This is a Request for Quote (RFQ) from the USDA Forest Service for forest-wide tree clearing work in the Big Horn National Forest. The solicitation seeks a contractor to perform clearing, grubbing, tree removal, stump removal, and disposal of material on three National Forest System Roads (NFSR 17, 24, and 26), totaling 42.60 miles of clearing and grubbing across approximately 52.47 project miles. The work includes tasks such as erosion control, traffic management, and personal protective equipment requirements.
The contract period of performance is from 06/01/2026 to 10/31/2027, with a total contract value to be determined by unit pricing. The solicitation includes provisions for small business set-aside, representations and certifications, and workforce requirements under the Migrant and Seasonal Agricultural Workers Protection Act. Offerors must submit a technical proposal demonstrating past performance, quality control plan, and experience, along with a price proposal. Offers must be submitted electronically to Curtis Landreth by the specified due date, with questions accepted until September 23, 2025. The government will evaluate offers based on past performance, technical capability, and price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LP25Q0112
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LP
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 4
GAOA09/12/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
09/12/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Big Horn National Forest
Forest Wide Tree Clearing which incorporates wage determination 1979-0948 rev 74 dated
07/29/2025.
Amendment 1: Removes Soil Erosion and Sediment Control from RFQ. Please see updated RFQ for changes.
All other terms and conditions remain unchanged.
Period of Performance: 06/01/2026 to 10/31/2027
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
CURTIS R. LANDRETH
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation Number: 1240LP25R0022
FAC 2025-05 August 7, 2025
SECTION B – CONTINUATION OF SF-1449
Schedule of Items/Price Schedule
Project Description:___________________________________________________________
Vendor Name: __________________________________Vendor UEI:___________________
Item Number Description Pay
Unit
Contract Quantity
NFSR
Contract Quantity
NFSR 24
Contract Quantity
NFSR 26
Total Contract
Quantity
Unit Price Amount
001 Mobilization LS - - - 1 $ $
Clearing & Grubbing, Disposal F/G/I
Miles* 9.90 10.39 22.31 42.60
Total $
Schedule Notes:
b) One award will be made from this solicitation, contractors must submit pricing for all items.
Description of Requirement
General Information
2.0 Scope of Work
Clearing, grubbing, tree removal, stump removal, disposal of material, temporary traffic control, soil erosion and sediment control. All work is adjacent to or on forest service roads. The following roads are included in this contract along with corresponding miles.
Road No.
Begin
MP
End
MP
Total Project Miles
Total Clearing and Grubbing Miles
NFSR 17 12.12 25.40 13.28 9.90
NFSR 24 0.00 14.90 14.90 10.39
NFSR 26 7.40 31.69 24.29 22.31
Total Miles: 52.47 42.6
3.0 Contractor Requirements
3.1 Control of Work and Material
1) See section “Deliverables” for information regarding submittals
2) Use of Roads by Contractor – The contractor is authorized to use roads under the jurisdiction of the forest service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or National Forest resources, and when traffic can be accommodated safely.
3) Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.
3.2 Acceptance of Work
1) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements.
The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
Government inspections and tests are for the sole benefit of the Government.
2) The Government may inspect, sample, or test all work at any time before final acceptance of the project.
3) Visual Inspection - Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.
4) Partial and Final Acceptance – When a segment of the project is completed, a final inspection of that segment may be requested. If the segment is complete and incompliance, it may be accepted. Notify the CO when the entire project is complete to schedule an inspection. If work is determined to be complete, the inspection will constitute the final inspection. Final acceptance relieves the contractor of further responsibility for the project. If the inspection discloses unsatisfactory work, then the CO will provide to the contractor a list of the work that is incomplete or requires correction. Immediately complete or correct the work. Submit notification when the work has been completed as provided above.
3.3 Legal Relations and Responsibility to the Public
1) Preserve public of private property. Protect monuments established for survey control. Do not disturb the area beyond the project limits. Do no excavate, remove, damage, alter, or deface archaeological or paleontological remains or specimens.
2) Utilities - Before beginning the work, contact the local utility locating service to mark utilities. Protect utilities from operations. Notify CO if work requires relocation or adjustment of utilities to complete the project.
3) Sanitation, Health, and Safety – Observe rules and regulations of Federal, state, and local health officials. Provide sanitation facilities for workers. Comply with Applicable OSHA regulations and notify the CO of any accidents. Install a reverse signal alarm audible above the surrounding noise level on motorized vehicles having an obstructed view and on earth-moving and compaction equipment.
4) Environmental Protection –
a) Clean Water Act - In accordance with the Federal Water Pollution Control Act (Clean
Water Act), do not operate equipment or discharge material within the boundaries of Waters of the United States (WOTUS) as defined by the federal and state regulatory agencies. Construct and maintain barriers in work areas and in material sources to prevent sediment, petroleum products, chemicals, and other liquids and solids from entering WOTUS. Remove and properly dispose of barrier collected material.
b) Hazardous Spill Plan - Submit a Hazardous Spill Plan describing preventative measures including location of refueling and storage facilities and the handling of hazardous material. Describe actions in case of a spill. Have all materials and supplied readily available to enact plan in case of a spill. Do not use equipment with leaking fluids.
Repair equipment leaks immediately. Keep absorbent material manufactured for containment and cleanup of hazardous material on the job site. Notify the CO of hazardous spills.
c) Equipment Cleaning and Inspection –
i) Remove dirt, plant, and foreign material from vehicles and equipment before mobilizing to work site. Prevent introduction of noxious weeds and non-native plant species into the work site. Follow applicable Federal land management agency requirements and state requirements. Maintain clearing and inspection reports.
ii) All heavy equipment (loaders, excavators, dump trucks, etc.) shall be cleaned of weeds and their seeds and thoroughly inspected prior to mobilization and each entrance onto the National Forest lands. Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds.
Special care shall be taken to assure removal of the following noxious weeds and their seeds. This may require the use of a pressure hose.
iii) Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands. At least 48 hours prior to mobilization of any piece of equipment, the contractor shall advise of a proposed date, time, and location for mobilization and provide the opportunity for the government to inspect the equipment. Inspections will take place at mutually agreeable en route locations in advance of entry onto National Forest lands.
iv) The contractor shall inspect all equipment prior to mobilization to the National Forest Lands and document that inspection on the “Equipment Cleaning Inspection/Verification Form”. The contractor shall attach photographic documentation of the cleaned equipment with the Equipment Inspection Form and include that with the daily report for the day.
v) If either the contractor or the Forest Service finds that the equipment is not sufficiently clean, then the equipment shall be recleaned and reinspected prior to use on the project site. All cleaning shall occur off of National Forest lands.
vi) Once on site, all equipment shall be inspected daily and all visible oil, grease, and hydraulic fluid will be removed; this inspection shall be documented in the daily dairy. Needed repairs will be implemented immediately before resuming work.
vii) All equipment shall be in good repair, and capable of accomplishing assigned tasks in a safe and environmentally acceptable manner.
d) Fish Protection
i) Draft hoses being used to withdraw water from any stream or pond located on Forest shall utilize one of the following methods of screening:
ii) Perforated Plate; screen openings shall not exceed 3/32 or 0.0938 inches (2.38 mm).
iii) Profile Bar Screen; screen openings shall not exceed 0.0689 inches (1.75 mm) the narrowest dimension.
iv) Woven Wire Screen; the screen openings shall not exceed 3/32 or 0.0938 inches (2.38
mm) in the narrow direction.
e) Fire Control
i) Comply with the requirements of the “Rocky Mountain Region Contractor Fire Plan Requirements”
5) Permissible Hours of Work - No work shall be performed on weekends and Federal Holidays, unless specifically stated in the task order, or otherwise approved in writing by the CO. No work shall be performed between the hours of 6 PM and 6 AM, unless specifically approved in writing by the CO.
3.4 Measurement and Payment
1) Payment for contract work is provided either directly or indirectly under the pay items listed in the bid schedule. Compensation provided by the pay items listed in the bid schedule is full payment for performing contract work in complete and acceptable manner. Risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the pay items. Work measured and paid for under one pay item will not be paid for under other pay items.
a) Direct payment – Payment is provided directly under a pay item listed in the bid schedule
b) Indirect payment – Work for which direct payment is not provided and there is no pay item listed in the bid schedule. Payment for such work is indirectly paid by the direct payment pay items listed in the bid schedule.
2) The quantities listed in the bid schedule are contract quantities and will be adjusted only when there are errors in the original design of 15% or more.
3.5 Mobilization
1) Work consists of moving all personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site, and including moving between sites within project. This work also includes obtaining permits and insurance.
3.6 Survey and Staking
1) Prior to beginning work on a road or road segment, stake the edge of road, limits of stump removal, and limits of roadside clearing. Provide CO 1 day notice to inspect the stakes prior to starting work.
2) Forest Service may provide Avenza points indicating the starting and finishing locations of clearing and grubbing sections.
3.7 Quality Control
1) Identify a Quality Control Manager. This individual will be on-site when work is performed and will be responsible for quality control including for performing inspections to confirm that all work conforms to the project requirements and responsible for correction of deficient work.
a) Weekly Operations Reports – The Quality Control Manager shall provide a weekly operations report that describes what work was performed including location, limits, equipment used, work tasks started/in progress/complete, equipment cleaned, inspected, and mobilized, quality control (QC) inspections performed, government quality assurance (QA) inspections performed, discussions, meetings, deficiencies identified, deficiencies corrected, etc.
b) The QCM can be a collateral duty with project superintendent.
2) The QCM shall use a Critical Path Method Schedule to ensure that the work is planned and implemented to assure timely completion and to enable QC and QA inspections.
3.8 Public Traffic
1) Accommodate traffic according to the MUTCD, approved traffic control plan, and this section. Perform work in a manner that ensures safety and convivence of the public. Unless there is a temporary road closure allowed, keep existing roads open to all traffic during road work. Delays shall not exceed 204 minutes at any one time followed up with an open period of at least 60 minutes.
2) Submit a Temporary Traffic Control Plan at least 30 days prior to intended use. Perform no work that interferes with or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post project signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15. All required signs will be in place and approved prior to beginning work on the project. The public will be alerted to any hazards on the roadway such as equipment, personnel, slash piles, etc. by means of signs, warning devices or flaggers.
3) Temporary Traffic Control - Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD.
When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags.
Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02. The public shall be alerted to any hazards on the roadway such as equipment, personnel, slash piles, etc by means of signs, warning devices, or flaggers.
4) Temporary Road Closures - Road segments may be closed as shown below. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).
Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated. Prior to closing roads during project work, give written notice to the Contracting Officer at least 10 days in advance.
Temporary Road Closures
Road Number
From Terminus
To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
NFSR 17
Begin Project End Project 1 1
NFSR 24
Begin Project End Project 1 1
NFSR 26
Begin Project End Project 1 1
3.9 Soil Erosion and Sediment Control
1) Thirty (30) days prior to the start of the project work, submit a written plan that provides temporary erosion control measures to minimize erosion and sedimentation during project work. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control without approval.
When erosion control measures are not functioning as intended, take corrective action to eliminate or minimize pollutants in storm water discharges from the project.
2) Before site disturbing activities, construct sediment controls around the perimeter of the project including filter barriers, diversion, and settling structure, as applicable to the work performed. Limit the combined clearing and grubbing operations to 8 acres of exposed soil at one time. Implement temporary controls in the incremental stages as project work proceeds.
3) Construct silt fence, berms, and fiber rolls and socks to reduce the velocity of runoff to allow sediment to settle.
3.10 Clearing & Grubbing
1) Construct erosion control measures.
2) Clearing and grubbing removal limits are shown in the typical sections.
3) Do not damage vegetation outside of the limits shown. If damage occurs, repair or replace vegetation in an acceptable manner. Treat cuts or scarred surfaces of trees and shrubs with tree wound dressing.
4) Clearing within the clearing limits shown, clear trees, brush, downed timber, and other vegetation. Cut trees so they fall within the clearing limits. In areas where stump removal is not shown on typical section, cut stumps flush with or below the final ground line.
5) Tree tops and limbs shall be disposed of in accordance with Disposal Method G. Limbs from trees outside of the clearing limits but extending within 4’ of the edge of road shall be removed to a height of 14 feet from the roadbed elevation. These limbs are to be cut flush with the tree.
6) Outside of the limits of stump removal shown on the typical section, cut stumps to maximum stump height shown in table below. Utilization standards for merchantable timber are listed below. Fall and buck merchantable material into lengths not to exceed ____8_____ feet.
Pieces (logs) meet utilization standards when such pieces would have met Utilization Standards if bucking lengths were varied to include such material.
7) Merchantable timber is Government property. Merchantable timber shall follow Disposal Method I, Decking, and be bucked into lengths not to exceed 8' and can be placed in convenient locations adjacent to the road for firewood cutters to collect.
Minimum Utilization Standards
Species Maximum Stump
Height (inches) Length (feet) Diameter1 (inches) % Net Scale2 Lodgepole Pine & Other Conifer
2 8 7.0
1 measured at inside bark at small end 2 in % gross scale
8) Clearing and grubbing Disposal Method F, G, or I shall be applied based on the typical section and the material to be disposed of.
9) Grubbing is required within 2 ft of the edge of roadway, as shown on the typical sections as ‘stump removal.’ Grub deep enough to remove stumps, roots, buried logs, moss, turf, or other vegetative debris. Backfill stump holes and other grubbing holes with backfill material to the level of the surrounding ground. Compact Backfill with project equipment.
10) Stumps within the “stump removal” limits shown on the typical shall be disposed of in accordance with disposal method F. All stumps outside of the “stump removal” limits are to remain and shall be cut horizontally and left a maximum of 2 inches above the ground.
11) All cleared and grubbed material shall be removed from the road surface and ditchlines.
12) Chipping or Grinding. Use an appropriate machine to chip or grind slash when disposal method G is applicable. No wood piece shall be greater than 3 inches in length. Deposit chips or ground woody material outside clearing limits to a loose depth no more than 3 inches. Areas exceeding 3 inches are to be spread out. All chipped material must be kept out of water courses. Submit equipment specifications on the chipper and grinder to be utilized to the CO for approval before the start of the project.
13) Clearing & grubbing is paid directly by the Clearing & Grubbing, Disposal G/F/I pay item.
Payment will be made at the contract price per unit of measurement. Payment will be full compensation for the work prescribed in this section and for any work indirectly paid by or incidental to this line item.
3.11 Disposing of Material
1) Dispose of debris, unsuitable material, and excess material in accordance with the following methods as specified in this contract:
• Method F - Scattering. Scatter slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other slash to reduce slash concentrations. When scattering for erosion control, place slash as flat as practicable on the completed slope.
• Method G - Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 3 inches. Method G
• Method I - Decking. Remove brush from designated log deck areas. Limb and top logs.
Logs not meeting the Utilization Standards described in Subsection “Clearing and
Grubbing” shall be cut to lengths less than 8 feet and decked in designated log deck location. Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection “Clearing and Grubbing.” Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage and will not roll. Keep logs in log decks free of brush and soil.
2) Disposal of Material is paid indirectly by the Clearing & Grubbing, Disposal G/F/I pay item.
4.0 Government Furnished
There are no government furnished equipment, property, or materials in this project.
5.0 Deliverables / Schedule
Key Deliverables Item No.
Deliverable / Item Title
Description Frequency Reference Delivery Format
Due By
1 Temporary Traffic Control Plan
An MUTCD compliant plan for temporary traffic control
Once Subsection “Public Traffic “
Via email to
COR
14 days prior to start of work on site.
Approval required prior to start of work.
2 Soil Erosion and Prevention Control Plan
A plan describing the best management practices that will be implemented to prevent and control soil erosion
Once Subsection “Soil Erosion and Sediment Control”
Via email to
COR
14 days prior to start of work on site.
Approval required prior to start of work.
3 Schedule of Work
A critical path method-based schedule showing the tasks required to complete the project and their relationships
Once, Update if more than 10 days behind schedule
Subsection “Quality Control”
Via email to
COR
14 days prior to start of work on site
4 Clearing and
Specifications of the equipment
Once Subsection “Clearing
Via email to
COR
14 days prior to start
Grubbing Equipment proposed for use for clearing and grubbing activities and Grubbing” of work on site.
Approval required prior to start of work.
5 Equipment Inspection Reports
Reports documenting that cleaning was acceptable prior to entrance on to NFS Lands
For each piece of equipment
Subsection “Legal Relations and Responsibility to the Pubic”
Via email to
COR
Within 48 hours of mobilizing the equipment
6 Weekly Operations Reports
Reports summarizing work performed
Weekly Subsection “Quality Control”
Via email to
COR
First business day following the week of the report
6.0 Travel
Contractor is responsible for all travel and mobilization for project.
7.0 Contractor’s Key Personnel
Quality Control Manager – Shall have at least 2 years’ experience as a Quality Control Manager on projects of similar scope, magnitude, and complexity.
Project Superintendent – Shall have at least 2 years’ experience superintending projects of similar scope, magnitude, and complexity.
8.0 Security Requirements
There are no security requirements applicable to this project
9.0 Data Rights
There are no data rights applicable to this project.
10.0 Section 508 – Electronic and Information Technology Standards There are no electronic or information technology standards applicable to this project
SECTION C - CONTRACT CLAUSES
Clauses Incorporated by Reference
FAR 52.203-3 Gratuities (APR 1984) FAR 52.204-13 System for Award Management Maintenance (OCT 2018) FAR 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) FAR 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts
(MAY 2024) (DEVIATION FEB 2025)
FAR 52.228-5 Insurance – Work on a Government Installation (JAN 1997) FAR 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (APR
1984) FAR 52.242-17 Government Delay of Work (APR 1984) FAR 52.245-1 Government Property (SEP 2021) Alt 1 (APR 2012) FAR 52.245-9 Use and Charges (APR 2012) AGAR 452.204-70 Modification for Contract Closeout
Clauses Incorporated by Full Text
FAR 52.212-4 Contract Terms and Conditions – Commercial Products and Commercial Services (NOV 2023)
FAR 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders – Commercial Products and Commercial Services (JAN 2025)
(DEVIATION FEB 2025)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) FAR 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) FAR 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) (Section 1634 of Pub. L. 115-91).
(3) FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115- 232).
(4) FAR 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015).
(5) FAR 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).
https://www.acquisition.gov/far/52.203-19#FAR_52_203_19 https://www.acquisition.gov/far/52.204-23#FAR_52_204_23 https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 https://www.acquisition.gov/far/52.209-10#FAR_52_209_10 https://www.acquisition.gov/far/52.232-40#FAR_52_232_40 https://www.govinfo.gov/link/uscode/31/3903 https://www.govinfo.gov/link/uscode/10/3801
(6) FAR 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(7) FAR 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
[Contracting Officer check as appropriate.]
☒ (1) FAR 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).
☐ (2) FAR 52.203-13, Contractor Code of Business Ethics and Conduct (NOV 2021) (41 U.S.C. 3509)).
☐ (3) FAR 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
☒ (4) FAR 52.203-17, Contractor Employee Whistleblower Rights (NOV 2023) (41 U.S.C.
4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).
☒ (5) FAR 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) (31 U.S.C. 6101 note).
☐ (6) [Reserved].
☐ (7) FAR 52.204-14, Service Contract Reporting Requirements (OCT 2016) (Pub. L. 111-
117, section 743 of Div. C).
☐ (8) FAR 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery
Contracts (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).
☒ (9) FAR 52.204-27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section
102 of Division R of Pub. L. 117-328).
☐ (10) FAR 52.204-28, Federal Acquisition Supply Chain Security Act Orders—Federal
Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts.
(Dec 2023) (Pub. L. 115–390, title II)
☒ (11)(i) FAR 52.204-30, Federal Acquisition Supply Chain Security Act Orders— Prohibition (Dec 2023) (Pub. L. 115–390, title II)
☐ (ii) Alternate I (Dec 2023) of FAR 52.204-30.
☒ (12) FAR 52.209-6, Protecting the Government’s Interest When Subcontracting with
Contractors Debarred, Suspended, or Proposed for Debarment, or Voluntarily Excluded.
(JAN 2025) (31 U.S.C. 6101 note).
☐ (13) FAR 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) (41 U.S.C. 2313).
☐ (14) [Reserved].
☐ (15) FAR 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (OCT 2022) (15
U.S.C. 657a).
https://www.acquisition.gov/far/52.233-3#FAR_52_233_3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.233-4#FAR_52_233_4 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.203-6#FAR_52_203_6 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.govinfo.gov/link/uscode/10/4655 https://www.acquisition.gov/far/52.203-13#FAR_52_203_13 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.203-15#FAR_52_203_15 https://www.acquisition.gov/far/52.203-17#FAR_52_203_17 https://www.govinfo.gov/link/uscode/41/4712 https://www.govinfo.gov/link/uscode/41/4712 https://www.acquisition.gov/far/3.900#FAR_3_900 https://www.acquisition.gov/far/52.204-10#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/52.204-14#FAR_52_204_14 https://www.acquisition.gov/far/52.204-15#FAR_52_204_15 https://www.acquisition.gov/far/52.204-27#FAR_52_204_27 https://www.acquisition.gov/far/52.204-28#FAR_52_204_28 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.acquisition.gov/far/52.209-6#FAR_52_209_6 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/52.209-9#FAR_52_209_9 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section2313&num=0&edition=prelim https://www.acquisition.gov/far/52.219-3#FAR_52_219_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637a&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637a&num=0&edition=prelim
☐ (16) FAR 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
☐ (17) [Reserved] ☒ (18) (i) FAR 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C.
644).
☐ (ii) Alternate I (Mar 2020) of FAR 52.219-6.
☐ (19) (i) FAR 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C.
644).
☐ (ii) Alternate I (Mar 2020) of FAR 52.219-7.
☐ (20) FAR 52.219-8, Utilization of Small Business Concerns (JAN 2025) (15 U.S.C.
637(d)(2) and (3)).
☐ (21) (i) FAR 52.219-9, Small Business Subcontracting Plan (JAN 2025) (15 U.S.C. 637(d)(4)).
☐ (ii) Alternate I (Nov 2016) of FAR 52.219-9.
☐ (iii) Alternate II (Nov 2016) of FAR 52.219-9.
☐ (iv) Alternate III (Jun 2020) of FAR 52.219-9.
☐ (v) Alternate IV (JAN 2025) of FAR 52.219-9.
☐ (22) (i) FAR 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).
☐ (ii) Alternate I (MAR 2020) of FAR 52.219-13.
☒ (23) FAR 52.219-14, Limitations on Subcontracting (OCT 2022) (15 U.S.C. 637s).
[Contracting Officer check as appropriate.] ☒ By the end of the base term of the contract and then by the end of each subsequent option period; or
☐ By the end of the performance period for each order issued under the contract.
☐ (24) FAR 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C.
637(d)(4)(F)(i)).
☐ (25) FAR 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (FEB 2024) (15 U.S.C. 657f).
☒ (26) (i) FAR 52.219-28, Postaward Small Business Program Rerepresentation (JAN 2025) (15 U.S.C. 632(a)(2)).
☐ (ii) Alternate I (MAR 2020) of FAR 52.219-28.
☐ (27) FAR 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (OCT 2022) (15 U.S.C. 637(m)).
☐ (28) FAR 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (OCT 2022) (15 U.S.C. 637(m).
☐ (29) FAR 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).
☐ (30) FAR 52.219-33, Nonmanufacturer Rule (SEP 2021) (15 U.S.C. 637(a)(17)).
https://www.acquisition.gov/far/52.219-4#FAR_52_219_4 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-6#FAR_52_219_6 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-6#FAR_52_219_6 https://www.acquisition.gov/far/52.219-7#FAR_52_219_7 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-7#FAR_52_219_7 https://www.acquisition.gov/far/52.219-8#FAR_52_219_8 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-13#FAR_52_219_13 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-13#FAR_52_219_13 https://www.acquisition.gov/far/52.219-14#FAR_52_219_14 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-16#FAR_52_219_16 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-27#FAR_52_219_27 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-28#FAR_52_219_28 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-28#FAR_52_219_28 https://www.acquisition.gov/far/52.219-29#FAR_52_219_29 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-30#FAR_52_219_30 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.219-32#FAR_52_219_32 https://www.govinfo.gov/content/pkg/USCODE-2018-title15/html/USCODE-2018-title15-chap14A-sec644.htm https://www.acquisition.gov/far/52.219-33#FAR_52_219_33 https://www.govinfo.gov/content/pkg/USCODE-2018-title15/html/USCODE-2018-title15-chap14A-sec637.htm
☒ (31) FAR 52.222-3, Convict Labor (JUN 2003) (E.O.11755).
☐ (32) FAR 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2025)
(E.O. 13126).[ ☐ (33) [Reserved] ☐ (34) [Reserved] ☒ (35) (i) FAR 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).
☐ (ii) Alternate I (JUL 2014) of FAR 52.222-35.
☒ (36) (i) FAR 52.222-36, Equal Opportunity for Workers with Disabilities (JUN
2020) (29 U.S.C. 793).
☐ (ii) Alternate I (Jul 2014) of FAR 52.222-36.
☒ (37) FAR 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).
☒ (38) FAR 52.222-40, Notification of Employee Rights Under the National Labor Relations
Act (Dec 2010) (E.O. 13496).
☒ (39) (i) FAR 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter
78 and E.O. 13627).
☐ (ii) Alternate I (Mar 2015) of 52.222-50 ( 22 U.S.C. chapter 78 and E.O. 13627).
☒ (40) FAR 52.222-54, Employment Eligibility Verification (JAN 2025) (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
☐ (41) (i) FAR 52.223-9, Estimate of Percentage of Recovered Material Content for EPA– Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
☐ (ii) Alternate I (MAY 2008) of FAR 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
☐ (42) FAR 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (MAY 2024) (42 U.S.C. 7671, et seq.).
☐ (43) FAR 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (MAY 2024) (42 U.S.C. 7671, et seq.).
☐ (44) FAR 52.223-20, Aerosols (MAY 2024) (42 U.S.C. 7671, et seq.).
☐ (45) FAR 52.223-21, Foams (MAY 2024) (42 U.S.C. 7671, et seq.).
☒ (46) FAR 52.223-23, Sustainable Products and Services (MAY 2024) (DEVIATION FEB
2025) (7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l).
☐ (47) (i) FAR 52.224-3 Privacy Training (JAN 2017) (5 U.S.C. 552 a).
☐ (ii) Alternate I (Jan 2017) of FAR 52.224-3.
☒ (48) (i) FAR 52.225-1, Buy American-Supplies (OCT 2022) (41 U.S.C. chapter 83).
☐ (ii) Alternate I (Oct 2022) of 52.225-1 ☐ (49) (i) FAR 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (NOV
2023) (19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C. chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.
☐(ii) Alternate I [Reserved] https://www.acquisition.gov/far/52.222-3#FAR_52_222_3 https://www.acquisition.gov/far/52.222-19#FAR_52_222_19 https://www.federalregister.gov/executive-order/13126 https://www.usda.gov/sites/default/files/documents/far-class-deviation-regarding-new-trade-agreements-thresholds.pdf https://www.acquisition.gov/far/52.222-35#FAR_52_222_35 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title38-section4212&num=0&edition=prelim https://www.acquisition.gov/far/52.222-35#FAR_52_222_35 https://www.acquisition.gov/far/52.222-36#FAR_52_222_36 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title29-section793&num=0&edition=prelim https://www.acquisition.gov/far/52.222-36#FAR_52_222_36 https://www.acquisition.gov/far/52.222-37#FAR_52_222_37 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title38-section4212&num=0&edition=prelim https://www.acquisition.gov/far/52.222-40#FAR_52_222_40 https://www.acquisition.gov/far/52.222-50#FAR_52_222_50 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.222-50#FAR_52_222_50 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.222-54#FAR_52_222_54 https://www.federalregister.gov/executive-order/12989 https://www.federalregister.gov/executive-order/12989 https://www.acquisition.gov/far/22.1803#FAR_22_1803 https://www.acquisition.gov/far/22.1803#FAR_22_1803 https://www.acquisition.gov/far/52.223-9#FAR_52_223_9 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.223-9#FAR_52_223_9 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.223-11#FAR_52_223_11 https://www.govinfo.gov/link/uscode/42/7671 https://www.acquisition.gov/far/52.223-12#FAR_52_223_12 https://www.govinfo.gov/link/uscode/42/7671 https://www.acquisition.gov/far/52.223-20#FAR_52_223_20 https://www.govinfo.gov/link/uscode/42/7671 https://www.acquisition.gov/far/52.223-21#FAR_52_223_21 https://www.govinfo.gov/link/uscode/42/7671 https://www.acquisition.gov/far/52.223-23#FAR_52_223_23 https://www.govinfo.gov/link/uscode/7/8102 https://www.govinfo.gov/link/uscode/42/6962 https://www.govinfo.gov/link/uscode/42/8259b https://www.govinfo.gov/link/uscode/42/7671l https://www.acquisition.gov/far/52.224-3#FAR_52_224_3 https://www.acquisition.gov/far/52.224-3#FAR_52_224_3 https://www.acquisition.gov/far/52.225-1#FAR_52_225_1 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.govinfo.gov/link/uscode/19/3301 https://www.govinfo.gov/link/uscode/19/2112 https://www.govinfo.gov/link/uscode/19/3805 https://www.govinfo.gov/link/uscode/19/4001 https://www.govinfo.gov/link/uscode/19/4001
☐(iii) Alternate II (JAN 2025) of FAR 52.225-3.
☐(iv) Alternate III (FEB 2024) of FAR 52.225-3.
☐(v) Alternate IV (OCT 2022) of FAR 52.225-3.
☐ (50) FAR 52.225-5, Trade Agreements (NOV 2023) (19 U.S.C. 2501, et seq., 19 U.S.C.
3301 note).
☒ (51) FAR 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
☐ (52) FAR 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).
☐ (53) FAR 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).
☐ (54) FAR 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area
(NOV 2007) (42 U.S.C. 5150).
☒ (55) FAR 52.226-8, Encouraging Contractor Policies to Ban Text Messaging While Driving (MAY 2024) (E.O. 13513).
☐ (56) FAR 52.229-12, Tax on Certain Foreign Procurements (FEB 2021).
☐ (57) FAR 52.232-29, Terms for Financing of Purchases of Commercial Products and
Commercial Services (NOV 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).
☐ (58) FAR 52.232-30, Installment Payments for Commercial Products and Commercial
Services (NOV 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).
☒ (59) FAR 52.232-33, Payment by Electronic Funds Transfer-System for Award
Management (OCT2018) (31 U.S.C. 3332).
☐ (60) FAR 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award
Management (Jul 2013) (31 U.S.C. 3332).
☐ (61) FAR 52.232-36, Payment by Third Party (MAY 2014) (31 U.S.C. 3332).
☐ (62) FAR 52.239-1, Privacy or Security Safeguards (AUG 1996) (5 U.S.C. 552a).
☒ (63) FAR 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or
Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024) (Sections 1821-1826, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).
☐ (64) FAR 52.242-5, Payments to Small Business Subcontractors (JAN 2017) (15 U.S.C. 637(d)(13)).
☐ (65) (i) FAR 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021) (46 U.S.C. 55305 and 10 U.S.C. 2631).
☐ (ii) Alternate I (Apr 2003) of FAR 52.247-64.
☐ (iii) Alternate II (Nov 2021) of FAR 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
[Contracting Officer check as appropriate.] https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-5#FAR_52_225_5 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section2501&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://www.acquisition.gov/far/52.225-13#FAR_52_225_13 https://www.acquisition.gov/far/52.225-26#FAR_52_225_26 https://www.acquisition.gov/far/52.226-4#FAR_52_226_4 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.226-5#FAR_52_226_5 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.226-8#FAR_52_226_8 https://www.federalregister.gov/executive-order/13513 https://www.acquisition.gov/far/52.229-12#FAR_52_229_12 https://www.acquisition.gov/far/52.232-29#FAR_52_232_29 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.govinfo.gov/link/uscode/10/3805 https://www.acquisition.gov/far/52.232-30#FAR_52_232_30 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.govinfo.gov/link/uscode/10/3805 https://www.acquisition.gov/far/52.232-33#FAR_52_232_33 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3332&num=0&edition=prelim https://www.acquisition.gov/far/52.232-34#FAR_52_232_34 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.232-36#FAR_52_232_36 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.239-1#FAR_52_239_1 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section552a&num=0&edition=prelim https://www.acquisition.gov/far/52.240-1#FAR_52_240_1 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section3901&num=0&edition=prelim https://www.acquisition.gov/far/52.242-5#FAR_52_242_5 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://www.govinfo.gov/content/pkg/USCODE-2019-title46/html/USCODE-2019-title46-subtitleV-partD-chap553-subchapI-sec55305.htm http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.247-64#FAR_52_247_64
☒ (1) FAR 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter67).
☒ (2) FAR 52.222-42, Statement of Equivalent Rates for Federal Hires (MAY 2014) (29
U.S.C. 206 and 41 U.S.C. chapter 67).
☐ (3) FAR 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price
Adjustment (Multiple Year and Option Contracts) (AUG 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).
☒ (4) FAR 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014) (29U.S.C.206 and 41 U.S.C. chapter 67).
☐ (5) FAR 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) (41 U.S.C. chapter 67).
☐ (6) FAR 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (MAY 2014) (41 U.S.C. chapter 67).
☒ (7) FAR 52.222-55,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .