Final Amendment 01 Limber Jim AOP.pdf
PDF 197 KB Posted
- Attached to
- Limber Jim Aquatic Organism Passage
- Solicitation number
- 1240BJ22R0008
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is an amendment to a solicitation for a federal construction contract. The amendment provides clarifications and revisions to the solicitation for a project called Limber Jim Aquatic Organism Passage. Specifically, it allows the contractor to close a section of road for up to 12 days total to accommodate excavation and embankment work outside of the in-stream work window. It also replaces the existing public traffic control section with a new section establishing requirements for accommodating public traffic, installing temporary traffic control devices, and obtaining approval for temporary road closures. The solicitation number is 1240BJ22R0008 and is being issued by the Department of Agriculture Forest Service for a project located on the Limber Jim stream to provide aquatic organism passage.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
CONTRACT ID CODE PAGE 1 OF 2 PAGES
2 AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
04/14/2022
4. REQUISITION/PUCHASE REQ. NO. 5. PROJECT NO.(IF APPLICABLE)
6. ISSUE BY CODE 7.ADMINISTERED BY (if other than item 6) CODE
Procurement & Property Services, Field Procurement Operations Northwest Zone – Construction & A-E Attn: Bryce Kamerdula, CO 1550 Dewey Ave., Suite A Baker City, OR 97814
8.NAME AND ADDRESS OF CONTRACTOR(No., street, county, State and ZIP Code) 9A.Amend Solicitation. 1240BJ22R0002
* 9B.Dated 4/04/2022
* 10A.Mod Contract/Order #
* 10B.Dated (see Item 13) code facility code
11. THIS ITEM APPLIES ONLY TO AMENDMENT OF SOLICITATION
[x] The above numbered solicitation is amended as set forth in the item 14. The hour and date specified for receipt of Offers [ ] is extended [x ] is not extended. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted, or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegam or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. This change order is issued pursuant to; (specifiy authority)
The changes set forth in item 14 are made in the Contract/Order # in item 10A.
B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.) set forth in item 14, pursuant to the authority of FAR 43.103(b)..
C. This supplemental agreement is entered into pursuant to authority of:
D Other: (Specify type of modification and authority):
E. IMPORTANT: Contractor [ ] is not [ ] is required to sign this document and return _ Original to the issuing office.:
14. DESCRIPTION OF AMENDMENT/MODIFICATION
Project Name and Location: Limber Jim AOP This amendment addresses the following (Revisions) (PBI’s), or (RFI’s) (see attached addendum)
1. Revisions (REV 01) for Contract Bidding (see attached addendum)
By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A.NAME AND TITLE OF SIGNER (Type or print)
16A.NAME AND TITLE OF CONTRACTING OFFICER
Contracting Officer
15B.CONTRACTOR/OFFEROR
By ______________________________ (Signature of person authorized to sign)
15C.DATE SIGNED 16B.UNITED STATES OF AMERICA
By______________________________ (Signature of Contracting Officer)
16C.DATE SIGNED
Standard Form 30 Prescribed by GSA FAR (48CFR) 53.243
Addendum to Amendment 1
PROJECT CLARIFICATIONS FOR LIMBER JIM AOP
Revisions
REV-001
Option Item 3 NFSR 5125 Bypass Road:
Contractor may close NFSR 5125 from June 27th to July 1st, and July 29th through August 5th at the Limber Jim stream crossing. The purpose of these closures is to accommodate excavation and embankment work outside of the stream, such as bypass road embankment, water diversion channel, and existing culvert preliminary excavation, and related removal/restoration work outside of the in-stream work window.
The intent is to allow as much of the in-stream work window as possible to be directed towards in-stream work only. The Bypass Road for NFSR 5125 shall be passable to public traffic from July 1st through July 29th. Contractor shall place all appropriate signage and barricades to maintain public safety during the closures.
All in-stream work shall be completed between July 1st and July 31st.
(see attached specifications) Replaces existing specification for FSSS 156
Pre-Bid Inquiries (PBI’s) for Contract Bidding
None
Requests for Information (RFI’s) for Plans and Specifications
None
156 - Public Traffic 156.00_National_11_4_2016
Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Permanent Traffic Control 633
Traffic Signing and Marking Material 718
Concrete Barriers and Precast Guardwalls 618
Temporary plastic fence 710.11
Construction Requirements
156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic.
Delays may not exceed 30 minutes at any one time followed by an open period of no less than 5 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).
Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.
Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).
Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.
Table 156-1 Temporary Road Closures
Road Number
From Terminus To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
<number> <MP or description>
<MP or description> <number> <number>
5125 NFSR 5130 MP 3.0 30 N/A
5125* NFSR 5130 MP 3.0
June 27th to July 1st;
July 29th to August
5th. N/A
*If option item three, NFSR 5125 bypass road is awarded.
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.