This is a Statement of Work (SOW) for the GMUG NF Culvert Contract issued by the US Department of Agriculture Forest Service, updated August 3, 2026.

The contractor must procure, deliver, and offload corrugated steel pipe culverts to the USDA Forest Service North Delta Administrative site located at 1560 H 50 Road, Delta, Colorado within 60 days of contract award. The specific culvert requirements include three types of 16-gauge galvanized spiral corrugated steel pipe (CSP) with connecting bands: 18-inch x 24-foot, 24-inch x 24-foot, and 36-inch x 20-foot configurations, with quantities specified in a separate Schedule of Items (Bid Schedule). All culverts must conform to AASHTO M 36 and either AASHTO M 218, M 274, or M 289 standards. Delivery is restricted to Monday through Thursday between 8:00 AM and 4:00 PM, and the contractor must provide a minimum of ten working days' advance notice to the technical specialist to coordinate Forest Service personnel for acceptance. The contractor is responsible for all procurement costs and is recommended to rent a forklift for safe offloading; any culverts damaged prior to or during offloading will be rejected. No government-furnished property is provided. The SOW indicates this contract represents a similar scope to one awarded in 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT #1

US Department of Agriculture (USDA)

Statement of Work

UPDATED 8/3/2026

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards Attachment

Project GMUG NF Culvert Contract

General Information

1.0 Scope of Work

The scope of this project is the purchase, delivery, and offloading of culverts as specified in the specifications and schedule of items.

2.0 Background

The general description of the requirement is the purchase and delivery of culverts. A similar contract of this scope was awarded in 2025.

Contractor Requirements

3.0 Technical Requirements / Tasks

The contractor must procure, deliver, and offload the culverts at the USDA Forest Service North Delta Administrative site at 1560 H 50 Road, Delta, Colorado.

It is recommended that the contractor rents a forklift capable of safely offloading the culverts at the administrative site.

Any culverts damaged prior to or during the offloading process will not be accepted. Culverts can be delivered Monday through Thursday between 8:00 AM and 4:00 PM. The contractor must contact the technical specialist a minimum of ten

(10) working days in advance of delivery to ensure there is a Forest Service employee that can accept the culverts.

Culvert requirements.

Section 707. — METAL PIPE

707.02 Metallic-Coated Corrugated Steel Pipe.

Provide pipe, special sections (such as elbows, branch connections, and prefabricated flared end sections) and coupling bands conforming to AASHTO M 36 and either AASHTO M 218, AASHTO M 274, or AASHTO M 289 for the dimensions, classification type, and thicknesses specified.

Fabricate underdrain pipe from steel sheets with a minimum thickness of 0.052 inch. Use any class of perforation specified in AASHTO M 36.

18-inch x 24-foot. 16-guage 2 2/3 x 1/2 galvanized spiral corrugated steel pipe (CSP) 18-inch band H-12 annular band with connecting bolts for spiral (CSP)

24-inch x 24-foot. 16-guage 2 2/3 x 1/2 galvanized spiral corrugated steel pipe (CSP) 24-inch band H-12 annular band with connecting bolts for spiral (CSP)

36-inch x 20-foot. 16-guage 2 2/3 x 1/2 galvanized spiral corrugated steel pipe (CSP) 36-inch band H-12 annular band with connecting bolts for spiral (CSP)

Refer to the schedule of items for quantities needed.

4.0 Government Furnished

There is NO government furnished property.

5.0 Deliverables / Schedule

Refer to the Schedule of Items (Bid Schedule) for deliverables. The contractor is responsible for delivering the culverts within 60 days of receipt of award.

6.0 Travel

Not applicable jpedrotti Cross-Out jpedrotti Cross-Out

7.0 Contractor’s Key Personnel

8.0 Security Requirements

Not applicable

9.0 Data Rights

Not applicable

10.0 Section 508 – Electronic and Information Technology Standards Not applicable

Attachments

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards