3 - answers to questions from vendors.docx
DOCX document 35 KB Posted
- Solicitation number
- 123A9423Q0050
About this file
This document contains answers to vendor questions regarding solicitation number 123A9423Q0050 from the Department of Agriculture Food Safety and Inspection Service. The solicitation requests proposals for data quality services, including a data analyst as key personnel. Vendors must submit their proposals within 10 pages excluding appendices, where resumes for key personnel may be included. An initial program plan is due as a PowerPoint presentation within 10 business days of award, and a project management plan is due as a Word or PDF document within 15 business days. The evaluation will consider the adequacy of information provided about project management and planning, oversight and monitoring. No draft project plan needs to be submitted with the proposal but information on relevant categories should be included.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2 - answers to questions from vendors.docx | DOCX document | |
| RULES OF BEHAVIOR FOR PRIVILEGED USERS.docx | DOCX document | |
| 1 - answers to questions from vendors.docx | DOCX document | |
| Solicitation 123A9423Q0050.pdf | ||
| Solicitation 123A9423Q0050.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section/ Paragraph
| Page |
| Reference Text |
| Question |
C.12
D
C.12 NON-DISCLOSURE REQUIREMENTS
If the contractor acts on behalf of, or provides advice with respect to any phase of an agency procurement, as defined in FAR 3.104-4, then the contractor shall ensure that all its personnel (to include subcontractors, teaming partners, and consultants) who will be personally and substantially involved in the performance of the TO:
a. Execute and submit a Corporate Non-Disclosure Agreement (NDA) Form (Attachment A) and submit to the CO, prior to the commencement of any work on the TO, and
b. Are instructed in the FAR 3.104 requirements for disclosure, protection, and marking of contractor bid or proposal information, or source selection information
D. ANY CONTRACT DOCUMENT, EXHIBITS OR ATTACHMENTS
(a) Statement of Work for Data Quality
(b) Evaluation Criteria and Methodology Please clarify: a) Where do we find Attachment A, Corporate Non-Disclosure Agreement (NDA) Form?
Contractors fill out the Non-Disclosure form after contract award, as part of background check and onboarding forms.
The form is not necessary for vendors’ response to this RFQ.
b) Although labeled a) in section D, Statement of Work for Data Quality is titled Attachment 1 on page 34.
Please excuse this oversight.
c) Although labeled b) in section D, Evaluation Criteria and Methodology is titled Attachment 2 on page 47 Please excuse this oversight.
C.17
E.4.B, paragraph 12(?)
The Offeror’s proposal must include:
(1) A detailed outline (commensurate with the size and complexity of the Performance Work Statement) of its present and proposed information technology systems security program. The response must demonstrate that it complies with the security requirements of the PW,S the Federal Information Security Management Act of 2002 (FISMA, Public Law 107-347, 44 U.S.C. 3531-3536); Office of Management and Budget (OMB) Circular A-130, Appendix III “Security of Federal Automated Information Systems” (http://www.whitehouse.gov/omb/circulars_a130_a130appendix_iii) and an acknowledgement of its understanding of the security requirements of the SOW.
(2) A signed copy of the USDA FSIS IT Rules of Behavior (Attachment B) shall be included with the Offeror’s proposal.
PAGE LIMITS
10 pages for the Technical Proposal (excluding Cover Letter, Executive Summary, and any Appendices) Please clarify: Does response to this requirement count against the page limit for Volume I?
This information is no longer necessary for the vendor response to this RFQ. Clause C.17 is hereby removed from the solicitation.
C.17
E.4.B, paragraph 12(?)
The Offeror’s proposal must include:
(1) A detailed outline (commensurate with the size and complexity of the Performance Work Statement) of its present and proposed information technology systems security program. The response must demonstrate that it complies with the security requirements of the PW,S the Federal Information Security Management Act of 2002 (FISMA, Public Law 107-347, 44 U.S.C. 3531-3536); Office of Management and Budget (OMB) Circular A-130, Appendix III “Security of Federal Automated Information Systems” (http://www.whitehouse.gov/omb/circulars_a130_a130appendix_iii) and an acknowledgement of its understanding of the security requirements of the SOW.
(2) A signed copy of the USDA FSIS IT Rules of Behavior (Attachment B) shall be included with the Offeror’s proposal.
PAGE LIMITS
10 pages for the Technical Proposal (excluding Cover Letter, Executive Summary, and any Appendices) Please clarify: a) Where do we find Attachment B?
Contractors will sign this document after award, as part of background check and onboarding.
The IT Rules of Behavior is part of the IT Security Awareness training.
It is not necessary to include a signed copy with any vendor response to this RFQ.
Vendors can find a sample of Attachment B among the files uploaded to www.sam.gov.
b) Does the signed copy of Attachment B count against the page limit for Volume I?
N/A
Attachment 1, Statement of Work for Data Quality, section 7.0
Attachment 2, Evaluation Criteria and Methodology, section 1.2
7.0 Contractor’s Key Personnel
Data Analyst
1.0 FTE at 1920 hours
The contractor shall be one FTE with the following required qualifications. The Government may require additional hours based on mission requirements.
1.2 Factor 2 Personnel, Qualifications, and Staffing
a. The Government will evaluate the adequacy of the Quoter’s:
i. Approach to providing the resources with the appropriate skills, depth of experience, training, and professional qualifications
ii. Ability to maintain continuity of assigned employees and ability to back-fill vacancies in a timely manner
iii. Accessibility, availability, and continuity of key personnel and the explanation of why the proposed project manager is uniquely qualified to occupy the project manager key personnel position Please clarify: a) Does the government expect a project manager key personnel position (as implied in the evaluation criteria) in addition to the key personnel Data Analyst?
The highlighted text was included in error. Highlighted text should not be included. We do not require a project manager for this effort.
b) If yes, what are the desired hours and qualifications for the project manager key personnel position?
N/A
Attachment 1, Statement of Work for Data Quality, section 7.0
7.0 Contractor’s Key Personnel
Data Analyst
1.0 FTE at 1920 hours
The contractor shall be one FTE with the following required qualifications. The Government may require additional hours based on mission requirements.
Any changes to the proposed Key Personnel(s) after award MUST be approved by the Contracting Officer and shall only be approved upon demonstration of as-good or better qualifications when the new individual is compared to the qualifications and experience of the original proposed individual. Key Personnel shall demonstrate their capabilities by providing a resume (not to exceed five pages). The resume shall explain, in detail, the qualifications of the proposed personnel to include how they meet the qualifications outlined in the statement of work.
Please clarify: a) Does the Key Personnel resume(s) count against the page limit for Volume I?
b) Is it acceptable to place the resume(s) for key personnel in an Appendix?
It is acceptable to include resume(s) in an appendix, which would not be subject to the 10-page limit.
Attachment 2, Evaluation Criteria and Methodology, section 1.4
Attachment 1, Statement of Work, section 5.0, paragraph 4 table
The evaluation will consider the adequacy of the Draft Project Plan/Schedule. During the evaluation, the Government will evaluate the extent to which the following information/approaches provided by the offeror ensures/enables the successful achievement of the goals/tasks:
i. Project Management and Project Planning
ii. Project Oversight and Monitoring (Schedule Management, Risk Management, Performance Management, Quality Management, Organizational Change Management, Configuration Management, Requirements Management, Release Management)
Item Deliverable Due Date Format Addressee
1. Kick-off Meeting with agenda and initial program plan (to be scheduled w/ COR) 10 business days after date of award Power Point N/A
3. Project Management Plan 15 business days after date of award MS Word or PDF
COR, PM
Please clarify: a) Does the government require a Draft Project Plan/Schedule be submitted with the proposal?
We are evaluating the offeror’s management plan, as partially detailed to the left, and further detailed in the rest of that section of the Evaluation Criteria. Please review the specifications of the solicitation.
b) We do not see a Draft Project Plan/Schedule listed in the Deliverables table. Is the Draft Project Plan/Schedule the same as Initial Program Plan mentioned in the kickoff meeting?
The Initial Program Plan is a (PowerPoint) presentation version of the Draft Project Plan.
c) Is the Draft Project Plan/Schedule the precursor to the Project Management Plan deliverable?
Yes
Attachment 2, Evaluation Criteria and Methodology, section 1.4
The evaluation will consider the adequacy of the Draft Project Plan/Schedule. During the evaluation, the Government will evaluate the extent to which the following information/approaches provided by the offeror ensures/enables the successful achievement of the goals/tasks:
i. Project Management and Project Planning
ii. Project Oversight and Monitoring (Schedule Management, Risk Management, Performance Management, Quality Management, Organizational Change Management, Configuration Management, Requirements Management, Release Management)
Please clarify: a) Does the government require we submit sections on Schedule Management, Risk Management, Performance Management, Quality Management, Organizational Change Management, Configuration Management, Requirements Management, Release Management with the proposal?
If not specified by the solicitation, vendors can organize their proposal information as they see fit. Section headers with the above names are not explicitly required. However, we are evaluating their plans for those categories, so the information should be included. Please review the specifications included in this solicitation.
b) Is it acceptable to place the Draft Project Plan/Schedule in an Appendix?
It is acceptable to include any schedules in an appendix.