This solicitation seeks proposals for a hazardous fuels treatment project located on the Sierra National Forest in California. Contractors must remove designated sawtimber and non-sawtimber material from various cutting units, reconstruct and maintain existing roads, and dispose of limbs and treetops in designated piles or disposal sites. The response date for proposals is August 16, 2022. The project aims to reduce wildfire risk around several housing tracts and allow for safe access. The soliciting agency is the USDA Forest Service.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF

CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0002 08/09/2022 1068832

6. ISSUED BY CODE 363N 7. ADMINISTERED BY (If other than Item 6) CODE

USDA-FS- Procurement & Property Services

National Procurement Operations

Stewardship Contracting Branch

3710 Fallon Street, Suite C

Bozeman, MT 59718

Email: norma.windle@usda.gov

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

Potential Quoters

12363N22Q4087

9B. DATED (SEE ITEM 11)

07/25/22

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 01 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION

OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return * copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

12363N22Q4087, Amendment 0002, Lakeshore Revised Stewardship IRSC

1. This amendment is to provide responses to questions that were asked on or about August 8, 2022.

2. Response date for the RFQ has NOT changed and RFQ is still due on August 16, 2022 at 4:00 p.m. PST.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N. JEAN WINDLE

Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

mailto:norma.windle@usda.gov

12363N22Q4087 Amendment No. 0002, dated 08/09/2022 Lakeshore Revised Stewardship IRSC

Sierra National Forest

Lakeshore Revised Stewardship IRSC

Solicitation Number 12363N22Q4087

Amendment 0002 – Questions and Answers from on or about August 8, 2022.

Q1.) Page 3 of 27 of Appendix C specifies Road Maintenance Requirements for several roads that don't appear to be on the Contract Area Map as well as T Specifications that don't seem to correspond to the

T- Specifications referred to on Page 4 of 27 - Appendix C. Are the road maintenance requirements called out on Pages 2 and 3 of Appendix sufficient for this portion of the contract?

A1.) It appears that page 3 may be a remnant from a previous contract. We do not have a Highway 372 on the project or forest. When Appendix C is downloaded and opened it also has the title

“CanyonHillsStew_FY2015”. This information is not correct either. Page 2 & 3 are the required road maintenance work.

Q2.) Since the current access roads are in various states of disrepair, is the contractor responsible for any surface replacement on roads perceived to be damaged by the contractor? If roads are going to have to be resurfaced or extensive repairs required based on the desires of the local residence, then the bid price will be affected.

A2.) Roads should and will be documented for their current state. It is expected that contractors do not do anything to further the disrepair of the roads. Excessive damage done by the contractor may cause grounds for a damage claim or be the contractors responsibility to repair. Excessive damage for example but not limited to ripping, tilling, tracking or blading roads and causing new ruts, holes and asphalt damage. The current damage that is present due to the fire and other use, is not the responsibility of this contract. The only road repair is that listed within Appendix C.

Q3.) Is there a performance bond?

A3.) Please refer to the solicitation, on page 4 of 75, For construction item 6, road reconstruction, the estimated price magnitude is less than $25,000; therefore, alternative payment protection does not apply until

$35,000 which can be a payment bond for construction. Performance bonds are required at $150,000 or greater for construction.