Amendment 1 - 1240BJ24Q0009.pdf

PDF 518 KB Posted

Attached to
Ship Cove Trail Restoration
Solicitation number
1240BJ24Q0009
Issued by

About this file

This document is Amendment 1 to Solicitation 1240BJ24Q0009 for the Ship Cove Trail Restoration project in the Tongass National Forest. The amendment provides additional site photos and extends the Period of Performance to July 31, 2025. The response due date has been extended to Friday, July 19, 2024, and all proposals must be emailed to Mai.Moua@usda.gov. The solicitation is issued by the USDA Forest Service and seeks contractor services for the restoration of the Ship Cove Trail. All previous terms and conditions remain unchanged, except as provided in this amendment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240BJ24Q0009

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40BJ

PORTLAND OR 97204-2829

STE 310

1220 SW 3RD AVE

USDA-FS CSA NORTHWEST 7

06/28/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/31/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Tongass National Forest - Sitka Ranger District

Ship Cove Trail Restoration

Amendment #1 - this amendment is to provide pictures of the sites, see "Site Pictures" file for details. This amendment also extends the Period of Performance to July 31, 2025.

The response due date has been extended to Friday, July 19, 2024. All proposals shall be emailed to Mai.Moua@usda.gov

All previous terms and conditions remain unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation No: 1240BJ24Q0009 Project Name: Ship Cove Trail Restoration, Tongass National Forest

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2) (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/Far/current/pdf/FAR.pdf

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within _15_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 31, 2024 July 31, 2025.

F.2 PROSECUTION OF WORK – WORK HOUR LIMITS – WORK ITEM LIMITS Work is to be performed Monday through Friday during daylight hours unless timing restrictions are specified. Work on Saturday will be permitted only with written permission of Forest Service. No work will be permitted on Sundays or Federal Holidays unless permitted in writing by the COR and/or

CO.

Construction activity shall be limited to the hours between 7:30 AM and 5:00 PM Monday through Friday, unless other hours are approved in writing by the Engineer. The Contractor shall conduct activities so that interference with the public shall be kept at a minimum. The project site shall be open to public access and free of hazards on weekends. Any activities requiring closure to the public shall be scheduled with the COR at least 7 days in advance.

The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.

AMENDMENT 0001

https://www.acquisition.gov/Far https://www.acquisition.gov/Far maimoua Cross-Out

File details come from the government source that posted it. Updated .