This document is Amendment 3 to a solicitation for the maintenance and improvements to the Harris Building in Petersburg, AK. The amendment extends the quote due date to April 23, 2024 at 1300 AK time and provides clarifications and updates to the Performance Work Statement. Key details include:
The successful contractor must be licensed in the state of Alaska. The amendment clarifies the requirements for the exterior staircase landing slab material, handrail terminations, responsibility for concrete cracking from cutting the slab, location of a third cap, whether the columns are pile-supported, and responsibilities for brush/tree removal and sloping the ground away from the building. It also provides updates to the wastewater line re-route task, including the depth of the existing line, no need for a concrete ring, and a 15-foot belly/sag in the line. Additionally, it clarifies details for the weather wall replacement and breezeway door work. Finally, it removes Option Item 1001 for replacing a column.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 3 Schedule Items Offer PSG Harris Blg Maint V3.xlsx | XLSX spreadsheet | |
| 1240BF24Q0010 Amend 2.pdf | ||
| Attachment 3 Schedule Items Offer PSG Harris Blg Maint V2.xlsx | XLSX spreadsheet | |
| 1240BF24Q0010 amend1 remove shelter options.pdf | ||
| Attachment 1 PWS Harris Building Maint V2.pdf | ||
| 1240BF24Q0010 Petersburg Harris Blg Maint.pdf | ||
| Attachment 2 SCA WD 2015-5685 R21 2023.12.26 TNF.pdf | ||
| Attachment 3 Schedule Items Offer PSG Harris Blg Maint.xlsx | XLSX spreadsheet | |
| Appendix 3 Photo of Items to Move Task 8.pdf | ||
| Attachment 1 PWS Harris Building Maint.pdf | ||
| Appendix 2 WeatherPort drawings.pdf | ||
| Appendix 1 Drawings_Harris Building Maintenance_3-6-24.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240BF24Q0010
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40BF
PORTLAND OR 97204-2829
STE 310
1220 SW 3RD AVE
USDA-FS CSA NORTHWEST 4
04/12/20240003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/18/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 3
1. Extends quote due to April 23, 2024 1300 AK time
2. see pages 2-4 of this amendment
3. see revised quote sheet V3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STACY G. DOUTT
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
1240BF24Q0010 – Amendment #3 Page 2 of 4
Question: Is the requirement for the General Contractor license from State of AK License apply to the prime?
Answer: Yes, the successful contractor must be licensed to work in state of AK.
Items from site visit.
Task 2 – Level Exterior Staircase and Slab
1. For task 2.2: What material is required for the staircase landing topping slab?
Answer: See PWS section 2.2.
2. For Task 2.3 – Clarify handrail terminations.
Answer: The handrail terminations shall return to a wall, guard, or the walking surface such that items do not get caught on the end of the handrail.
Task 3 – Interior Slab Settlement Mitigation:
3. For Task 3.1: Who is responsible for concrete cracking that may develop after cutting the slab at the column bases?
Answer: If the work is performed in accordance with contract requirements, then the contractor will not be responsible for mitigating slab damage that may result from performance of this task. If damage occurs the government may open discussions with the successful contractor for possible repair.
4. Where is the 3rd cap:
Answer: The 3rd cap is in the wall between the shop and the record room.
5. Are the columns pile supported?
Answer: The Government drawings indicate that they are.
6. Clarifications for column at gridline B/5 - columns at gridlines B/3 and C/5:
a. The slab is a slab on grade.
b. The slab is likely connected to the pile caps via rebar.
c. The slab had foam injected under it several years ago to slow the settlement.
d. The slab on grade is separated from the exterior walls but has not been separated from the columns.
e. The columns are supported by piles.
f. It was noted the slab could drop suddenly when the joints are cut around the pile caps, which could result in pinching the saw blade, cracks in the concrete, or other unintended consequences.
Task 4 – Earthwork:
7. Task 4: Who is responsible for removing the brush required to perform this task?
Answer: The Contractor is required to remove brush within 6 ft of the building, as necessary to perform Task 4.
8. Task 4: Who is responsible for removing the trees in the swale?
Answer: The Contractor is not responsible for removing the trees.
1240BF24Q0010 – Amendment #3 Page 3 of 4
9. Task 4.2: Does the contractor need to provide material to slope the ground away from the building?
Answer: Yes. Task 4.2 has been changed to read as follows (new words are in red text, removed words are struck through):
Task 4.2 Where ground does not slope away from the building for 6 ft minimum, furnish, install, grade and compact enough D-1 aggregate up to 2 inches from the bottom of siding and grade so that the ground slopes away from the building for minimum of 6 ft, measured perpendicular to the face of the wall. Exclude locations where building perimeter borders asphalt or concrete.
Task 5 – Wastewater Line Re-Route:
10. Task 5: How deep is the existing sanitary sewer line?
Answer: The sewer line is about 3 feet below ground where it leaves the building. The City of PSG indicated that they did not know specifically only stating that they didn’t think it was that deep.
11. For Task 5: Is a concrete ring required to support the new cleanout where it meets the ground surface?
Answer: Concrete ring is not required. Cap on cleanout pipe, 6 inches above grade, is required.
12. Add the following to PWS Task 5:
All equipment, materials, excavation, and fill to remain within 20 ft of the Harris building, to stay on Forest Service property.
13. It was noted that the City has scoped the line with a video camera and discovered a 15 foot belly/sag in the line, below the back staircase landing slab.
14. How long is the section needing replaced for the wastewater line?
Answer: The section is not the entire length from the building to the street but shall be as shown on Drawing Sheet C-01.
Task 6 – Insulate and Weatherize Section of Exterior Wall:
15. It was clarified that the green corrugated pipe at the base of the siding, under the stairs, contains the fuel oil lines.
Task 7 – Rebuild Weather Wall at Main Entrance:
16. For Task 7: Does the Forest Service want to fully enclose the entry, or just replace the existing weather wall?
Answer: Replace the existing weather wall only, per PWS requirements.
17. For Task 7: Does the Forest Service want the existing planter bed removed and reinstalled? If yes, who is responsible for this work?
Answer: Contractor shall remove and reinstall the planter bed as needed to perform the work, including replacement of rotten planter bed boards.
1240BF24Q0010 – Amendment #3 Page 4 of 4
18. For Task 11: Are the breezeway doors fire doors?
Answer: The metal door adjacent to the shop area is a fire door.
19. For Task 11: Does the Forest Service want the re-squared doors flush with the threshold, or floating above the threshold?
Answer: Flush with the threshold.
Task 1001 – Replace Column:
20. Remove Option Item 1001 – see revised quote sheet V3.