This is Amendment 0001 to Solicitation 1240BH26Q0004 for the Sutton Boat Launch Replacement project on the Siuslaw National Forest in Lane County, Oregon. The amendment, effective April 14, 2026, clarifies requirements pertaining to dive operations and authorizes contractors to propose alternative methods for completing in-water work that do not require certified divers. When an alternative method is proposed, submission of a formal Dive Plan is not required; however, contractors must still identify all applicable safety measures and risk mitigation procedures. The amendment replaces Attachments 2, 3, and 4 in full.
The project involves replacing deteriorating concrete structures including a boat launch ramp, wood pier, gangway, concrete dock, and steel piles with cast-in-place and precast concrete segments, along with installation of a new floating dock, subsurface drainage system, and riprap placement. The estimated project value ranges from $500,000 to $750,000. Quotations must be submitted via email to susie.felton@usda.gov by the solicitation deadline, with a 90-calendar-day price hold requirement. All quoters must provide a signed Standard Form 1442, completed Schedule of Items (Attachment 2), a technical response limited to six pages addressing project experience and technical approach, a scanned bid guarantee, and acknowledgment of amendments. Award will be made to the highest technically rated quoter with fair and reasonable pricing and acceptable or neutral past performance. Questions are due by April 17, 2026, and the estimated project start date is June 1, 2026, with completion by October 1, 2026. A post-award conference will be held within 15 business days of contract award via Microsoft Teams. Performance and Payment Bonds (100% each) are required for awards exceeding $150,000, and a Bid Bond (20%) is required for offers exceeding $150,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Portfolio A - Solicitation Documents (1-4).pdf | ||
| Portfolio B - Supporting Documents (5-20).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240BH26Q0004
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40BH
PORTLAND OR 97204-2829
STE 310
1220 SW 3RD AVE
USDA-FS CSA NORTHWEST 6
04/14/20260001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/23/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Sutton Boat Launch Replacement on Sutton Lake - Siuslaw National Forest(Central Coast
Ranger District, Lane County, Oregon)
The purpose of this amendment is to clarify requirements pertaining to dive operations and to authorize the use of an alternative method for performing in water work that does not require certified divers. When an alternative method is proposed, submission of a Formal
Dive Plan is not required; however, contractors must still identify all applicable safety measures and risk mitigation procedures associated with their proposed in water work approach.
This amendment revises the following:
1. Attachment 2 Schedule of Items
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
DARCY J. RAPOZA
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
x 1
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1240BH26Q0004/0001
2. Attachment 3 Solicitation Details &
Requirements
3. Attachment 4 Instructions and Evaluation
Criteria
Attachments 2, 3 and 4 are replaced in full.
Except as modified by this amendment, all other terms and conditions of the solicitation remain unchanged.
Period of Performance: 06/01/2026 to 10/01/2026
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Sutton Boat Launch Replacement Attachment 2 – Schedule of Items Solicitation: 1240BH26Q0004
SCHEDULE OF ITEMS
Siuslaw National Forest
Central Coast Ranger District (Lane County, Oregon)
CLIN Supplies/Services Measurement Qty. Unit Price Total Price Method Unit
0001 Mobilization LSQ LS ALL N/A $
0002 Materials Testing & Monitoring LSQ LS ALL N/A $
0003 Project Layout & Survey Verification LSQ LS ALL N/A $
0004 Erosion Control LSQ LS ALL N/A $
0005 Floating Silt Curtain AQ LF 160 $ $
Existing Structures Removal & Disposal LSQ LS ALL N/A $
0007 Unclassified Excavation DQ CY 475 $ $
Over Excavation and Subgrade Stabilization AQ CY* 48 $ $
0009 Geotextile - Subbase Uplands AQ SQF 720 $ $
0010 Geotextile – Subbase In-Water AQ SQF 1125 $ $
0011 Geotextile - Riprap AQ SQF 2628 $ $
0012 Aggregate Base - Open Graded DQ CY 140 $ $
0013 Aggregate Base - Dense Graded DQ CY 70 $ $
0014 Riprap - Class 700 DQ CY 155 $ $
0015 Dive Team LSQ LS 1 N/A $
0016 Steel Rail System AQ SQF 1066 $ $
0017 Precast Planks AQ SQF 1066 $ $
0018 Cast-In-Place Concrete Launch Ramp AQ SQF 358 $ $
0019 Concrete Dock Abutment AQ SQF 130 $ $
0020 Traffic Delineators AQ EA 1 $ $
0021 Aluminum Boarding Docks AQ EA 3 $ $
0022 12" Steel Piles AQ EA 2 $ $
0023 Trench Drain AQ LF 24 $ $
0024 6-Inch Storm Drain Piping AQ LF 20 $ $
Sutton Boat Launch Replacement Attachment 2 – Schedule of Items
Item(s) denoted with * will only be paid if required to be used.
SCHEDULE NOTES
1. Payment will be made on actual work performed as described in the Schedule of Items.
Contractors should include all labor, materials, and supplies needed to perform the work described under its corresponding unit price.
2. Payment for bond premiums in accordance with AGAR 452.232-71, Progress Payments for Commercial Construction Contracts, shall not be in addition to the contract price.
3. A Bid Bond (20%) will be required of offer whose total price exceeds $150,000.
4. Performance and Payment Bonds (100% each) will be required for all individual awards that exceed $150,000.
5. Contractors proposing an alternative to dive operations as listed in this solicitation are not required to price CLIN 0015 – Dive Team. Enter a value of $0.00 if the alternate method without certified divers is proposed. (see Attachment 3 and 4)
NOTE: System for Award Management (SAM), an Offeror is required to be registered in SAM when submitting an offer and at time of award, and shall continue to be registered during performance, and through final payment. Information on registration may be obtained via: https://www.sam.gov. All Offerors must complete the electronic version of the Representations and Certifications in the SAM system.
Please provide the following information:
Vendor UEI Number: _________________________
Vendor Email: _______________________________
0025 Catch Basin AQ EA 1 $ $
0026 Portland Cement Concrete Pavement AQ SQF 250 $ $
0027 Installation of Signs LSQ LS 2 N/A $
TOTAL PRICE $
https://www.sam.gov/
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
SOLICITATION DETAILS AND REQUIREMENTS
SCOPE OF CONTRACT
Project consists of replacing a deteriorating concrete boat launch ramp, wood pier, wood gangway, concrete dock, and steel piles with a combination of cast-in-place concrete and pre-cast concrete segments. A new floating dock will be constructed adjacent to the new ramp. Steel piles driven into the ground underwater will anchor the floating dock and the dock segments will be assembled onsite from parts. A new subsurface drainage system will catch the parking lot runoff and drain to the lake after passing through a catch basin. New rip rap will be placed around the new construction. Contractors shall include a narrative of their proposed Dive Operations Plan with their offer. (See Attachment 10 - Checklist for Commercial Diving Operations)
Note: Contractors may propose an alternative method for completing required in-water work without certified divers. If an alternative method is proposed, see Attachment 4 – Instructions and Evaluation Criteria for additional information and requirements.
PROJECT LOCATION
The project is located on the Siuslaw National Forest. From the Central Coast Ranger Station in Waldport, Oregon, drive south on US-101 for 27.4 miles. Turn left into Sutton Boat Launch Recreation Site.
[44.05392, -124.09705] Sutton Lake, Lane County, Oregon.
MAGNITUDE OF CONSTRUCTION PROJECT
The aggregate magnitude of construction for all items is between $500,000 and $750,000.
TECHNICAL SPECIFICATIONS
The attached Supplemental Specifications apply. All specifications not included in the specification listing, but referenced by listed specifications, are applicable and will be incorporated into the awarded contact.
The contractor is required to adhere to all the terms and conditions in the attached documents.
FOREST SERVICE HANDBOOK 4209.11 – WILDLIFE, FISH, WATER, AND AIR
RESEARCH HANDBOOK
https://www.usda.gov/guidance-documents/diving-and-snorkeling-safe-practices/fs/forest-service-handbook-420911- 10-wildlife-fish-water-and-air-research
Chapter 10 – Diving and Snorkeling Safe Practices The Forest Service Diving Program is designed to ensure that all diving under the auspices of the Forest Service is conducted in a manner that maximizes protection of divers from accidental injury, illness, or death. Contractor will need to provide contract diving operations per Part 16 https://www.usda.gov/guidance-documents/diving-and-snorkeling-safe-practices/fs/forest-service-handbook-420911-10-wildlife-fish-water-and-air-research https://www.usda.gov/guidance-documents/diving-and-snorkeling-safe-practices/fs/forest-service-handbook-420911-10-wildlife-fish-water-and-air-research
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
16 - CONTRACT DIVING OPERATIONS
16.1 - General
1. Contractors shall demonstrate compliance with OSHA requirements of 29 CFR part 1910, Subpart T or 29 CFR part 1910, Subpart T, Appendix B.
2. Contracting officers or contracting officer representatives shall have a working knowledge of OSHA requirements of 29 CFR part 1910, Subpart T and 29 CFR part 1910, Subpart T, Appendix B to monitor contract diving operations or consult with the Regional Dive Safety Officer.
3. Any failure to comply with the requirements of Section 11 will be cause of suspension or termination of the contract.
16.2 - Dive Operations Plans
1. Dive operation plans must be developed and implemented by the contractor for each separate diving operation. As a minimum, the plan must contain the following:
a. Names and duties of diving team members, including diving supervisor.
b. Date, time, and diving location of the diving operation.
c. Safety procedures for contract.
d. Emergency management plan, including emergency procedures, means of notification, telephone numbers (for ambulance, doctors, and recompression chambers), and location of evacuation routes, nearest U.S. Coast Guard rescue center, and emergency assistance.
e. Diving mode to be used (for example, SCUBA or surface supplied air), giving a description of the backup air supply.
f. Nature of work to be performed by the divers and requirements for inspection.
g. Surface and underwater conditions, including visibility, temperature, thermal protection, and currents.
h. Maximum depth and bottom time (altitude adjustments to dive tables must be accomplished for dives made at altitudes of 1,000 feet (300 meters) or more above sea level).
i. Lockout/tag out procedures, including procedures for dealing with differential water pressures due to unequal water elevations (when applicable).
j. Equipment certification, procedures, and checklists and requirements for special tools and equipment.
k. The statement, if for any reason the dive operations plan is altered in mission, depth, personnel, or equipment, the contracting officer shall be contacted and shall review any revision prior to actual operation.
2. The dive operation plans must be submitted to the unit dive safety officer prior to commencement of diving operations and must conform with OSHA Commercial diving standards.
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
3. A copy of the diving operation plan must be at the diving location whenever diving is conducted.
4. The dive operation plans must be made available to the government contracting officer.
NOTE: Plan should include list the years of experience, skills, and licensing of personnel to be used on the project in accordance with OSHA requirements of 29 CFR part 1910, Subpart T or 29 CFR part 1910, Subpart T, Appendix B. OSHA 29 CFR Part 1910 Subpart T.
https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910SubpartT
16.3 - Pre-Dive Conferences and Briefings A pre-dive conference must be held on site with the lead diver under this contract and designated contractor representative with sufficient authority to implement any requirements made by the government contracting officer.
16.4 - Recordkeeping and Reporting Requirements The contractor shall submit two copies of all dive operations plans, dive logs, and diving related accident reports to the contracting officer and contracting officer representative for inclusion in the contract file. The contracting officer submits a copy to the unit dive safety officer.
CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground.
"Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances. Designs were completed by the Oregon State Marine Board.
INSPECTION AND ACCEPTANCE
1. The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the completed work performed under this contract.
2. Inspection and acceptance will be performed at the project locations.
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
The Contractor shall be required to commence work under this contract within 15_ calendar days after the date the Contractor receives the notice to proceed, prosecute the work diligently, and complete the entire work ready for use not later than as noted below (the time stated for completion shall include final cleanup of the premises.
Estimated Start Date is on or before: June 1, 2026
POST AWARD CONFERENCE
A post award conference with the successful offeror is required. It will be scheduled and held within approximately (15) business days after the date of contract award. The conference will be https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-T?toc=1 https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910SubpartT
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements held online through Microsoft Teams.
SITE VISIT
1. No formal site visit is planned. See attached project maps for Project Locations.
2. Contractors are encouraged to visit project location prior to providing offer.
3. The Government assumes no responsibility for any expense incurred by an offeror prior to contract award.
SPECIAL CONTRACT REQUIREMENTS
GUIDELINES FOR SUBMITTALS
Submittals are required by their corresponding specifications (basic reference & detailed requirement). Work covered on requiring submittals shall not begin until submittals have been approved.
Submittals shall include the following unless otherwise required in the specification:
1. Date and revision dates.
2. Project name and contact number.
3. Names of contractor, subcontractor, supplier, and manufacturer.
4. Specifications section number.
5. Field dimensions and relation to adjacent structures.
6. Applicable standards such as ASTM or Federal Specifications.
7. Contractor’s stamp, initial, or signature, certifying the review of submittal, verification of field measurements, and compliance with contract documents.
Contractor shall provide submittal schedule within 14 days after the notice to proceed unless otherwise required by the specification.
Manufacturer's requirements:
Supply manufacturer's catalog sheets or brochures with diagrams, schedules, or performance charts. Illustrations shall be clearly marked to identify pertinent materials or models, dimensions, and clearances required. Supplement standard drawings to provide information unique to this project.
Approval or Rejection Time Allowance:
Submittals will be reviewed and either approved or rejected after their receipt by the Contracting Officer and COR based on tables listed below.
PRODUCT SAMPLES AND SUBMITTALS
Title Referenced by Contract clause or Specification No.
Time of Government
Approval Project Specific Construction Schedule FAR 52.236-15 7 days
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
Dive Operations Plan FSH 4209.11 14 days Erosion Control Plan FSS 01560.10 14 days Fire Prevention and Suppression Plan FAR 52.236-9 14 days Project Specific Safety/Accident Prevention Plan FAR 52.236-13 7 days
Product Data Aggregate Base Material/ FSS 02200.20 14 days Product Data Geotextile Fabrics FSS 02200.20 14 days Product Data Riprap FSS 02200.20 14 days Product Data Erosion Control (A-E) FSS 01560.20 14 days Product Data Driven Steel Piles (A-F) FSS 02362.20 14 days Product Data Pipe and Fittings FSS 02720.20 14 days Trench Backfill Material FSS 02720.30 14 days Trench Drain & Grating FSS 02720.40 14 days Product Data Reinforcement FSS 03412.60 14 days Product Data Dock Material FSS 05150.50 (c) 14 days Product Warranties FSS 05150.91 14 days Product Data Traffic Delineators FSS 10110.60 14 days
MATERIAL CERTIFICATIONS, DESIGN/SHOP DRAWINGS, AND TESTING REPORTS
Title Referenced by Contract clause or Specification No.
Time of Government
Approval Material Certification Straw Bales FSS 01560.20 (c) 14 days Narrative and Illustrations Installation Plan FSS 02362.20 14 days Quality Assurance Test Report FSS 02362.30 14 days Welding Procedures & Welder Qualifications FSS 05150.50 (e) 14 days Inspection and Quality Control Reports and Results FSS 05000.30 3 days
Diver and Experience Certifications FSS 05150.50 (a) 14 days Material Source Certifications FSS 05150.50 (a) 14 days Manufacturer’s Instructions FSS 05150.50 (f) 14 days Inspections: Manufacturing Schedule FSS 05150.50 (g) 14 days Test Reports and Certificates of Compliance FSS 05150.50 (d) 14 days Compaction Test Reports FSS 02720.70 14 days Quality Control Testing FSS 03300.70 14 days Certification and Testing of Concrete FSS 03300.75, 03412.81 14 days Shop Drawings Structural Precast Concrete Planks – if different from drawings & specs FSS 03412.20 10 days
Concrete Mix Design FSS 03300.30 14 days Concrete Mix Design – Concrete Planks FSS 03412.55 10 days Shop Drawings Metal Fabrication FSS 05000.20 14 days Shop Drawings Dock FSS 05150.50 (b) 20 days Shop Drawings Traffic Signs FSS 10110.10 14 days Shop Drawings Concrete Wheel Stops FSS 10110.10 14 days Material Certification FSS 01305.10; FAR 52.225-1 14 days
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
GOVERNMENT QUALITY ASSURANCE
Quality assurance will be performed by the Government during the contract at regular intervals.
Methods may include visual survey and review of Contractor quality control documents.
USE OF PREMISES
1. Before any camp, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. Contractor may request permission from the CO to establish a camp at the Sutton Boat Launch Ramp parking lot;
no other facilities are provided. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
2. Unless excepted elsewhere in the contract, the Contractor shall provide and maintain sanitation facilities for the work force at the site and dispose of solid waste in accordance with applicable Federal, State and local regulations.
3. Construction activity shall be limited to the hours between 7:00 a.m. and 6:00 pm.
Monday through Friday, unless other hours are approved in writing by the CO and no work will be permitted on Federal Holidays.
PHYSICAL DATA
1. Data and information furnished or referred to below are for the Contractor's information.
The Government shall not be responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor.
2. The indications of physical conditions on the drawings and in the specifications are the result of surveys and site investigations by FS Personnel and the Oregon Marine Board.
Weather conditions are available at www.noaa.gov.
Normal Work Season: June 1st through October 31st.
Normal Fire Season: June 1st through October 31st.
3. Use of Roads: The Contractor is authorized to use all roads under the jurisdiction of the Forest Service that are open and necessary for direct route access to contract work sites for all activities necessary to complete this contract.
4. Sanitary Facilities: Sanitary facilities are available (Vault Toilet) for use during construction. Potable and non-potable water is not available on site.
5. Utilities: Electricity is not available on site.
6. Trash and Refuse: Contractor shall remove all of his own trash and refuse from the contract area.
ARCHAEOLOGICAL OR HISTORIC SITES
If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.
http://www.noaa.gov/
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION
1. Operations shall be scheduled and conducted to minimize erosion of soil and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments of (e.g.
lakes, reservoirs).
2. Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
3. Mechanized equipment shall not be operated in streams, lakes, or other bodies of water without written approval by the Contracting Officer.
CONTROL OF INVASIVES
See the attached Invasive Species Management Protocols including but not limited to Relevant decontamination procedures in Special Protocols subsections Boats and other large aquatic conveyances, Heavy equipment when used in aquatic environments and Diving equipment. (See Attachment 8)
SPECIAL EQUIPMENT CLEANING REQUIREMENTS
All earth moving equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands. Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose.
Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands. The Contractor shall advise of a proposed date for mobilization. Inspections will take place at mutually agreeable en-route locations in advance of entry onto National Forest lands.
Special care shall be taken to ensure removal of the following noxious weeds and their seeds:
Black henbane (Hyoscyamnus niger) Mediterranean sage (Salvia aethiopis) Myrtle spurge (Euphorbia myrsinites) Russian knapweed (Acroptilon repens) Yellow flag iris (Iris pseudacorus) Yellow star-thistle (Centaurea solstitialis) Diffuse knapweed (Centaurea diffusa) Houndstongue (Cynoglossum officinale) Leafy spurge (Euphorbia esula) Meadow knapweed (Centaurea jacea) Musk thistle (Carduus nutans) Perennial pepperweed (Lepidium latifolium) Scotch thistle (Onopordum acanthium) Spotted knapweed (Centaurea stoebe ssp. Micranthos) Sulphur cinquefoil (Potentilla recta) Whitetop (Cardaria (Lepidium) draba) Bull thistle (Cirsium vulgare) Canada thistle (Cirsium arvense) Dalmatian toadflax (Linaria dalmatica) Yellow toadflax (Linaria vulgaris) Squarrose knapweed (Centaurea virgata ssp.
Squarrosa)
Lenspot whitetop (Cardaria (Lepidium) chalapensis)
Common st. johnswort (Hypericum perforatum)
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements
The Contractor shall exercise all necessary precautions to ensure that no petroleum products, residues, or related contaminants from mechanical equipment enter any waterbody at the project site. This requirement includes, but is not limited to, performing daily inspections of equipment and conducting cleaning activities as appropriate to prevent contamination.
NOTE: Due to the presence and risk of highly invasive species, including New Zealand Mudsnails, Chinese Mitten Crabs, and Chinese Mystery Snails, the Contractor shall thoroughly clean and decontaminate all equipment prior to entering and leaving the construction site, and before the equipment is moved to any other body of water.
HAZARDOUS CONDITIONS SAFETY PLAN
The following conditions have been identified as inherently hazardous to the degree that failure to take the proper precautions could lead to severe injury or loss of life. This listing shall not be construed as all inclusive. The Contractor shall provide a written job-specific hazard analysis and safety plan that addresses and conforms to the requirements of 29 CFR 1910 and 1926 and the clause entitled Accident Prevention (FAR 52.236-13) included herein. The Contractor shall take appropriate actions to implement this plan during performance and to take any and all other necessary steps to mitigate the dangers from hazards.
The following activities have been identified by the Government as potential safety hazards.
☒ Limited visibility ☒ Drowning ☒ Entanglement hazards ☒ Boat traffic ☒ Marine life ☒ Crush hazards ☒ Confined space ☒ Electrical hazards ☒ Fire hazards ☒ Heavy equipment operation ☒ Hydraulic and/or pneumatic and/or other high-pressure hazards ☒ Mechanical hazards such as pulleys, springs etc.
☒ Temporary excavation / deep trenching / slope stability ☐ Traffic control on high-volume and/or high-speed and/or limited visibility roads ☒ Other standard diving hazards
PAYMENT FOR MATERIALS DELIVERED OFF THE SITE
As provided in AGAR 452.232-71, Progress Payments for Commercial Construction Contracts, material acquired for incorporation into the project, and stored off site by the Contractor, may, at the option of the Contracting Officer, be included in progress payments. Prior to payment, such material will be subject to Government inspection and must be stored separately from other materials, and be identified as, "PROPERTY OF THE UNITED STATES, Project Name and Contract Number." In addition, the Contractor shall furnish the Government with a right of ingress
Sutton Boat Launch Replacement Attachment 3 – Solicitation Details & Requirements and egress the property together with right of removal.
RETURN OF PERFORMANCE AND PAYMENT BONDS
Performance and payment security furnished under this contract must be retained by the Government for a minimum of one year after acceptance of all work under the contract.
Performance and payment security other than corporate or individual surety bonds will be returned to the Contractor one year after completion of work if no claims against these bonds have been filed at that time.
PAYMENT FOR PERFORMANCE AND PAYMENT SECURITY EXPENSES
It is mutually agreed that the premium costs for performance bonds, payment bonds and alternative payment protections furnished for this contract are included in the total amount bid for other items and that any payment to the Contractor for the cost of bonds made in accordance with FAR 52.232-5 refers only to corporate sureties listed in the current Department of Treasury Circular 570 and no advance payment will be made for bond premiums where other than corporate surety bonds are furnished. Bond premiums as used in this paragraph and FAR 52.232-5 shall include any Small Business Administration fees paid in connection with SBA guaranteed corporate surety bonds.
PUBLIC OFFICIALS NOT PERSONALLY LIABLE
There shall be no personal liability upon the Government or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.
Sutton Boat Launch Replacement Attachment 4 – Instructions and Evaluation Criteria Solicitation No.: 1240BH26Q0004
INSTRUCTION AND EVALUATION CRITIERA
52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov 2025)
FAR 52.212-1 is amended as follows:
Period for acceptance of quotes.
The Quoter agrees to hold the prices in its quote firm for 90 calendar days from the date specified for receipt of quotes.
All submissions shall be emailed as noted below (i.e. no hand carry/USPS/FedEx):
Subject Line: 1240BH26Q0004 Sutton Boat Launch Replacement Email: susie.felton@usda.gov Submit the following documents with your response, no hard-copy originals are required.
1. Signed Standard Form 1442, Solicitation/Offer/Award (Construction, Alteration, Repair), with blocks 14 – 20c completed by the quoter.
2. Attachment 2 – Schedule of Items.
3. Technical Response to Evaluation Criteria
4. Scanned copy of fully executed Bid Guarantee (Standard Form 24 and Power of Attorney).
5. Acknowledgement of solicitation amendments (if any) via signed SF-30(s) with your quote.
Each of the parts should be separate and complete so that evaluation of one may be accomplished independently from evaluation of the other. All documents shall be Microsoft Word or Adobe PDF.
All Quotes should be submitted in the following format:
• 1 Copy of the completed technical response.
• 1 Copy of the completed Schedule of Items.
Questions Questions shall be submitted via email to Susie.felon@usda.gov and are due no later than 17 April 2026, by COB (1630) Pacific Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.
EVALUATION CRITERIA
The provision at FAR 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the quoter with the highest technically rated quotation with fair and reasonable pricing and acceptable or neutral past performance.
TECHNICAL APPROACH
The technical approach will evaluate the ability of the quoter to provide a sound, compliant approach that meets all requirements and shows a thorough understanding of them. It is the contractor's responsibility to ensure their quotation clearly demonstrates their capability to meet these requirements. All quoters must provide the following minimum information and documentation mailto:susie.felton@usda.gov mailto:Susie.felon@usda.gov
Sutton Boat Launch Replacement Attachment 4 – Instructions and Evaluation Criteria with their quotations to be considered acceptable and have their quotes evaluated. The Technical Approach is limited to (6) six pages. Attachment 18 (Past Performance Form) is excluded from this page limit.
1. Similar Project Experience: Submit a short narrative providing details of relevant experience the firm has (either as a prime or sub-contractor) for work similar in scope, nature and complexity to this requirement.
2. Technical Requirements The narrative shall address the following:
Work Sequence and Approach
• Provide anticipated work sequence with key milestones, identifying scheduling risks and workarounds. Narrative should demonstrate the contractor’s Project Management and Quality Control strategy and ability to meet the Period of Performance.
Equipment and Subcontractors
• Equipment to be used and its purpose
• Subcontractors and their roles
Note: Quoters have the option to either:
Provide a Dive Operations Overview as described in this section, or Propose an alternative method that does not require the use of certified divers. Regardless of the method proposed, all quoters must demonstrate a safe, compliant, and feasible approach for completing required in-water work.
Dive Operations Overview Quoters are not required to submit a full Dive Operations Plan with the technical submission.
Instead, provide a brief overview that includes:
• General approach for conducting dive operations
• Expected types of diving activities
• Major dive equipment anticipated
Alternative to Dive Team Operations If the quoter chooses not to use certified divers, the technical narrative must clearly explain:
• How all in-water work will be completed without certified divers
• The equipment and methods to be used
• Safety measures and controls specific to in-water work
• How the proposed approach will meet project requirements and maintain environmental and personnel safety
• Any limitations, risks, or constraints associated with the non-diver approach and how those will be mitigated
Sutton Boat Launch Replacement Attachment 4 – Instructions and Evaluation Criteria
PAST PERFORMANCE
Submit a list of relevant prior work the contractor has performed within the past six (6) years along with contact information so the government may contact prior customers to evaluate past performance. If you will be utilizing subcontractor(s), provide the same information as noted above.
Information should include the project name, location, description of the work, dollar value and name/phone/email of project owner representative. Attachment 18 to this solicitation is a Past Performance Form that is optional for use.
The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System (CPARS) to determine if the Contractor has acceptable or neutral Past Performance. Past Performance will be evaluated using the following rating system:
Acceptable: The contractor shows a demonstrated ability to meet contract requirements in prior or current contracts, including quality of work, timeliness, cost control, business relations, and adherence to contract terms.
Neutral: Quoter does not have a past performance record.
Unacceptable: The contractor has a documented history of failing to meet contract requirements, including poor quality, missed deadlines, cost overruns, lack of responsiveness, or unethical behavior.
PRICE
Submit a completed Attachment 2 – Schedule of Items with all items priced. Please double check math to make sure the total for each line item is calculated correctly and the sum of all line items is equal to the total price. The offeror’s quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.
EVALUATION METHOD:
All quotations will be evaluated to identify the quoter presenting the most technically advantageous solution based on the stated evaluation criteria. Once the highest technically rated quoter is identified, their price will be evaluated to determine whether it is fair and reasonable. Past performance will also be assessed to ensure it is acceptable or neutral.
Award will be made to the quoter whose quote is determined to be the highest technically rated, provided that:
1. Past performance is assessed as acceptable or neutral, and
2. The proposed price is fair and reasonable.
Award will not necessarily be made to the lowest-priced quoter. Tradeoffs will not be conducted.
| Att 2. Schedule_of_Items.pdf |
| SCHEDULE OF ITEMS |
| SCHEDULE NOTES |
| Att 3. Solicitation_Details_Requirements.pdf |
| SOLICITATION DETAILS AND REQUIREMENTS |
| SCOPE OF CONTRACT |
| PROJECT LOCATION |
| MAGNITUDE OF CONSTRUCTION PROJECT |
| TECHNICAL SPECIFICATIONS |
| FOREST SERVICE HANDBOOK 4209.11 – WILDLIFE, FISH, WATER, AND AIR RESEARCH HANDBOOK https://www.usda.gov/guidance-documents/diving-and-snorkeling-safe-practices/fs/forest-service-handbook-420911-10-wildlife-fish-water-and-air-research |
| 16 - CONTRACT DIVING OPERATIONS |
| CONFORMITY WITH DRAWINGS AND SPECIFICATIONS |
| INSPECTION AND ACCEPTANCE |
| COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK |
| POST AWARD CONFERENCE |
| SITE VISIT |
| SPECIAL CONTRACT REQUIREMENTS |
| GUIDELINES FOR SUBMITTALS |
| PRODUCT SAMPLES AND SUBMITTALS |
| MATERIAL CERTIFICATIONS, DESIGN/SHOP DRAWINGS, AND TESTING REPORTS |
| GOVERNMENT QUALITY ASSURANCE |
| USE OF PREMISES |
| PHYSICAL DATA |
| ARCHAEOLOGICAL OR HISTORIC SITES |
| CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION |
| CONTROL OF INVASIVES |
| SPECIAL EQUIPMENT CLEANING REQUIREMENTS |
| PAYMENT FOR MATERIALS DELIVERED OFF THE SITE |
| RETURN OF PERFORMANCE AND PAYMENT BONDS |
| PAYMENT FOR PERFORMANCE AND PAYMENT SECURITY EXPENSES |
| PUBLIC OFFICIALS NOT PERSONALLY LIABLE |
| Att 4. Instructions_and_Evaluation_Criteria.pdf |
| INSTRUCTION AND EVALUATION CRITIERA |
| Questions shall be submitted via email to Susie.felon@usda.gov and are due no later than 17 April 2026, by COB (1630) Pacific Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name a... |
| TECHNICAL APPROACH |
| PAST PERFORMANCE |
| PRICE |
| EVALUATION METHOD: |