PhaseIPresentation.pptx

PPTX presentation 10 MB Posted

Attached to
Design-Build Services for the Renovation of BARC Building 307
Solicitation number
123K2518R0010
Issued by

About this file

Power Point Presentation - Phase I - Pre-Proposal Meeting.

View the file

Other files

File Type Posted
FBO Award Notice - BARC 307.pdf PDF
Short_Listed_Offerors_Phase_II_FBO_Notice.pdf PDF
SignInSheet.pdf PDF
RFIForm.doc DOC document
RegistrationForm.docx DOCX document
AmendmentForm.doc DOC document
QuestionForm.doc DOC document
SFLLL.pdf PDF
ARS242-01m-DesignStandards.pdf PDF
ARS-371-ProgressandPaymentSchedule.pdf PDF
SF1442.pdf PDF
SF25-PerformanceBond.pdf PDF
Ars372_(with_Certs)-RequestforPaymentTransmittal.xls XLS spreadsheet
SF24-BidBond.pdf PDF
SF25A-PaymentBond.pdf PDF
Solicitation.docx DOCX document
WageDetermination.txt TXT text file
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Beltsville Agricultural Research Center Building 307 Renovation and Rehabilitation Phase I pre-proposal meeting Beltsville, MD

LOCATION

BACKGROUND

BARC Building 307 was constructed in 1940 and has never been renovated or modernized.

Project Scope will include a complete gut and rebuild.

Building will contain Biological Safety Level 2 Laboratories, support spaces, and associated administrative space.

Proposed construction will be performed on an active research campus, in an unoccupied building.

This renovation project will be implemented by the Design-Build project delivery method.

REQUIREMENTS

Design-Build Services are expected for the following:

Architectural Elements (Roof, Windows, Finishes) Mechanical-Electrical-Plumbing Laboratory Systems Upgrade Site Utilities Upgrade Structual Systems Removal of HAZMAT Bridging Documents will consist of a 35% design submission. Design-Build contractor will use these documents as the basis of the design.

Procurement requires the use of biobased products. Refer to the USDA BioPreferred Program.

PROJECT ACQUISITION REQUIREMENTS

BASE:

01a – BASE ITEM – Design 01b – BASE ITEM – Construction

GENERAL ACQUISITION POINTS:

Performance Period – 800 Calendar Days from issuance of the Notice to Proceed.

Maginitude of construction is more than $10 million.

Full and open competition

OVERVIEW OF SOLICITATION PROCESS

Two-Phase Design-Build Solicitation Phase One Prepare technical proposal based on all evaluation factors Technical Evaluation Panel will review and determine a short list.

Phase Two Request for Proposal will be issued to the short list. Maximum of four.

Site Visit will be scheduled for short list contractors.

Technical Evaluation Panel will review and determine the awardee.

Award will be based on Best-Value Tradeoff Process

SITE PLAN

- BUILT IN THE 1930’S

- 60,000 SF

- 3 STORIES, PLUS A

BASEMENT AND ATTIC

- HISTORIC STRUCTURE

- MHT HAS APPROVED

THE PROPOSED WORK.

- EA IS NEARLY COMPLETE

- ABANDONED ABOUT 15

YEARS AGO

- HAZMAT INCLUDES LEAD

PAINT AND ASBESTOS

VERIZON ROOM

RESTORE EXTERIOR WINDOWS, CUPOLAS AND ENTRANCES

REAR OF BUILDING

3 FLOORS PLUS BASEMENT AND ATTIC

CUTOUT OF BUILDING

ATTIC TO INCLUDE DUCTWORK AND AHU’S

REAR OF BUILDING

BASEMENT TO INCLUDE STORAGE, ELECTRIC ROOM AND FIRE SUPPRESSION

TYPICAL FLOOR TO INCLUDE OFFICES, LABORATORIES AND CONFERENCE AREAS

SITE UTILITIES TO INCLUDE NEW STEAM PIPE, WATER, SEWER, GAS, ELECTRIC AND COMMUNICATIONS

SITE IMPROVEMENTS TO INCLUDE NEW PAVING, SIDEWALK CURB AND RESTORATION

QUESTIONS AND ANSWERS

SITE VISIT

image6.jpeg image7.png image1.jpeg image2.png image3.png image4.png image5.png image8.png image9.png image12.png image13.png image14.png image10.png image11.png image11.jpg image12.JPG image13.jpg image20.png image21.png image22.png image15.png image19.png image16.png image17.png image18.png image23.png image24.png image25.png

File details come from the government source that posted it.