This document provides notes from a pre-bid site visit meeting for the Devil's Creek Integrated Resource Stewardship Contract solicitation number 12363N21Q0003 issued by the United States Department of Agriculture Forest Service. The contract is located on the Arapaho/Roosevelt National Forests in Colorado and involves group selection harvesting, thinning, fuels reduction and removal of approximately 750-800 CCF of sawtimber across 320 acres. Additional requirements include road maintenance, snag and downed wood management. The purpose of the pre-bid meeting was to show contractors the project area and answer questions. The estimated start date is July 1, 2021 with all work to be completed by October 15, 2023. The contract will be awarded on a best value basis as a firm fixed price commercial services agreement.

View the file

Other files

File Type Posted
Amendment1_SF30.doc DOC document
Amendment1_AttachmentJ4_FinalContractMap.pdf PDF
DevilsCreekRFQ.docx DOCX document
AttachmentJ1_AppendixA.docx DOCX document
AttachmentJ5_SCA_WageDetermination_ForestryLandMgmt.pdf PDF
AttachmentJ4ContractMap.pdf PDF
AttachmentJ3_AppendixC.docx DOCX document
AttachmentJ2_AppendixB.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: 12363N21Q0003 Attachment J.6 Devil’s Creek Pre-Bid Meeting Notes 05/27/21 Prepared by Janna Osofsky Time: 0800-1115 Purpose: Pre-bid site visit meeting to show contractors project area and answer any questions related to the solicitation.

The following individuals were in attendance for the meeting.

Ron SchmelzerSummitt Forests, inc.summittforests@gmail.com
Janna OsofskyUSDA Forest Servicejanna.osofsky@usda.gov
Gabe HenryUSDA Forest Servicegabriel.henry@usda.gov

Group departed Canyon Lakes Ranger District parking lot for the field at 0810 and arrived at project site at 0940. Forest service personnel and the contractor walked into units 8,9, 10, and 92.

Reviewed contract specification regarding utilization and blowdown timber. Deteriorating or old blowdown that does not meet minimum utilization specifications is not required to be skidded to landing.

A question was asked: What amount of biomass may be lopped and scattered as incidental amounts?

Answer: Incidental amounts of biomass may be lopped and scattered when unable to meet minimum pile size (hand piles). See H.22 Slash Treatment specifications.

In general, this may be interpreted as less than 2 tons per acre when minimum pile size cannot be achieved.

Group departed project area at approximately 1115.