Questions and Answers.pdf
PDF 132 KB Posted
- Attached to
- Cole Ranch Farmhouse Demolition Services
- Solicitation number
- 1240LP26Q0074
About this file
This is a Questions and Answers document addressing clarifications related to a federal contract for the demolition and remediation of three structures.
The project scope is limited to three structures and their foundations only, excluding concrete pads, walkways, driveways, propane tanks, fencing, and outbuildings. Weather shutdown days extend the contract duration only under circumstances outlined in FAR 52.212-4. The contractor is responsible for utility disconnections located after the meter, requiring only an electrician. No septic tanks, leach fields, or mapped water lines exist on the property; any water lines connected to the well must be capped. Asbestos and lead-based paint surveys have been completed for the three structures. Backfilled areas require 85 to 90 percent compaction. Seeding is not required and will be omitted from final documents. The contractor retains salvage rights to materials of value including metals, fixtures, appliances, and lumber. A site visit is being offered prior to the proposal due date as instructed on SAM.gov. On-site staging and laydown area details are referenced in the Performance Work Statement. The applicable Department of Labor wage determination is attached in the SAM.gov attachments section and is covered by the Service Contract Act. No performance or payment bond is required. Concrete and brick do not need to be removed from the site but can be placed in the basement prior to backfill, provided all concrete and brick remain at least 3 feet below finished grade.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Will weather shutdown days extend the contract duration?
• Only in circumstances outlined by 52.212-4 Terms and Conditions
2. Will utility disconnects be completed by the utility providers, or is the contractor responsible for coordination and physical disconnects?
• The contractor is responsible for the disconnection. The disconnect is located after the meter and should only require an electrician.
3. Is there a known location map for septic tanks, leach fields, or water lines?
• There are no known septic tanks or leach fields. At one time there was a lagoon and that has been mitigated.
• There are no mapped water lines. Any line would be connected to our well and will need to be capped.
4. What compaction percentage is required for backfilled areas?
• 85 to 90 percent compaction
5. Although Section 3.3 states seeding is not required, the performance table references grading and seeding. Please clarify whether seeding is required.
• Seeding is not required and will be omitted in the final documents.
6. Have asbestos and lead-based paint surveys been completed for the three structures? Yes
7. Are concrete pads, walkways, driveways, propane tanks, fencing, and outbuildings/sheds included, or limited strictly to the three structures?
• The project is limited to the three structures and there foundations.
8. Does the contractor retain salvage rights to materials of value (metals, fixtures, appliances, lumber), or does all material remain Government property?
• Yes
9. Is a site visit being offered prior to the proposal due date?
• Yes, as instructed in SAM.gov in the description.
10. Is an on-site staging/laydown area identified, and may the contractor stage equipment overnight?
• Please refer to the PWS.
11. Will an applicable DOL wage determination be incorporated by amendment, or does the WG-3 reference govern?
• Wage Determination is attached in the attachments section of sam.gov. This wage determination is covered by the SCA.
12. Is a performance and/or payment bond required?
• No
13. Does concrete and brick need to be removed from the site?
• No, concrete and brick can be placed in the basement of the house prior to backfill. All concrete and brick must be at least 3 feet below finished grade.