1240BH24Q0050 Crescent Sidewalk Repairs SOI Revised.pdf

PDF 194 KB Posted

Attached to
Deschutes NF Crescent Sidewalk Repairs
Solicitation number
1240BH24Q0050
Issued by

About this file

This document is a Solicitation for a firm fixed-price contract for the Crescent Sidewalk Repairs project at the Crescent Ranger Station in Oregon. The project involves replacing 500 linear feet of sidewalk curbs, repairing 9 concrete columns, and removing and replacing 316 square feet of concrete under a gate. The period of performance is 60 calendar days, estimated to begin on 09/03/2024. The magnitude of the construction project is between $25,000 and $100,000. Payment bonds (100%) will be required. Offerors must be registered in the System for Award Management (SAM) to submit a proposal. The solicitation is being issued by the USDA Forest Service.

View the file

Other files

File Type Posted
Amendment 2.pdf PDF
1240BH24Q0050 Amendment 2 SF30.pdf PDF
Attachment For Amendment 0001 Crescent Sidewalk Repair.docx DOCX document
1240BH24Q0050 SF 30.pdf PDF
1240BH24Q0050 Crescent Sidewalk Repairs RFQ.pdf PDF
Attachments.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No: 1240BH24Q0050 Project Name: Crescent Sidewalk Repairs

FAC 2024-05 May 22, 2024

FAC 2024-

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS REVISED

Item Description Quantity Unit Unit Price Total Price

0001 Base Item: Concrete Curb repair 1(Approx 500

LF)

LS $ $

Option 1: Columns

1001 Column End Cap Replacement (No light poles)

1(Approx 9 columns)

LS $ $

1002 Column Repair (Light Poles) 1(Approx 4 columns)

LS $ $

Total Option Item 1 $

2001 Option 2: Below Gate Concrete Removal & Replacement

1(Approx

316 SF

plus, the 1Thickness of the pour)

LS

Grand Total

B.2 SCHEDULE NOTES

Project Notes:

1. See attached Project Description

2. Payment bonds required for awards over $35,000.

3. All work shall be completed in 60 days. Work is estimated to begin 09/01/2024.

4. Mark all areas to be repaired and coordinate work with COR.

5. All quantities are listed as reference/estimates only to help prospective bidders determine the scope of work. Contractors are strongly encouraged to visit the site to verify the scope of work prior to bidding. All payments shall be made in Lump Sum quantity.

All work in this SOW not included in these pay items shall be considered incidental, including mobilization.