Amendment 01 - Questions and Answers.pdf
PDF 38 KB Posted
- Solicitation number
- 12405B24R0018
About this file
This document is a set of Questions and Answers related to Amendment 01 of Solicitation Number 12405B24R0018 for construction services to perform multi-task work including painting of the main building eaves, greenhouse covered walkways, and exposed I-beams, as well as installing gutters and downspouts at the USDA Agricultural Research Service (ARS) Southeast Area U.S. Horticultural Research Laboratory in Fort Pierce, FL.
The key details include specifications for the gutters and downspouts (7" K-type 032 aluminum gutters with 4"x5" downspouts), limitations on use of certain chemicals due to ongoing research, allowance for power tools to sand metal, the option to replace soffit vents entirely instead of just painting, the need to address divots in the grass from lift equipment, and coordination required with the Facility Manager for pressure washing and material staging. The solicitation has a NAICS code of 236220 with a $45M size standard.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12405B24R0018-AMENDMENT 01-Questions and Answers
What type of gutters and what size are the Gutters? It is K type 7” gutters 032 aluminum with 4”x5” downspouts.
Can we use chlorine remove mold and mildew of existing exterior surfaces? NO; due to the sensitivity of ongoing research
Can we use power tools to sand metal where necessary? Absolutely
Can we estimate painting the entire soffit and PVC vents the same color rather than only painting the PVC soffit vents? Submit as a separate line item to review the cost.
Are we responsible for filling divots in the grass formed by the wheels of the lift? Yes
If we find it cost effective can we replace the soffit vents in their entirety rather than taping and protecting the soffit to paint only the soffit vents? Submit as a separate line item to review the cost.
Does the USDA have the color code for the current soffit color? For matching the color in the soffit repair areas? No color sample on file. Remove sample from the ceiling and have it color matched
Are all areas where work will be done lift accessible for a 45ft articulating boom lift?
Yes
Will the loading dock be completely cleared of materials when we get to it? Or will it be partially cleared as we move from section to section? Coordinate schedule with Facility Manager.
Are we able to pressure wash the ceiling of the greenhouse covered walkway? Yes, coordinate schedule with Facility Manager.