| Government |
| Always use the CANOPY method |
| Sample Recorder |
| Yes |
| Contractor |
| First, MI, Last |
| Regen EV Code/Prev Cover Type |
| Yes |
| Contractor |
| If the polygon does not currently have a total of 25% crown cover of trees, but was previously tree cover, enter the previous SAF tree cover type. (Refer to code list) |
| Stocking Flag |
| Yes |
| Contractor |
| ‘Y’ or ‘F’ (Refer to code list definitions) |
SAMPLE INFORMATION
| Date |
| Yes |
| Contractor |
| mm/dd/yyyy |
| Purpose code |
| Yes |
| Government |
| Always record ‘WV’ |
| Horizontal Diversity |
| Yes |
| Contractor |
| Enter ‘P’ or ‘C’ |
(Refer to code list definitions)
| Tree Crown Condition |
| Yes |
| Contractor |
| Enter ‘A’, ‘P’, ‘D’, or ‘S’ |
(Refer to code list definitions)
| Habitat Structural Stage |
| No |
Will be calculated by the government from the data collected
| Canopy Closure TREES |
| Yes |
| Contractor |
| Used for the CANOPY survey method only. Record the total crown cover of trees within the polygon on one plane looking down, corrected for overlap. Codes 1-100. |
| Change Category |
| Yes |
| Contractor |
| Refer to code list definitions |
| Change Date |
| No |
PHOTO FLIGHT ID
| Photo Project |
| No |
| Date |
| No |
| Remarks |
| No |
SPECIES ATTRIBUTES
| Lifeform/GSC |
| Yes |
| Contractor |
| Refer to code list definitions |
| Layer |
| Yes |
| Contractor |
| 0, 1, 2, 3 (Refer to code list definitions) |
| Species |
| Yes |
| Contractor |
| National Plants Database plant codes |
| Plant Cover % (Live) |
| Yes |
| Contractor |
| Record the % live cover based on the cover method used – 1-100 |
| Tree Size Class |
| Yes |
| Contractor |
| Record the size of tree lifeforms (Refer to code list definitions) |
| Shrub Size Class |
| Yes |
| Contractor |
| Record the size of shrub lifeforms (Refer to code list definitions) |
| Tree Dead % (Standing Dead) |
| Yes |
| Contractor |
| Record the % of live cover lost to dead (previous cover – current cover)– 1-100 |
4.0 Safety
Contractor’s operations shall facilitate the Government’s safe and practical inspection of Contractor’s operations and conduct of other official duties on Contract Area. The Contractor has all responsibility for compliance with safety requirements for the Contractor's employees. In the event that a conflict develops between the requirements of this Contract or agreed upon methods of proceeding hereunder and State or Federal safety requirements, the Contract shall be modified and the Contractor may request an equitable adjustment.
| a. | Contractor shall provide a copy of their Safety Plan at the Prework Conference and electronically, via email, to the CO. The Safety Plan shall be kept in the Contract folder for OSHA’s review. |
| b. | The Safety Plan shall be available to all employees and subcontractors working on the Contract. |
| c. | The Safety Plan shall contain contingency plans for emergencies such as medical, fire, hazardous material spills, and any other assessed hazard; as well as prevention and abatement requirements that apply to this Contract. |
5.0 Protection Measures
5.1 Protection of Land Survey Monuments
Contractor shall protect all known survey monuments, witness corners, reference monuments, and bearing trees against avoidable destruction, obliteration, or damage during Contractor’s Operations. If any known monuments, corners, or accessories are destroyed, obliterated, or damaged by Contractor’s Operations, Contractor shall hire the appropriate county surveyor or a registered land surveyor to reestablish or restore at the same location the monuments, corners, or accessories at no additional cost to the Government. Such surveyors shall use procedures in accordance with the Bureau of Land Management “Manual of Instructions for the Survey of the Public Lands of the United States” for General Land Office surveys and in accordance with State law for others. Contractor shall record such survey in appropriate county records.
5.2 Protection of Residual Trees
Contractor's Operations shall not unnecessarily damage young growth or other trees to be reserved.
5.3 Protection of Improvements
So far as practicable, the Contractor shall protect specified roads and other improvements (such as roads, trails, telephone lines, ditches, and fences):
| a. | Existing in the operating area, and |
| b. | Determined to have a continuing need or use, and |
| c. | Designated on the Map. |
The Contractor shall keep roads and trails needed for fire protection or other purposes and designated on the Map reasonably free of equipment and products, slash, and debris resulting from the Contractor’s operations. The Contractor shall make timely restoration of any such improvements damaged by the Contractor’s operations and, when necessary, because of such operations, shall move such improvements.
5.4 Camping Requirements
The Forest Service (FS) has various camping opportunities. Check with local FS unit for camping requirements; camping permits may be required. Verify local fire restriction policies.
If camps will be used to house workers subject to MSPA, they are also subject to the temporary labor camp standards at 29 CFR 1910.142. The Forest Service reserves the right to terminate a camping permit at any time. These requirements are in addition to those contained in or provided for under the clause titled “452.236-72 Use of Premises” in this Contract. Any violation of these conditions constitutes a breach of contract and may result in revocation of camping approval.
a. Every structure used as shelter must provide protection from the elements. Where adequate heat is not provided, make other arrangements to protect workers from the cold. Cut firewood only after a District Firewood Permit is obtained.
b. The campsite must not encroach beyond the boundaries designated by the Forest Service. The campsite location must minimize impacts on streams, lakes, and other bodies of water. Camping is not permitted within developed recreational sites or along primary recreational roads.
c. The campsite must have a clean appearance at all times. Upon abandonment of any campsite, or termination, revocation, or cancellation of camping privileges, the Contractor shall remove, within 10 calendar days, all structures and improvements except those owned by the United States, and shall restore the site, unless otherwise agreed upon in writing or in the camping permit. Structures or improvements the Contractor fails to remove within the 10-calendar day period becomes the property of the United States, however, the Contractor remains liable for the cost of the removal and restoration of the site.
d. Unless otherwise designated by the CO, the use of the area is not exclusive and may be granted to other permittees, contractors, or recreating public. Disorderly conduct is not permitted.
e. Damaging or removing any natural feature or other property of the Forest Service is prohibited.
f. Servicing of motorized equipment in the campsite is not permissible.
g. Provide sanitary facilities for storing food. Provide ice chests or coolers, with ice supply made from potable water, and replenish as necessary. Provide sufficient storage for perishable food items. All food must be stored in a closed vehicle or other bear-proof container.
h. Provide an adequate and convenient potable water supply in each camp for drinking and cooking purposes.
i. Provide adequate toilet facilities and toilet paper for the capacity of the camp. Service and maintain facilities in a sanitary condition.
j. Collect, store, and dispose of garbage in a manner to discourage rodent access, minimize attraction of flies, and prevent scattering by wind. All garbage must be stored in a closed vehicle or other bear-proof container, or immediately disposed of in a bear-proof receptacle.
k. Maintain basic first aid supplies available, which must be under the charge of a person trained to administer first aid. The basic supplies must include:
· Gauze pads (at least 4x4 inches)
· Two large gauze pads (at least 8x10 inches)
· Box adhesive bandages (band-aids)
· One package of gauze roller bandage (at least 2-inches in width)
· Two triangular bandages
· Scissors
· At least one blanket
· Tweezers
· Adhesive tape
· Latex gloves, and
· Resuscitation device such as resuscitation bag, airway, or pocket mask.
l. Wash laundry in such a way that washing and rinsing will not pollute lakes, streams, or other flowing water.
m. Dispose waste water away from living and eating areas and in such a way that minimizes pollution to lakes, streams, and other flowing water.
n. The Contractor shall take all reasonable precautions to prevent and suppress forest fires. Do not dispose of material by burning in open fires during the closed season established by law or regulation without the written permission from the Forest Service.
o. If authorized to have an open fire, the Contractor shall comply with the following fire regulations:
· A shovel, axe or Pulaski, a 10-quart pail, which is full of water for immediate use, and a fire extinguisher with an Underwriters Laboratory (UL) rating of at least 1:A 10:BC is required.
· All fire rings or outside fireplaces must be approved by the Forest Service representative. The area must be cleared down to mineral soil for a distance of one foot outside of the ring or fireplace, and it must not have any overhanging material. Fire rings must be dismantled and material disposed prior to leaving the site.
· All generators and other internal combustion engines must be equipped with Forest Service-approved spark arrestors and/or factory designed muffler and exhaust system in good working order. They will be located in a cleared area with the same requirements as in described in the previous paragraph.
All fuel must be stored in UL approved flammable storage containers and be located at least 50 feet from any open flame.
6.0 Deliverable / Schedule
6.1 Deliverables and Schedule
Table 10. Deliverables required under the Contract.
| Item Description |
| Submittal Due |
| Copies Required |
| Post-award/prework conference |
| Within 30 days after the date of contract award. |
| NA |
| Proposed Operation Plan (Overall Schedule): The Contractor shall prepare and submit two copies (or one electronic copy) of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the starting and completion dates of various phases of the work. The schedule shall comply with the contract time requirements in the Contract. The schedule shall be provided in either 8.5’x11’ or 11’x17’ format. |
| With Proposal |
| Proposal evaluation requirements: The vendor shall submit items required for the evaluation of factors other than price. See Proposal Evaluation Criteria included with Contract for details. |
| With Proposal |
| 1 |
| Subcontractors: List of proposed subcontractors and their intended work. Subcontractors must have Contracting Officer’s written approval prior to starting work on the project. |
| With Proposal |
| Safety Plan: The Contractor shall comply with the requirements of FAR 52.236-13 – Accident Prevention, for all activities under this Contract. |
| With Proposal |
| Quality Control Plan: Submit original with proposal. Any updates need to be provided for approval to the CO. See Section 13.1. |
| With Proposal |
| 2 |
| Designation of Contractor personnel describing responsibilities and authorities. |
| At prework conference |
| 2 |
| Common Stand Exam Data: Submitted in inspection blocks of completed stands only. See data format requirements. |
| Weekly, or a minimum of once every two weeks during the performance period. |
| 1 |
| R2 FSVEG Spatial Polygon Vegetation Attributes data: Submitted with stand exam data for the corresponding stands. See data format requirements. |
| Weekly, or a minimum of once every two weeks during the performance period. |
| 1 |
| Return of Government Property: Items listed in section 7 as to be returned to the Government |
| At end of contract performance or upon contract termination. |
| NA |
6.2 Data Format Requirements
Data recorded on paper forms shall not be accepted (except stand sketches and traverse notes where applicable). Data shall be provided to the Government in electronic files on CD-R disks, DVD-R disks, a portable USB flash drive, portable flash memory card, or via Contractor provided FTP site. An email with a zipped attached file shall also be acceptable. The file shall be zipped to help avoid data corruption. With any electronic media, data must be readable by the Government’s computers (Windows 10 operating system) and free of viruses or other threats to information systems. Adjustments shall not be made for software or hardware errors that result in data error or loss of data. Data will be subject to inspection and acceptance of work prior to payment.
Unless otherwise specified, Common Stand Exam data shall be submitted in the .CSE file format and R2 FSVEG Spatial Polygon Vegetation Attributes Form data shall be submitted in the .TRU or Survey123 ArcGIS Online file format for each stand. Specific electronic file naming conventions shall be outlined during the prework conference. A listing of all settings (stands) and plots contained in each submitted data file shall also be provided with each inspection block.
7.0 Government Furnished
Government Property listed in this clause is furnished to the Contractor in an “as-is, where is” condition. The Government makes no warranty regarding the suitability for use of the Government property specified in this Contract. The Contractor shall be afforded the opportunity to inspect the Government property as specified in the solicitation.
a. The Government bears no responsibility for repair or replacement of any lost Government property. If any or all of the Government property is lost or becomes no longer usable, the Contractor shall be responsible for replacement of the property at Contractor expense. The Contractor shall have title to all replacement property and shall continue to be responsible for contract performance.
b. Unless the Contracting Officer determines otherwise, the Government abandons all rights and title to unserviceable and scrap property resulting from contract performance. Upon notification to the Contracting Officer, the Contractor shall remove such property from the Government premises and dispose of it at Contractor expense.
c. Except as provided in this clause, Government property furnished under this Contract shall be governed by the Government Property clause of this Contract.
d. Government property provided under this clause:
Table 11. Government property provided.
| Item Number |
| Item |
| Description |
| Where, When, How |
| Returned to Government prior to final payment |
| 00001 |
| General Area Maps |
| Maps of stands with access roads identified. |
| Provided as identified in Attachments. |
No
| 00002 |
| NAIP images |
| Print-outs (8.5X11 at app. 1:12000 scale) of the plot locations displayed over orthophotography will be available at prework conference. |
| Provided at prework conference. |
| No |
| 00003 |
| Common Stand Exam (CSE) Field Guide (R2), appendices, and data collection forms |
| One copy (paper or electronic) of the USDA Forest Service’s Common Stand Exam Field Guide, appendices, and data collection forms. |
| Available from the internet website: https://www.fs.usda.gov/nrm/fsveg/ |
Yes, if paper copy provided
| 00004 |
| R2 Supplement to the FSVeg Spatial User Guide, and data collection forms |
| One copy (paper or electronic) of the R2 Supplement used for completing the R2 FSVeg Spatial Polygon Vegetation Attributes form. |
| Provided as identified in Attachments. |
| No |
| 00005 |
| Survey Stand List |
| List of settings, number of plots, and additional information (Location/Watershed Alias, Elevation, Aspect, Acres, Setting ID, Region/Forest/District Code) |
| Provided at prework conference. |
| No |
| 00006 |
| Specified plot locations |
| Shapefiles or .kml files of Plot location points and stands to be sampled. |
| Available from COR; provided at prework conference. |
| No |
| 00007 |
| Topographic maps |
| Print-outs of the plot locations displayed over topo maps. |
| Provided at prework conference. |
| No |
| 00008 |
| Forest Visitors Map and district transportation map |
| One copy of the forest map and the district transportation map. |
| Provided at prework conference. |
| Yes |
| 00009 |
| Use of Premises permit |
| Permit to occupy the national forest in excess of time limits imposed in standard orders. |
| Provided when and/or if needed. |
| No |
| 00010 |
| Common Stand Exam & R2 Veg Polygon Inspection Forms |
| One copy of inspection forms. |
| Provided in Appendix A of the QASP. |
| No |
| 00011 |
| Portable Data Recorder software for CSE |
| Available at: https://www.fs.usda.gov/nrm/fsveg/#software |
| No |
| 00012 |
| PC-based data entry software (MS Windows XP operating system required) |
| ExamsPC program. |
| Available at: https://www.fs.usda.gov/nrm/fsveg/#software |
| No |
| 00013 |
| Tablet or PC-based VEGPY, tablet or PC-based Survey123 software for R2 Veg Attribute data |
| Contractor preference. |
| Provided at prework conference |
| No |
| 00014 |
| Yale Key |
| Key used to access plot behind closed gates. |
| Provided at prework conference. |
| Yes |
8.0 Travel
Travel to and from the worksite is the sole responsibility of the Contractor.
9.0 Contractor’s Key Personnel
The Contractor shall assign to this Contract the following key personnel:
a. Contractor’s Representative
b. Field Representative
i. Contractor’s Field Representative (Field Rep)—The Contractor shall designate (in writing) an on-site Field Rep and an alternate in their absence. Each designated representative shall be fluent in both spoken and written English. The Field Rep shall be readily available to the area of operations when operations are in progress, shall have a copy of the Contract on site during operations, and shall be authorized to receive notices in regard to performance under this Contract and take related action. The responsibilities of the Field Rep shall include the safeguarding of National Forest resources and performance within the terms of the Contract.
c. Field Representative – Alternate
10.0 Security Requirements
Security Requirements are not applicable to this Contract.
11.0 Data Rights
Restriction on disclosure and use of data: Offerors that include in their proposal data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall mark the title page with the following legend: “This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed – in whole or in part – for any purpose other than to evaluate this proposal. If, however, a Contract is awarded to this Offeror as a result of – or in connection with – the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government’s right to use information contained in this data if it is obtained from another source without restriction. The Government shall own all data rights for deliverables produced by this Contract.
12.0 Section 508 - Electronic and Information Technology Standards If information technology is to be acquired, include language describing Section 508 requirements.
Section 508 requirements do not apply to the electronic data acquired through this Contract.
13.0 Performance Requirement Measures
13.1 Contractor Quality Control Plan
The Contractor shall provide a general Quality Control Plan (QCP) with the technical proposal. The Contractor shall supplement the QCP within 10 days before start work based on the items awarded to the Contractor.
The QCP must demonstrate how the Contractor will assure quality and meet the requirements and specifications of the Contract. It shall describe how quality will be monitored to assure that work meets the standards for measurement, safety and other associated tasks.
13.2 Quality Assurance Surveillance Plan
The Government shall assess work, accept or reject deliverables, and issue payments based upon surveillance methods established in the attached Quality Assurance Surveillance Plan. This plan includes accuracy standards as well as AQL’s.
Attachments Exhibit 1 –SAMPLE DESIGN SPECIFICATIONS –Pay Items 3.1 & 3.3)
REGION: _ PROC. FOREST: _ _ DISTRICT: _ LOCATION: ____ STAND NO.___________
Form
Sample Selection Method
XXX
Sample Expansion Factor
XXXXX.X
Starting Azimuth
XXX
Subpop.
Filter
XXXXXXXX
Selection Criteria Number
XX
Subpop.
Variable
XXX
Subpop.
Minimum Value
XXXX.X
Subpop.
Maximum Value
XXXX.X
| TREE |
| BAF |
| Contractor selection; see 3.5.b. |
| LIVE |
| 1 |
| DBH |
| 5.0 |
| 999.9 |
| LIVE |
| 2 |
| DRC |
| 5.0 |
| 999.9 |
| TREE |
| FRQ |
| Contractor selection; see 3.5.b. |
| LIVE |
| 3 |
| DBH |
| 0.1 |
| 4.9 |
| LIVE |
| 4 |
| HGT |
| 0.5 |
| 4.49 |
| LIVE |
| 5 |
| DRC |
| 0.1 |
| 4.9 |
| TREE |
| FRQ |
| Contractor selection; see 3.5.b. |
| DEAD |
| 6 |
| DBH |
| 10.0 |
| 999.9 |
| DEAD |
| 6 |
| HGT |
| 12.0 |
| 999.9 |
| DEAD |
| 7 |
| DRC |
| 10.0 |
| 999.9 |
| DEAD |
| 7 |
| HGT |
| 6.0 |
| 999.9 |
| DNWDY |
| FRQ |
| Contractor selection; see 3.5.e. |
| DOWN |
| 8 |
| DIA |
| 3.00 |
| 999.9 |
| DOWN |
| 8 |
| LGT |
| 3.00 |
| 999.9 |
| VEGCOM |
| FRQ |
| 10 |
| LIVE |
| 9 |
| CVR |
| 1 |
| 100 |
| SURCOV |
| FRQ |
| 10 |
| 10 |
| SVC |
| 1 |
| 100 |
1-2. Using a XX BAF, sample standing live and dead trees 5.0” DBH/DRC and larger
3-5. Using a XX acre plot, sample DBH live trees between 0.1” and 4.9 “ DBH, live seedlings between 0.5’ and 4.49’ in height, and DRC live trees between 0.1” and 4.9” DRC.
6-7. Using a XX acre plot, sample large standing dead trees 10.0” DBH/DRC and 12’ Height (or 6’ Height for DRC species) and larger.
8. Using a XX acre plot, measure dead down woody material 3 to 999.9 inches in diameter and between 3 to 999.9 feet in length. Diameter measured is the midpoint diameter.
9. On a 1/10 acre plot, measure vegetation composition by lifeform, and all species listed in Appendix 10.
10. On a 1/10 acre plot, measure the ground surface cover for all cover types that cover 1% or more of the plot.
Exhibit 2- Setting Form
Project Name:_________________________________________________________(25 characters total)
Region*
XX
Proc.
Forest*
District*
Location*
XXXXXXXXXXXXXX
Stand # *
XXXX
Owner
State
County
XXX
Admin.
Forest
XX
Admin.
Region
Date*
MM/DD/YYYY
Photo ID
XXXXXXXXXXXXXX
Exam Level*
XXXX
Exam Purpose
Stratum
XXXXXX
Exist. Veg. Ref.
XXXX
Existing Vegetation
XXXX
Potential Veg. Ref
XXX
Potential Vegetation
XXXXXXXX
Structure
Capable Growing
Fuel Model
Elevation
XXXXX
Aspect
Slope
Slope Position
Acres
Radial Growth Interval
XX
Radial Growth Interval 2
XX
Height Growth Interval
Fuel Photo Reference
Precision Protocol
XXXXXX
Examiner
XXXXXXXXXXXX
Remarks (242 characters)
Damage Category
Damage Agent
XXX
Damage Severity
XXX
Species of Management Interest
XXXXXXXX
User Code
Exhibit 3- Sample Design Form
REGION:__________ PROCLAIMED FOREST:__________ DISTRICT:__________
LOCATION:_______________ STAND NO.:_______________
Sample Selection Method*
XXX
Sample Expansion Factor*
XXXXX.X
Starting Azimuth
XXX
Subpop. Filter
XXXXXXXX
Selection Criteria Number*
XX
Subpop. Variable
XXX
Subpop. Min. Value
XXXX.XX
Subpop. Max. Value
XXXX.XX
Sample Design Remarks: (242 characters)
Exhibit 4- Plot Data Form
REGION:_____ PROC. FOREST:________ DISTRICT:________ LOCATION:____________________ STAND NUMBER:________
Plot # *
Lat.
DDDMMSS
Long.
DDDMMSS
Cap Grow Area
Asp
Slope
Slope Pos.
XX
Slope Horz.
Shape
XX
Slope Vert.
Shape
Elev
XXXXX
Existing Vegetation
XXXXXXXX
Potential Vegetation
XXXXXXXX
Fuel Mod
XX
Residue Desc.
Code
XXXXXXXXXXXXXXX
Dist. Seed Wall
Hist
Hist Date
YYYY
User Code
Plot Remarks (255 Characters)
Exhibit 5- Tree Data Form
BAF:_____ FIXED PLOT SIZE:_______ MIN. DBH:______ LOCATION:____________________ STAND NUMBER:________
Plot
XXX
Ta g
XXXX
Tree Status
X
Tree Class
XX
Site/
GST
X
Species
XXXXXXXX
Tree Count
XXX
DRC
Stems
XXX
DBH/
DRC
XXX.X
Height
Height to Crown
XXX
Rad Grow
XX
Rad Grow
XX
HGT
Grow
XX.X
Age
Crown Ratio
XXX
Crown Class
XX
Crown Width
XXX
Wildl.
Use
XX
L/S Decay
X
Cone Serotiny
X
Damage Category
XX
Damage Agent
XXX
Tree Part
XX
Damage Severity
XXXXX
Tree Remarks
30 charact
User Code
XXXX
Ttmnt.
Option
X
Alternate Tree Data Form
BAF: __________ Fixed Plot Size: _________ MIN. DBH: _______ Location: ________ Stand Number: ____
| Plot # |
| Tag # |
| Tree Status |
| Tree Class |
| Site/GST |
| Species |
| Tree Count |
| DRC # Stems |
| DBH/DRC |
| Height |
| Height to Crown |
| Radial Growth |
| Radial Growth 2 |
| Height Growth |
| Age |
| Crown Ratio |
| Crown Class |
| Crown Width |
| Wildlife Use |
| L/S Decay |
| Cone Serotiny |
| Damage Category |
| Damage Agent |
| Tree Part |
| Damage Severity |
| Tree Remarks |
| User |
Code Treatment Option
| XXX |
| XXX |
| X |
| X |
| X |
| XXXXXXXX |
| XXX |
| XXX |
| XXXXX |
| XXX |
| XXX |
| XX |
| XX |
| XXXX |
| XXXX |
| XXX |
| XX |
| XXX |
| XX |
| X |
| X |
| XX |
| XXX |
| XX |
| XXXXX |
| 30 Char. |
| XXXX |
| X |
Exhibit 6 -- Downed Woody Material Form: Brown’s Transect or Fixed-Area Piece Count
Admin Region: ______ Admin For: ______ Proc Region: ______ Proc For: ______ District: ______ Location: _____________________ Stand No: __________
1000-Hr (3”+)
Plot
XXX
1st Duff inches
XX.X
2nd Duff inches
XX.X
Fuel Depth Inches
XX.X
(Twig1) 1-Hr 0-.24”
XXX
(Twig2) 10-Hr 0.25-.99”
XXX
(Twig3) 100-Hr 1-2.99”
XXX
Piece Count
XXX
Decay Class
X Diam
XXX.X
Piece Length*
XXX.X
Small End Dia
XXX.X
Large End Dia
XXX.X
*1000-Hr piece length is needed to compute pieces/acre Exhibit 7--Vegetation Composition Forms 1 & 2, Cover By Lifeform (Live only) Admin Region: _____ Admin For: _____ Proc Region: _____ Proc For: _____ District: _____ Location: ___________________ Stand No: _______ Plot: _____
| Required Data |
| Optional Data |
Life form
Layer
Layer Code
% Canopy Cover (0.1 for trace)
XX.X
Live/ Dead
X Predom Height
XXX
Predom Diameter
XXX
User Code
XXXX
Remarks
20 Char Max.
Required Layers, if present
| Total Vegetation |
| TV |
L
| TR |
| Total Tree |
| TOT |
L
| TR |
| Trees >= 6.1’ |
| TOV |
L
| TR |
| Trees <= 6.0’ |
| TSA |
L
| SH |
| Total Shrub |
| TOS |
L
| SH |
| Shrubs >= 6.1’ |
| ST |
L
| SH |
| Shrubs 1.6’ to 6.0’ |
| SM |
L
| SH |
| Shrubs < 1.6’ |
| SL |
L
| FB |
| Total Forbs |
| TOF |
L
| GR |
| Total Graminoids |
| TOG |
L
| Optional Layers |
| HB |
| Total Herbs |
| TOH |
L
| AL |
| Total Algae |
| TAL |
L
| LC |
| Total Lichen |
| TLC |
L
| FU |
| Total Fungus |
| TFU |
L
| LI |
| Total Woody Liana |
| TLI |
L
| SS |
| Tot Woody SubShr |
| TSS |
L
| VI |
| Total Herb. Vine |
| TVI |
L
| NP |
| Total NonVascular |
| TNP |
L
| UN |
| Total Unknown |
| TUN |
L
| VP |
| Total Vascular |
| TVP |
L
Hatched fields = Not filled for the layer Vegetation Composition Form 1, Cover By Lifeform (Live and Dead) Admin Reg: _____ Admin For: _____ Proc Reg: _____ Proc For: _____ District: _____ Location: ______________ Stand No: _______ Plot: _____
| Required Data |
| Optional Data |
Life form
Layer
Layer Code
% Canopy Cover (0.1 for trace)
XX.X
Live/ Dead
X Predom Height
XXX
Predom Diameter
XXX
User Code
XXXX
Remarks
20 Char Max.
Required Layers, if present. Collect data on dead veg only if specified in the Sample Design
| Total Vegetation |
| TV |
L
D
| TR |
| Total Tree |
| TOT |
L
D
| TR |
| Trees >= 6.1’ |
| TOV |
L
D
| TR |
| Trees <= 6.0’ |
| TSA |
L
D
| SH |
| Total Shrub |
| TOS |
L
D
| SH |
| Shrubs >= 6.1’ |
| ST |
L
D
| SH |
| Shrubs 1.6’ to 6.0’ |
| SM |
L
D
| SH |
| Shrubs < 1.6’ |
| SL |
L
D
| FB |
| Total Forbs |
| TOF |
L
D
| GR |
| Total Graminoids |
| TOG |
L
D
| Optional Layers |
| HB |
| Total Herbs |
| TOH |
L
D
| AL |
| Total Algae |
| TAL |
L*
| LC |
| Total Lichen |
| TLC |
L*
| FU |
| Total Fungus |
| TFU |
L*
| LI |
| Total Woody Liana |
| TLI |
L*
| SS |
| Tot Woody SubShr |
| TSS |
L*
| VI |
| Total Herb. Vine |
| TVI |
L*
| NP |
| Total NonVascular |
| TNP |
L*
| UN |
| Total Unknown |
| TUN |
L*
| VP |
| Total Vascular |
| TVP |
L*
*L = Live; do not collect Dead data for this layer. Hatched fields = Not filled for the layer Collect data on dead vegetation only if specified in the Sample Design.
Vegetation Composition Form 2, Cover By Layer and Species
| Required Data |
| Optional Data |
Life form
Layer
Layer Code
Species
XXXXXXXX
% Canopy Cover (0.1 for trace)
XX.X
Live/ Dead
X Predom Height
XXX
Predom Diameter
XXX
Predom Age
XXXX
Maturity
XXXX
Shrub Form
XXXX
User Code
XXXX
Remarks
20 Char Max.
| TR |
| Trees >= 6.1’ |
| TOV |
| TR |
| Trees <= 6.0’ |
| TSA |
| SH |
| Shrubs >= 6.1’ |
| ST |
| SH |
| Shrubs 1.6’ to 6.0’ |
| SM |
| SH |
| Shrubs < 1.6’ |
| SL |
Admin Reg: _____ Admin For: _____ Proc Reg: _____ Proc For: _____ District: _____ Location: ______________ Stand No: _______ Plot: _____ Collect data on dead vegetation only if specified in the Sample Design. Hatched fields = Not filled for the layer
Exhibit 8 -- Vegetation Composition Form 4, Ground Surface Cover Ground Surface Cover Type
XXXX
% Cover
XX.X
Remarks
20 Char Max.
Admin Reg: _____ Admin For: _____ Proc Reg: _____ Proc For: _____ District: _____ Location: ______________ Stand No: _______ Plot: ____
Total ground surface cover of all features must equal 100%
Exhibit 9 -- R2 FSVEG SPATIAL POLYGON VEGETATION ATTRIBUTES FORM Rev 04-17-2014 Zwisler POLYGON SAMPLE INFORMATION: bold* fields are required
(in NRIS_VegPoly table)…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .