Amendment 0001_ Q and A with attachments.pdf

PDF 4 MB Posted

Attached to
GAOA - El Cap Recreation Area Improvements: Campground and Day Use Area
Solicitation number
1240BJ24R0012
Issued by

About this file

This document is an amendment to a solicitation for the GAOA - El Capitan Recreation Area Improvements, Phase 3 project. The amendment provides responses to questions submitted by potential offerors regarding the project requirements.

The key details are:

  • The project involves construction of improvements to the El Capitan Campground and Day Use Area, as well as repairs to the adjacent USFS dock facility. The work includes site preparation, earthworks, gravel parking, trails, signage, site furnishings, drainage, installation of a vault toilet, and removal of debris and invasive plant species.
  • There is a base bid and three option items: Option 1 for additional recreation area work, Option 2 for a campground, and Option 3 and 4 for dock repairs.
  • The project is located in the Thorne Bay Ranger District of the Tongass National Forest, about 75 road miles north of Craig, Alaska.
  • The magnitude of construction is between $1,000,000 and $5,000,000, with a period of performance from June 15, 2024 to June 30, 2025.
  • The amendment addresses questions related to invasive species management, disposal of overburden, quality control, pipe locations, planting soil, and decking materials, among other topics.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

ROXANNE ANDERSON

Project Name: GAOA - EL Capitan Recreation Area Improvements, Phase 3 This amendment 0001 is issued to:

1. provide responses to Questions that have been submitted as of May 20, 2024.

Procurement & Property Services, Field Procurement Operations Northwest Zone – Construction & A-E Attn: Roxanne Anderson, CO

1240BJ24R0012

05/20/2024

04/25/2024

5/20/2024

Questions and Answers

EL Cap Recreation Improvements Project

Solicitation: 1240BJ24R0012

1. For the invasive species plan: would the USFS be open to disposing of this material by digging deep into the rock pit floor and covering with overburden and then capping with rock. I have read the specs on this I'm just curious if the USFS would be open to other less costly options.

Please see response to Question #13.

2. In the event of running out of room for waste in the rock pit, could we dispose of overburden off the east end of the project.

Please provide a location on the plans where you are proposing the disposal of overburden.

3. Clarify note 5 on sheet L7. It appears that the only thing to be removed is the concrete pad.

There’s a picnic table and fire ring there. See picture 3 on sheet L5 for reference.

4. What is the other contractor’s timeline with the use of the rock pit for the cabin and spur road parking lot.

Mid-June for the cabin and we have not received a schedule from road contractor yet. However, it is likely they will both develop rock together as they are aware of the mid-June timeline by cabin contractor.

5. is the contractor building the new cabin planning to use the admin cabin for housing. Is there a potential conflict with the other contractor after Labor Day of this year if we plan to use this facility for housing.

They have no plans to use the admin cabin as their current schedule has them done and mobbed out by end of August.

6. Is the USFS wanting a third-party quality control person on site at all times of work, I know that this is a large added cost, or can the contractor fulfill the quality control duties required. Excepting special testing requirements such as concrete testing

Contractor can fulfill quality control duties required. Third party quality control is not mandatory.

7. Is the 8" pipe on the spur road included in this contract or the spur road contract.

The 8" pipe on the spur road is included in this contract.

8. on sheet L8 the note that states, Place 745 sq ft of 12" depth planting soil and reseed etc... If option 2 is not chosen, install 3880 sq ft etc.... is this to mean that we place 12" of soil in the areas of option 2, if it is not chosen. I wonder if this should be a separate option or line item so that cost can be separated out?

That note is part of Option 1 and not in contract.

9. plans show only 87 LF of 18" CPP. Where is the 222 LF that the schedule of items shows for the base bid?

Plans are correct, 222 LF is wrong. Please omit that quantity and bid on 87 LF of 18” CPP.

10. Is bio-based oil required for equipment on this project

It is not required.

11. would a bolt on sacrificial anode cathodic protection system be allowed for this project, instead of a weld on system

Yes, a bolt on sacrificial anode will be acceptable.

12. The bid sheet under option item #3 -O3.04 - states to remove timber decking and replace with non-slip timber decking. and on the finger float O3.12 it asks for non-slip composite/lumber decking. in the specs it has specs for FRP fiberglass decking. What is the product that will be used to replace the decking on the docks?

The contractor can use either Timber Deck as currently exists on the dock, or composite decking. A submittal will need to be provided by the awarded Contractor.

13. The specs say that 4" of the invasive sites is to be placed in plastic bags to be hauled off. This can be done but is very time-consuming and very expensive. We would like to propose that this can be loaded in trucks and tarped to be hauled to its final destination? We do have the concern that if we bid on this to bag the material, our competitors will bid on this to just haul off without bagging and have a cost advantage in the bid, so we do want this to be clarified either way. It will save a lot of money to tarp the material for hauling.

Bagging will not be required. Within limits of excavation at Bishops Weed Patch #1 (see BW1 noted in red font), remove plants and top 8” of soil and roots. Contain securely and transport excavated materials to location of Bishops Weed Patch #2 located near Option Item 1 area (see BW2 noted in blue font). Deposit excavated materials on top of BW2.

Once all bishops weed has been excavated from BW1 and dumped on BW2, move all tools and equipment used during this process to the BW2 location. Thoroughly clean tools and equipment by scraping off dirt, plant materials, and roots to the greatest extent practicable.

Materials cleaned from equipment shall be gathered and added to the BW2 location, including any that fell from equipment between BW1 and BW2 locations. With tools and equipment still at BW2 site, rinse off remaining organics and soil using a portable sprayer, backpack pump, or similar.

Tarp the BW2 site with 6 mil black plastic sized to allow 1’ min of tarp to lay flat against undisturbed ground on all sides of freshly deposited material. Securely anchor edges to prevent tarp from lifting and plant materials from being scattered by wind.

Do not remove Bishops Weed present outside the limits of excavation. Fill material may be allowed to cover unexcavated BW within limits of work.

14. The specs call for the swppp be prepared and stamped by a PE. We have swppp officers that write swppp's often, but they will not meet this requirement. Will this be a requirement for this contract.

The following are the current requirements per the 2021 State of Alaska Construction General Permit (Permit # AKR100000):

Total disturbed acreage for this project appears to be within the “1 to <5 acres” category.

15. 06.13.33-2.1A-2 Requires creosote treatment of all timbers for the dock work. Our lumber supplier is advising that creosote is no longer available as a treatment option. Please advise with alternative treatment requirements.

a. Pressure treated .60 ACZA timber finish will meet the requirement.

16. 03.04 - Dock - Main Decking - specifies the use of "non-slip timber decking" - I can't find a specification for this. Is this something other than an S4S deck board?

a. Pressure treated .60 ACZA timber finish will meet the requirement.

17. 03.06 Floatation Modules - What size floatation modules are required?

a. Flotation Modules are similar for both Main Dock and Finger Docks as being Styrofoam (20"x10.5") as depicted on provided dock drawings, "El Capitan Dock Drawings 20240411 ec", G-03 Cross Sections. The contractor is able to utilized a different size of float size so long as it meets a weight and buoyance and a submittal is provided.

18. 03.12 - Finger Dock - Is the replacement dock supposed to be in kind?

a. Finger Dock work items were included in Task Items 2.08-2.11 and can be reference on the SOI for Dock work identified under the element "Finger Dock" (attachment was added for Contractor's reference)

3 .,,.

/ 3 � :/,·

A�i;t:�o :i���� � (� � C l;f

2" DBH) AND APPROX �

5 SPRUCE (8-12" DBH)

I 3

REMOVE AND/OR LIMB -

TREES ALONG PROPOSED

TRAIL CORRIDOR 18 �

�-=-.L •

PROTECT APPR "L/ �

DBH SP 5

CUT AND REMOVE APPROX

15 ALDERS (8-16" DBH)

PROTECT TREES IN THIS

PRUCE AND HEML

0 25' ABOVE GROUN

PHASE II EL CAP

IMPROVEMENTS

OR TO ALLOW CLEAR

DAY-USE AREA TO WAT

X 20 ALDER (6-12" DBH)

RGROWTH (1-6" DBH). A

0 BE CUT FLUSH WI

PS LEFT IN PLACE. ----

O' 40' 80' I

120' w w w w w

DEMO KEY NOTES

DEMO EXISTING 10' HIGH WOOD POST

DEMO ABANDONED ELEC PANELS AND WOOD POSTS AND

ASSOCIATED BURIED UTILITIES (APPROX)

DEMO EXISTING ABANDONED UNDERGROUND UTILITIES AND

BURIED FACILITIES, SEE NOTES BELOW

DEMO CONCRETE SLAB

DEMO PICNIC TABLE AND FIRE RING

SIZE, CONDITION, AND CONTENTS OF TANKS ARE UNKNOWN

AND SHALL BE PUMPED (EMPTIED) IF WASTE OR OTHER

MATERIALS ARE PRESENT. FILL TANKS WITH APPROVED FILL

AND SEAL OPENINGS IN TANKS. DEMO BURIED SEPTIC

PIPING AND CLEANOUTS. LOCATIONS SHOWN ON PLANS ARE

APPROXIMATE.

DEMO WOOD LIGHT POLE AND ASSOCIATED BURIED

UTILITIES

REMOVE USFS FACILITY SIGN AND RETURN TO

GOVERNMENT

DEMO BISHOP'S WEED PLANTING AND 12" DEPTH OF SOIL

(APPROX) AND DISPOSE PER PROJECT SPECS.

REMOVE EXPOSED ABS PIPE. COORDINATE REMOVAL TO

PROTECT TREES.

DEMO ELEC HANDHOLE BOX AND ASSOCIATED BURIED

UTILITIES.

DEMO WOOD PANEL AND ELEC COMPONENTS AND

ASSOCIATED BURIED UTILITIES

DEMO (3) ABANDONED WOOD POWER POLES AND

ASSOCIATED OVERHEAD AND BURIED ABANDONED

ELECTRICAL UTLITIES. COORDINATE LIMITS OF DEMO OF

BURIED UTILITIES THROUGH AREAS WITH MATURE TREES

WITH COR.

DEMO METAL GATE WITH METAL SWING POST AND METAL

LOCK POST AND FOOTINGS.

DEMO TRASH CAN ENCLOSURE (APROX 4'x12'x6'). REFUSE

WITHIN IS PRESENT AND IS TO BE REMOVED.

DEMO TIMBER STAIRS (12 RISERS) AND TIMBER

BOARDWALKS (APPROX 8' LONG x 2' WIDE)

CUT ABANDONED OUTFLOW PIPE 10' BACK FROM POINT OF

DAYLIGHT. REMOVE ALL EXPOSED PIPE IN ITS ENTIRETY.

REMOVE 4" ABS PIPING ON OR OBVIOUSLY PRESENT JUST

BELOW SURFACE.

DEMO TIMBER BOX AND ASSOCIATED ABS PIPING.

RELOCATE BOULDERS TO ALLOW DRIVEWAY EXPANSION.

NOTES:

1. EXISTING BURIED ABANDONED UTILITIES INCLUDING

SEWER, ELECTRICAL, WATER, AND SEPTIC SYSTEMS

SHOWN ON PLANS ARE BASED ON 1995 LOGGING CAMP

AS-BUil T DRAWINGS AND ARE APPROX. ONLY.

LOCATIONS AND QUANTITIES OF THESE UTILITIES MAY

DIFFER FROM WHAT IS SHOWN ON PLANS. ADDITIONAL

ABANDONED BURIED UTILITIES MAY BE PRESENT THAT

ARE NOT SHOWN ON PLANS.

2. ALL DEBRIS AND FOREIGN MATERIALS LOCATED ON

THE GROUND OR WHICH ARE OBVIOUSLY PRESENT

JUST BELOW THE SURFACE ARE TO BE REMOVED

FROM WITHIN THE DEMOLITION AREA LIMIT AS SHOWN

ON DRAWING AND AS DIRECTED BY THE COR. NO

SPECIALIZED EQUIPMENT OR DEEP EXCAVATION IS

ANTICIPATED FOR REMOVAL.

3. ALL TREES TO BE REMOVED INCLUDE REMOVAL OF

STUMPS AND ROOT WADS, LION, OR DIRECTED BY COR.

4.

100% CONSTRUCTION DOCUMENTS

us

United States Department of Agriculture Forest Service

NO.

R10

ALASKA REGION

STAMPS, LOGOS, AND SEALS

__ ...... ,..._,,,\ ?�t9f !IHs:\'1 ,,__"?:-· *--�•1 "f-1. f .... 49:lli ·-.•�

� ::�: ::�t.t:.: � � �'11, •. Chnslopher R. Meril : � f'1t,'·. 02/09/2024 ---� .,�◊··.f'!o.1CJ449.·i�-

\\�\Vffs�s��i�1\lo�

Corporate License #1195

REVISION / ISSUE

PROJECT NAME

DATE

GAOAELCAP

RECREATION AREA:

CAMPGROUND &

DAY USE AREA

I MPROVEMENTS

TONGASS NATIONAL

FOREST

THORNE BAY RANGER DISTRICT

DRAWING TITLE

DEMOLITION

PLAN

DATE

ARCHIVE NO.

02/09/2024

DESIGNER

CORVUS DESIGN

DRAWN

BL

CHECKED

CM

PROJECT NO.

USF-22--01

DRAWING SHEET NO.

L7

SHEET 7 OF 28

L--------------------------------------------------------------------------------------

OPTION 1

WORK AREA:

*SEE NOTES

SEE DRAWINGS FOR

DOCK REPAIRS - REMOTE DOCK

5.

ALL DEMOLITION WORK ON THIS SHEET IS BASE BID.

*OPTION 1 WORK AREA NOTE: COMPLETE DEMOLITION

ACTVITIES WITHIN OPTION ITEM #1 WORK AREA AS

SHOWN IN DRAWINGS EXCEPT FOR REMOVAL OF:

TREES AND OTHER VEGETATION INCLUDING INVASIVE

PLANTS, BURIED UTILITIES OR FACILITIES, AND

EXISTING TIMBER STAIRS AND BOARDWALKS.

cljensen Polygon cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Line cljensen Polygonal Line cljensen Polygonal Line cljensen Typewritten Text

PHASE II EL CAP IMPROVEMENTS

COMPLETED; N.I.C.

cljensen Typewritten Text

BW1

cljensen Typewritten Text

BW2

File details come from the government source that posted it. Updated .