This document provides an amendment to a solicitation for the Lamonta Historical Structures Restoration project. The Forest Service will remove external electrical and plumbing fixtures and provide storage areas for the awarded contractor. Lead-based paint is assumed to be present and all new wood materials must be primed on all sides as specified. The agency will replace an HVAC unit and remove vehicles and equipment from building exteriors prior to work commencing. The pre-proposal meeting addressed questions on site visits, garage door rebuilding, window restoration, and travel expenses, which fall under mobilization. The glazing pay item scope of work was also clarified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment2.pdf | ||
| CompleteSolicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240BH21R0023
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40BH
PORTLAND OR 97204-2829
STE 310
1220 SW 3RD AVE
USDA-FS CSA NORTHWEST 6
05/25/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/11/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The attached notes from the planned site visit are provided, for information.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
DARCY J. RAPOZA
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Summary of Lamonta Historic Structures Project Pre-Proposal Meeting
Meeting Date: 05/19/21 10:00 AM – 11:00 AM
Meeting Location: At project site, Lamonta Compound, Prineville Oregon
Attendance: Forest Service: Mike Krawczyk, Dale Beshara, Ellten Davis, Bryan Kurtz
Contractors: Axiom Construction, Richards Remodeling, Cedar Mill Construction
GENERAL DISCUSSIONS
- External Electrical and Plumbing Fixtures:
The Forest service will remove external electrical and plumbing fixtures from the exterior of buildings prior to commencement of work by the contractor.
- Is lead based paint present on the exterior of buildings included in this project?
o Answer: It is assumed that lead based paint is present under the current top paint coat on all the buildings. A test was conducted on exposed underlying paint layers, on building 2101, and the test confirmed the presence of lead.
- All 4 sides of new boards, including siding, trim, and others, shall be primed, and treated as specified in contract documents.
- If material substitution requests or unexpected conditions encountered require SHPO (Historic Structure) approval; it should be assumed that the approval process will take several weeks.
- Where possible, and as approved by the Forest Service; Existing siding boards shall be repaired in lieu of replacement.
- A mini-split HVAC unit will be installed on building 2101, near the NW corner of the building prior to commencement of work on the building.
- Work and storage areas for the awarded contractor: The Forest service will provide material and equipment storage locations within the secure fenced area of the Lamonta compound. The Forest Service will work with the contractor to provide adequate space based on their plan of operation. Existing vehicles, equipment, and materials will be removed from the exterior of buildings prior to the Contractor’s commencement of work on individual buildings. Adequate clear space will be created to allow the contractor access to the work areas.
SPECIFIC QUESTIONS
- Is an in-person site visit required for potential Contractor’s to be eligible to bid on this project?
o Answer: No, not a requirement per Solicitation, but highly advised.
- Is the overhead garage door on the South wall of building 2101 to be rebuilt or replaced?
o Answer: The door shall be rebuilt as specified in the drawings, specifications, and other contract documents.
- Building 2105: Are the existing boarded-up windows to be restored to glass windows?
o Answer: Yes, at the quantity and as specified in contract documents.
- What Bid Item would travel expense fall under?
o Travel Expense will fall in Mobilization.
- What work is included in the glazing pay item?
Per Specification Section 01 01 01 Definition of Bid Items
WINDOW GLAZING – SUB ITEM 08800
1. Inspect and identify all windows or parts of windows requiring reglazing
2. Prepare for glazing
3. Replacement broken or cracked existing glass panes
4. Caulking of all new joints
5. Replace window putty stops as needed
6. Measurement shall be made as “each” to include the entire building including materials, labor, equipment, tools, and incidentals required to complete this item.
7. Incidentals to pay item include glazing and remove and installation of hardware
8. Payment shall be made at the contract price for this bid item.