This document is a pre-solicitation notice for the BCLH Stewardship IRSC Phase 2 project, which will be awarded under the Stewardship Authority. The objectives of this project are to reduce the risks of hazardous fuels along important access routes within the 2020 fire-affected road system. Key work requirements include cutting and removing fire-killed trees within 100 feet of roads (176 acres mandatory, 300 acres optional), falling and leaving hazard trees in special measure areas (161 acres mandatory, 332 acres optional), performing small fuels treatment within 30 feet of roads (200 acres mandatory, 257 acres optional), and road reconstruction and maintenance activities. The mandatory road reconstruction work is estimated between $1,000,000 and $5,000,000, and the optional work between $500,000 and $1,000,000. A site visit is scheduled for October 5, 2024, and the final solicitation is anticipated to be issued on or around February 21, 2025, with award planned for April 25, 2025. The resulting contract will be a firm fixed price contract using a best value source selection method.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SiteVisitNotes_110424.pdf | ||
| DRAFT_Phase2_Appendix A_103024.docx | DOCX document | |
| DRAFT_Phase2_Appendix B_103024.docx | DOCX document | |
| Phase2_AppendixC_DRAFT.pdf | ||
| Excerpt_DRAFT_RFP_Phase2_102924.pdf | ||
| DRAFT_Phase2_Construction_FSSS_102924.pdf | ||
| DRAFT Phase 2 Burn Severity Map_102924.pdf | ||
| DRAFT Slope Table_102924.xlsx | XLSX spreadsheet | |
| DRAFT_ConstructionTypicals_102924.pdf | ||
| DRAFT Burn Severity Table_102924.xlsx | XLSX spreadsheet | |
| Attachment1_VICINITY MAPS.pdf | ||
| Attachment2_ProjectAreaAccessInstructions.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LH-15
LH-14
LH-54
LH-66
LH-14A
LH-55
LH-64
LH-66A
LH-55A
LH-55D
LH-15D
LH-53
LH-13
LH-15C
LH-1
LH-63
LH-51
LH-55C
LH-15A
LH-75
LH-15CA LH-64A
LH-55B
LH-3A
LH-52 LH-4
LH-54D
LH-50
LH-52ALH-54C
LH-72
LH-54B
LH-15B
BC-8
LH-54A
LH-64B
LH-3B
LH-51A
LH-15E
LH-52BLH-52C
24 1 4
6 4
9 8
36 15
5 46 3
2 3 56
34 32
33 31
36323334
1012 1014
061610
505535
461 313
717 099
056 058
055J
540 513
0 70
0 225
2234 023
T 1 1 S
T 1 2 S
T 0 9 S
T 1 0 S
T 0 8 S
T 1 1 S
T 1 1 S
T 1 1 S
T 1 2 S
T 0 9 S
T 1 0 S
R 06 ER 05 ER 05 E R 05 E R 05 E
R 07 E
R 07 E R 08 E
R 05 E R 06 E R 07 E
R 04 E
W a l d o L a k e
Hwy 22
R
0 1.5 30.75 Miles
TJR - 10/28/2024
Contract Provision References C5.12# Use of Roads by Purchaser: Applies to All Roads Identified on the Contract Area Map and as Agreed to by Forest Service C2.355# Applies to All Subdivisions C6.74# Slash Treatment Requirements: Applies to All Mandatory Subdivisions
Hwy 22 Portland
BendEugene
Roseburg
§̈¦80
§̈¦5
§̈¦5 ¬«97
¬«97
¬«58
Willamette National Forest
BCLH Phase 2 DxP IRSC Project Area
¬«58
¬«22
¬«20
¬«126
Place Holder for C5.12# info
BCLH Phase 2 DxP IRSC Contract Area Map
Detroit Ranger District Willamette National Forest
Mt. Jefferson Wilderness
Mt. Jefferson Wilderness
§̈¦80
BC-8
LH-1
LH-13
LH-14
LH-14A
LH-15
LH-15A
LH-15B
LH-15C
LH-15CA
LH-15D
LH-15E
LH-3A
LH-3B
LH-4
LH-4A
LH-50
LH-51
LH-51A
LH-52
LH-52A
LH-52B
LH-52C
LH-53
LH-54
LH-54A
LH-54B
LH-54C
LH-54D
LH-55
LH-55A
LH-55B
LH-55C
LH-55D
LH-6
LH-63
LH-64
LH-64A
LH-64B
LH-66
LH-66A
LH-72
LH-75
BCLH Phase 2 DxP IRSC Boundary
Waterbody
! ! ! ! Protect Streams B6.5
PRIVATE
Wilderness
# Subdivision, C2.355#
Subdivision # B1.1
Total Tree Felling Ac.
C2.355#
Total Required
Fuels Treamtent
(0-30')
Subdivision # B1.1
Total Tree Felling Ac.
C2.355#
Total Required
Fuels Treamtent
(0-30')
BC-8 2.6 5.9 LH-13 21.6 16.9
LH-1 16.6 16 LH-14A 22.6 10.4
LH-14 51 41.8 LH-15A 7.6 9.3
LH-15 0 25.7 LH-15B 2.7 1.5
LH-51 33.7 29.3 LH-15C 18 10.2
LH-51A 1.9 1.1 LH-15CA 6.1 2.7
LH-54 35 30.8 LH-15D 11.8 7.2
LH-63 0 9.5 LH-15E 0 0.5
LH-64 0 5.7 LH-15F 0 0.7
LH-64B 0 2.2 LH-3A 30.6 33.7
LH-66 30.8 28.9 LH-3B 1.9 3
LH-75 4.8 3.3 LH-3C 0.5 1
TOTAL 176.4 200.2 LH-4 8.9 8.3
LH-4A 3.3 4.3
LH-50 6 6.9
LH-52 13 16.5
LH-52A 3.1 1.5
LH-52B 0 0.3
LH-52C 0.4 0.1
LH-53 10 8
LH-54A 1.3 3.9
LH-54B 2.6 3.5
LH-54C 9.8 9
LH-54D 0.3 4
LH-55 33 27.6
LH-55A 25.2 20.4
LH-55B 18.7 12.6
LH-55C 8.8 8.7
LH-55D 11.2 7.8
LH-6 0 0.4
LH-64A 4.9 2.5
LH-66A 10.5 7.5
LH-72 2.9 3.5
LH-74 2.9 2.6
TOTAL 300.2 257