C04-5 Quality Assurance Surveillance Plan rev 1.pdf

PDF 1 MB Posted

Attached to
Rock Crushing Service for the Wallowa Whitman National Forest
Solicitation number
1240BE26Q0107
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) for rock crushing services at the Wallowa Whitman National Forest under USDA solicitation 1240BE26Q0107. The QASP establishes procedures and methodologies for monitoring contractor performance against Performance Work Statement (PWS) requirements. The contractor must provide rock crushing services at three locations: NFSR 6700 MP 9.24 Rock Pit, NFSR 70 MP 8.6 Rock Pits, and an optional site at NFSR 7700 MP 9.30, all located within the Wallowa Whitman National Forest.

Performance standards focus on stockpiled aggregate production with specific gradation requirements per FSSS 703-3 Surface Course Aggregate Grading S, requiring gradation testing every 700 cubic yards. The contractor must submit representative samples and maintain target values within specified sieve size ranges (3/4 inch, 1/2 inch, 3/8 inch, No. 4, No. 8, No. 40, and No. 200). Surveillance methods include 100 percent monthly inspections using Acceptable Quality Level (AQL) calculations based on satisfactory occurrences divided by total observations. The Contracting Officer Representative (COR) conducts performance monitoring and analysis, rating contractor performance as Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory. The contractor is responsible for implementing a Quality Control Plan and appointing a single quality control point-of-contact. The QASP includes appendices with example forms for discrepancy reports, customer feedback records, inspection checklists, quality assurance monitoring documentation, complaint investigations, and surveillance activity tracking.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Quality Assurance Surveillance Plan

Rock Crushing Service for the Wallowa Whitman National Forest

Solicitation: 1240BE26Q0107

Contents Project Name

Section 1: Introduction

1.1 Purpose

1.2 QASP Relation to the Contract

1.2.1 QASP Revisions

1.2.2 Surveillance of Performance Progression

1.3 QASP Relation to the Quality Control Plan (QCP)

Section 2: Performance Description

2.1 Performance Standards and Acceptable Quality Levels (AQLs)

2.1.1 Allowable Deviation

2.1.2 Substantially Complete

2.2 Non-Performance

2.2.1 Documentation

2.2.2 Remedial Actions

Section 3: Contractor and Government Responsibilities

3.1 Contractor Responsibility

3.2 Government Responsibility

3.2.1 Contracting Officer (CO)

3.2.2 Contracting Officer Representative (COR)

3.2.3 Customers

Section 4: Surveillance Methods to Perform Quality Assurance

4.1 Surveillance Methods

4.2 Analysis and Results

Appendix A: Maintenance Standards and Quality Levels

314 – Stockpiled Aggregate

Appendix B: Example Discrepancy Report

Appendix C: Customer Feedback Record

Appendix D: Example Guide / Inspection List

Appendix E: Example Quality Assurance Monitoring

Appendix F: Example Customer Complaint Investigation

Appendix G: Example Surveillance Activity Checklist

Project Name Rock Crushing Service for the Wallowa Whitman National Forest

Section 1: Introduction This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) Rock Crushing Service for the Wallowa Whitman National Forest.

The Wallowa Whitman National Forest requires rock crushing service at the NFSR 6700 MP 9.24 Rock pit, or NFSR 70 MP 8.6 Rock Pits located in the Wallowa Whitman NF. An Option Item for rock crushing services at NFSR 7700 MP 9.30 is also included. Specific performance tasks are listed in the Performance Work Statement, Paragraph 3.

This plan sets forth the procedures and guidelines that the USDA, Wallowa Whitman National Forest will use in ensuring the required performance standards or services levels are achieved by the contractor.

1.1 Purpose

The purpose of the QASP is to describe the systematic methods used to measure performance and to identify the reports required and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards identified in the Performance Work Statement, PWS. This QASP is designed to define roles and responsibilities, identify the performance objectives, define the methodologies used to monitor and evaluate the contractor’s performance, describe quality assurance reporting, and describe the analysis of quality assurance monitoring results.

1.2 QASP Relation to the Contract

1.2.1 QASP Revisions

The Contracting Officer Representative (COR) may make revisions or changes to the QASP procedures and surveillance methods or increase or decrease the degree of surveillance methods at any time during the contract performance period. Changes to the Metric must be incorporated into the PWS, Performance Requirement Summary (PRS) and QASP by a bilateral modification to contract that is issued by the Contracting Officer (CO). A copy of the QASP is provided to the contractor to enable the contractor to enhance its Quality Control (QC) program to perform in accordance with its Quality Control Plan (QCP).

1.2.2 Surveillance of Performance Progression

As the performance period progresses, the levels of surveillance may be altered for service areas where performance is either consistently excellent or unsatisfactory. If consistently good performance, then the amount of surveillance may be reduced. If observations reveal consistent deficiencies, increased surveillance may be implemented.

1.3 QASP Relation to the Quality Control Plan (QCP)

The QCP is a required element of contract and the Contractor shall adhere to its established quality control processes and procedures in managing and performing work as described in the contract. While the QCP represents the way in which the Contractor will ensure its quality and timeliness of services, as defined in the PWS, the QASP represents the way in which the Government personnel specified in Section 3: Contractor and Government Responsibilities, Paragraph 3.2, Government Responsibilities will evaluate the contractor’s performance. The contractor’s QC program and the residual organization’s QASP should be complementary programs that ensure successful contractor performance.

Section 2: Performance Description Performance of the contractor will be monitored through the surveillance methods described in Section 4:

Surveillance Methods to Perform Quality Assurance to assess the Contractor’s performance against PWS requirements.

2.1 Performance Standards and Acceptable Quality Levels (AQLs) For selected activities in the PWS, the PRS provides a performance standard and an AQL. A performance standard is the expected level of contractor performance. An AQL defines the level of performance that is satisfactory. Depending on the service evaluated and the evaluation method selected, performance standards and AQLs may be stated as a number of occurrences or as a percentage.

Performance standards and AQLs for random sampling and 100 percent inspection are generally stated as percentages. For periodic inspections, performance standards may be stated as either percentages or as absolute numbers.

The contract requires the Contractor to perform all work as specified. Any inaccuracies or omissions in services or products are referred to as “defects” on the part of the Contractor. The Contractor shall be responsible for all identified defects and may be required to perform the work at no cost to the government. The AQLs take into account that in some instances an allowable level of deficiencies (deviations) is possible while overall performance continues to meet the government’s desired level of service.

2.1.1 Allowable Deviation

The AQLs define the level or number of performance deficiencies the Contractor is permitted to reach under this contract. AQLs take into account the difference between an occasional defect and a gross number of defects. AQLs can be expressed as a percentage of or as an absolute number (e.g., three per month). There may be instances where 100 percent compliance is required, and no deviation is acceptable (e.g., where safety is involved).

2.1.2 Substantially Complete

In some cases, service outputs are evaluated using subjective values (e.g., excellent, satisfactory, unsatisfactory). The criteria for acceptable performance and for defects must be defined for these service outputs. The concept of “substantially complete” should be the basis for inspections based on subjective scales. Work is considered “substantially complete” where there has been no significant departure from the terms of the contract and no omission of essential work. In addition, the Contractor has performed the work required to the best of its ability and the only variance consists of minor omissions or deficiencies.

2.2 Non-Performance

Non-performance occurs when the contractor’s performance does not meet the AQL for a given requirement. Requirements may contain multiple performance elements, and therefore, deficiencies may occur in one or more aspects of performance (e.g., timeliness, accuracy, completeness, etc.) or subject areas of effort.

When surveillance indicates that the contractor's service output is not in compliance with the contract requirements, the Contracting Officer’s Representative (COR) must determine whether the Contractor or the Government caused the deficiency. If the cause of the defect rests with the Government, corrective action must be taken through Government channels. If the cause of the defect is due to action or inaction by the contractor, the contractor is responsible for correction of the problem at no additional expense to the Government.

2.2.1 Documentation

Documentation of work non-performed or unacceptable work is essential for tracking Contractor performance. The COR will document deficient work by compiling facts describing the inspection methods and results and to substantiate nonconformance with the contract. A sample documentation reporting form is provided in Appendix B, Example Discrepancy Report. The documentation, with any recommendations, will be forwarded to the CO. In the case of the Contractor, the COR will decide whether to elevate the problem to the CO for corrective action.

2.2.2 Remedial Actions

The Federal Acquisition Regulation allows for penalties in the event that the Contractor fails to perform the required services. Penalties are defined as those actions taken under the direction of the CO against the contractor within the general provisions of the contract for nonconformance to the PWS and PRS.

Section 3: Contractor and Government Responsibilities

3.1 Contractor Responsibility

The Contractor is responsible for delivering products or services in accordance with the contract.

Implementing its QCP, which describes the Contractor’s methods for ensuring all products and services under the contract meet established performance standards and AQLs. Maintaining, and providing for audit, quality control records and reports and all records associated with the investigation and complaint resolutions. Appointing a single quality control point-of-contact to act as a central recipient of communication from the COR or CO.

3.2 Government Responsibility

3.2.1 Contracting Officer (CO)

The CO is responsible for administering and monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by COR and the contractor’s performance. The CO may delegate various day-to-day contract administration duties to the COR for performance management and administrative actions such as invoice approval and issuance of Contract Discrepancy Reports may be, and normally are, delegated by the CO to the COR. The CO shall approve any revisions to the QASP processes or standards.

3.2.2 Contracting Officer Representative (COR)

The COR, is designated in writing, by the CO. The COR will ensure that the QA function is properly executed, plays a key role in contract administration and performs the contract surveillance and monitoring. Some key contract administration duties include, but are not limited to, performs surveillance as required by this QASP; make recommendations to the CO for issuance of Contract Discrepancy Reports or letters of commendation and acceptance or rejection of completed work and for administrative actions based on unsatisfactory or non-performed work, and revisions or changes to the QASP; and assists the CO in identifying necessary contract modifications and preparing reports of Contractor performance and cost.

The COR may use the form(s) included in the Appendices to perform the inspection or other forms as approved by the CO.

3.2.3 Customers

Customers or organizations/offices that the Contractor provided support may be requested to assist the COR in conducting QA to provide information relating to the Contractor’s performance through Customer Feedback. Information gained from the Customer Feedback may be used in conjunction with other methods of observation to rate the performance of the Contractor.

Section 4: Surveillance Methods to Perform Quality Assurance

4.1 Surveillance Methods

The surveillance methods used in the QA process are the Government’s tools to monitor the Contractor’s products and services. The best means of determining whether the Contractor has met all contract requirements is to inspect the Contractor’s service products and analyze the results. Further, documented inspection results are an effective tool in contract administration that can confirm the successful achievement of all performance requirements or highlight areas where defects exist and improvements are necessary.

4.1.a 100 Percent Inspection The 100 percent inspection method requires complete inspection each month and will be used for critical contract requirements.

4.1.b Performance Standards and AQLs Calculating Acceptable Quality Level, AQL: Acceptable quality levels AQL will be calculated by dividing the number of acceptable occurrences observed by the number of possible occurrences observed.

For example: Paragraph 3.2 in month one the COR observed 30 rock samples. Of the 30 observed services, 28 were satisfactory. 28 satisfactory observations divided by 30 possible observation equals

0.971 or 97%.

4.2 Analysis and Results

When the inspections and validations have been completed, the COR will perform an analysis of the Contractor’s performance. The purpose of the analysis is to ensure Government is receiving high-quality products and services from the Contractor. The COR will review the results, rate the Contractor’s compliance with the performance standards and AQLs, and characterize the Contractor’s overall performance. Analysis of all types of contract monitoring will result in one of the following outcomes:

Performance Rating

Criteria

Exceptional

Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good

Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Appendix A: Standards and Quality Levels

314 – Stockpiled Aggregates Description

314.01 This work consists of furnishing and placing material in a stockpile for future use by the Government. Pit or quarry development work consists of clearing, grubbing, stripping topsoil, removing overburden, constructing access roads, conducting restoration activities, and performing other incidental work required for pit or quarry development.

Material

314.02 Conform to the following Section:

After a representative quantity of aggregate is produced, submit proposed target values for the appropriate sieve sizes along with the representative sample size. Set target values within the gradation ranges shown in the applicable table for the required grading.

Performance Task 3.2 & 3.3; Gradation for Surface Course Aggregate; NFSR 6700 MP 9.24 Rock Pit; & NFSR 7700 MP 9.30 Rock Pit.

See FSSS 703-3 Surface Course Aggregate; Grading S. Gradation testing required every 700 CY.

Table 703-3 Gradation Limits for

Surface Course Gradation S

Sieve Size Percent by Mass Passing

Designated Sieve

(AASHTO T 27 & T 11)

3/4 inch 100

1/2 inch

3/8 inch

No. 4 50-78

No. 8 37-67

No. 40 13-35

No. 200 8 – 15 (4)

Construction Requirements

314.03 General. Conform to the gradation and quality requirements specified in the Section identified for the material.

314.04 Stockpile Site. The Government will acquire the permits and rights to stockpile aggregate from sources identified in the contract if the material is stockpiled for future use.

Prepare a plan of operation. Do not perform work within a Government-provided source until a plan of operation for the development of the source is accepted. Submit quality control plan a minimum of two weeks for approval before start of work.

Obtain CO approval before preparing sites. Prepare sites as necessary to accommodate the quantity of material to be stockpiled in a manner that prevents contamination of the stockpiles.

Prepare new sites as follows:

(a) Clear and grub vegetation from the site to the extent needed for the crushing and storage operations. Do not clear and grub beyond the limits needed for operations.

(b) Grade, shape, and compact the site to a uniform cross-section that drains; and

(c) Place, compact, and maintain a minimum 6-inch layer of crushed aggregate over the stockpile site and access roads for stabilization.

Obtain COR approval before stockpiling aggregates.

314.05 Stockpile. Build aggregate stockpiles in layers not to exceed 36 inches in thickness. Make the side slopes of each layer no flatter than 1V:1.5H. Spread aggregates with trucks or other approved pneumatic-tire equipment. Complete each layer before depositing aggregates on the next layer. Do not allow aggregates from the layer being built to run down over lower layers. Do not drop aggregates from a bucket or spout in one location to form a cone-shaped pile. Do not push aggregates into piles. Make the stockpiles neat and regular in shape.

Use plank runways or other suitable methods to avoid tracking dirt or other foreign matter onto the stockpiled material when operating trucks on stockpiles.

Space stockpiles far enough apart or install partitions to prevent the mixing of aggregate gradations.

Protect stockpiles for future use with an approved cover.

314.06 Acceptance. Submit a minimum of one representative graduation for each 700 cubic yards of aggregate crushed.

Measurement

314.07 Measure the Section 314 pay items listed in the bid schedule in the finished stockpile.

Payment

314.08 The accepted quantities will be paid at the contract price per unit of measurement for the pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.

Appendix B: Example Discrepancy Report The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.

DISCREPANCY REPORT 1. DISCREPENCY REPORT NO.

2. TO: (Contractor / Project Manager Name) 3. FROM: (Name of COR)

CONTRACT NUMBER: DATE:

PREPARED ORAL NOTIFICATION RETURNED BY CONTRACTOR ACTION COMPLETE

4. DISCREPENCY OR PROBLEM (Describe in Detail. Include PWS references. Attach Continuation Sheet if Necessary)

5. SIGNATURE OF COR

6. TO: (Name of COR) 7. FROM: (Contractor / Project Manager)

8. CONTRACTOR RESPONSE AS TO CAUSE, EFFECT, CORRECTIVE ACTION AND ACTIONS TO PREVENT RECURRENCE (Attach Continuation Sheet if necessary. Cite applicable Contractor QC program procedures or new QC procedures)

9. SIGNATURE OF CONTRACTOR REPRESENTIVE 10. DATE

11. GOVERNMENT EVALUATION (Acceptance, partial acceptance, or rejection. Attach Coordination Sheet if necessary)

12. GOVERNMENT ACTIONS (Cure notice, show cause, other)

CLOSE OUT

KTR NOTIFIED

NAME AND TITLE SIGNATURE DATE

COR

Appendix C: Customer Feedback Record The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.

CUSTOMER FEEDBACK RECORD

DATE AND TIME OF COMPLAINT CONTRACT NUMBER/ OR PROJECT:

SOURCE OF COMPLAINT

ORGANIZATION

INDIVIDUAL

NATURE OF COMPLAINT

PWS REFERENCE

VALIDATION

DATE AND TIME CONTRACTOR INFORMED OF COMPLAINT NAME OF CONTRACTOR REPRESENTATIVE INFORMED OF COMPLAINT

ACTION TAKEN BY CONTRACTOR (Responsible officer):

RECEIVED AND VALIDATED BY

Determination: Complaint Valid Complaint Invalid

Appendix D: Example Guide / Inspection List The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.

CONTRACT NUMBER: ___________________________________

SERVICE FUNCTION:

PWS SECTION:

1 Method of Surveillance:

2 Lot Size:

3 Sample Size:

4 Performance Requirement: Performance is Excellent (E) when ___________or fewer defects are discovered per month. Performance is Satisfactory (S) when ________ or fewer defects are discovered per month. Performance is Unsatisfactory (U) when _______ or more defects are discovered per month.

5 Sampling Procedure: Instructions on how to select the sample must be clear and complete

6 Inspection Procedure: The procedure must be detailed enough to allow a yes/no objective decision as to the acceptability of performance by anyone making the inspection. Explain when evaluation is to occur and what is acceptable/unacceptable

Performance: Excellent (E), Satisfactory (S), Unsatisfactory (U), Not Applicable (N/A)

PRS Requirements Timeliness Quality of Work Notes

Overall Rating Of Inspection (E, S, U or N/A)

COR/Inspector Comments:

Contractor Signature: ___ Date: __

COR Signature: ____________________Date: _________________

Appendix E: Example Quality Assurance Monitoring The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.

CONTRACT NUMBER: ______________________________________

SERVICE or STANDARD:

SURVEY PERIOD:

SURVEILLANCE METHOD (Check the applicable item):

Random Sampling 100% Inspection Periodic Inspection Customer Complaint

LEVEL OF SURVEILLANCE (Check the applicable item):

Monthly Quarterly As needed

PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %

ANALYSIS OF RESULTS:

Observed Service Provider Performance Measurement Rate: ______%

Service Provider’s Performance (Check the applicable item):

Meets Standards

Does Not Meet Standards

Narrative of Performance During Survey Period:

Prepared By: _______________________________ Date: ______________

Appendix F: Example Customer Complaint Investigation The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.

CONTRACT NUMBER: _________________________

SERVICE or STANDARD:

SURVEY PERIOD: ___________________

DATE COMPLAINT RECEIVED: ____________

SOURCE OF COMPLAINT: _________________________________________ (Name) _______________________________________________________________ (Organization) ___________________ (Phone No.) _________________________________ (Email Address)

NATURE OF COMPLAINT:

RESULTS OF COMPLAINT INVESTIGATION:

DATE SERVICE PROVIDER INFORMED OF COMPLAINT: _____________

CORRECTIVE ACTION TAKEN BY SERVICE PROVIDER:

Received and Validated By: __________________________________________ Prepared By: _____________________________ Date: _________________

Appendix G: Example Surveillance Activity Checklist The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.

Performance Requirement

Performance Standard

Method of Measurement

Performance Metrics

Method of Surveillance

Date Accomplished

Compliance (Exceed, Met, Partial Met)

File details come from the government source that posted it. Updated .